Lewis Tree Service, Inc. v. Lucent Technologies, Inc.

239 F. Supp. 2d 332, 2002 U.S. Dist. LEXIS 22398, 2002 WL 31619029
District Court, S.D. New York·Decided November 20, 2002·No. 99 Civ. 8556 (JGK)·Published·Cited by 12 cases

Opinion

OPINION AND ORDER

KOELTL, District Judge.

This is a purported class action brought by Lewis Tree Service, Inc. (“Lewis Tree”) and Ironman Magazine (“Ironman”) (collectively the “plaintiffs”) against AT & T Corporation (AT & T) and AT & T’s successor, Lucent Technologies, Inc. (“Lu-cent”) -(collectively the “defendants”) on behalf of purchasers of various telecommunications equipment sold by the defendants. The plaintiffs in their Third Amended Complaint (the “Complaint”), asserting that the products sold by the defendants were ‘Y2R. defective,” alleged six causes of actions, namely (1) statutory claims under the New Jersey Consumer Fraud Act (“NJCFA”) N.J.S.A. 56:8-1 et seq.; (2) breach of implied warranties of merchantability and fitness for a particular purpose; (3) breach of contract; (4) breach of express warranty; (5) fraud; and (6) breach of duty of good faith and fair dealing. This action was removed to this Court from New York state court pursuant to 15 U.S.C. § 6614(c)(1) (the “Y2K Act”).

The defendants now move to compel arbitration of the claims by the plaintiff Iron-man on the grounds that the agreement governing the purchase of telecommunications equipment between Ironman and AT & T requires that all grievances arising out of the agreement, if not resolved by non-binding mediation, be arbitrated. Ir-onman, in response, argues that its claims under the NJCFA cannot be arbitrated, because class action claims are not covered by agreements to arbitrate, and that the arbitration clause in the purchase agreement is unenforceable because the contract is a contract of adhesion.

I.

Pursuant to a Business Product Purchase Agreement (the “Purchase Agreement”) signed on March 15, 1996, Ironman purchased various telecommunications equipment, including a “Merlin Legend” *335 system, from AT & T for a total price of $91,351.28. (Purchase Agreement attached as Ex. A to Decl. of James Tyrrell (“Tyrell Decl.”) sworn to November 15, 2001.) This equipment, like much of the equipment sold by the defendants and other companies, was not programmed to be Y2K compliant. Consequently, on January 1, 2000 the equipment had the potential to experience technical glitches or malfunctions. In December, 1999 as part of the defendants’ attempts to make equipment it had sold Y2K compliant, Ironman was offered various options for correcting the flaws in the technology it had purchased. (See Dep. of Komla Ametu dated October 3, 2001 at 115-119 attached as Exh. Q to Plaintiffs’ Index of Exhibits.)

Under the Purchase Agreement’s “Terms and Conditions” provisions, all disputes related to the purchase from the defendants were subject to certain mediation and arbitration procedures. (Purchase Agreement ¶ 16.) It is the sales of these products and the Purchase Agreement’s arbitration provisions that are at the center of this motion to compel.

II.

The defendants’ motion to compel arbitration is governed by the Federal Arbitration Act (the “FAA”), pursuant to the explicit terms of the Purchase Agreement’s arbitration provision, which provides, in relevant part,

A. Any controversy or claim ... related directly or indirectly to this Agreement ... shall be resolved solely in accordance with the terms of this [section]. B. If [a dispute] cannot be settled by good faith negotiation between the parties, AT & T and [the purchaser] will submit the [d]ispute to non-binding mediation. If complete agreement cannot be reached within thirty (30) days of submission to mediation, any remaining issues will be resolved by binding arbitration ... The Federal Arbitration Act, 9 U.S.C. Sections 1 to 15, not state law, will govern the arbitrability of all [disputes.

(Purchase Agreement ¶ 16.) The parties agreed at oral argument that any question regarding the arbitrability of any particular dispute was governed by the FAA. 1

The FAA creates a “body of federal substantive law of arbitrability, applicable to any arbitration agreement within the coverage of the [FAA].” Moses H. Cone Mem’l Hosp. v. Mercury Constr. Corp., 460 U.S. 1, 24, 103 S.Ct. 927, 74 L.Ed.2d 765 (1983); see also Oldroyd v. Elmira Sav. Bank, FSB, 134 F.3d 72, 75 (2d Cir.1998). In accordance with the FAA, a district court may stay proceedings if it finds a valid arbitration agreement and may compel arbitration when a party does not abide by an arbitration agreement. See 9 U.S.C. § § 3 & 4; see also Aerotel, Ltd. v. RSL Comm., Ltd., 99 F.Supp.2d 368, 372 (S.D.N.Y.2000).

When considering a motion to compel arbitration under the FAA, a court must resolve four issues:

first, it must determine whether the parties agreed to arbitrate; second, it must determine the scope of that agreement; third, if federal statutory claims *336 are asserted, it must consider whether Congress intended those claims to be nonarbitrable; and fourth, if the court concludes that some, but not all, of the claims in the case are arbitrable, it must then decide whether to stay the balance of the proceedings pending arbitration.

Oldroyd, 134 F.3d at 75-76 (citing Genesco, Inc. v. T. Kakiuchi & Co., 815 F.2d 840, 844 (2d Cir.1987) (citation omitted)). “There is a strong federal policy favoring arbitration as an alternative means of dispute resolution.” Oldroyd, 134 F.3d at 76 (citation omitted); see also Hartford Accident and Indemnity Co. v. Swiss Reinsurance Am. Corp., 246 F.3d 219, 226 (2d Cir.2001). In accordance with that policy, courts should “construe arbitration clauses as broadly as possible,” Oldroyd, 134 F.3d at 76 (citation and quotation omitted), and “any doubts concerning the scope of arbi-trable issues should be resolved in favor of arbitration.” Moses H. Cone, 460 U.S. at 24-25, 103 S.Ct. 927; see also Hartford Accident and Indemnity, 246 F.3d at 226; Collins & Aikman Products Co. v. Bldg. Sys. Inc., 58 F.3d 16, 19 (2d Cir.1995).

The existence of a broad arbitration clause creates a presumption of arbi-trability which can be overcome only if it may be said “with positive assurance” that the arbitration clause is not susceptible to the interpretation that it covers the asserted dispute. Oldroyd, 134 F.3d at 76. The arbitration clause in this case that covers “any controversy or claim ... related directly or indirectly to this Agreement ...” is a broad arbitration clause.

Free access — add to your briefcase to read the full text and ask questions with AI

Lewis Tree Service, Inc. v. Lucent Technologies, Inc., 239 F. Supp. 2d 332, 2002 U.S. Dist. LEXIS 22398, 2002 WL 31619029 (S.D.N.Y. 2002).

239 F. Supp. 2d 332 (Lewis Tree Service, Inc. v. Lucent Technologies, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Katz v. Cellco Partnership
Second Circuit, 2015
In re Titanium Dioxide Antitrust Litigation
962 F. Supp. 2d 840 (D. Maryland, 2013)
NULIFE ENTERTAINMENT, INC. v. Torres
698 F. Supp. 2d 409 (S.D. New York, 2010)
Kuklachev v. Gelfman
600 F. Supp. 2d 437 (E.D. New York, 2009)
Kowalewski v. Samandarov
590 F. Supp. 2d 477 (S.D. New York, 2008)
Orange County Choppers, Inc. v. Goen Technologies Corp.
374 F. Supp. 2d 372 (S.D. New York, 2005)
Jlm Industries, Inc. v. Stolt-Nielsen Sa
387 F.3d 163 (Second Circuit, 2004)
Cason v. Conoco Pipeline Co.
280 F. Supp. 2d 1309 (N.D. Oklahoma, 2003)
In Re Currency Conversion Fee Antitrust Litigation
265 F. Supp. 2d 385 (S.D. New York, 2003)
Ranieri v. Bell Atlantic Mobile
304 A.D.2d 353 (Appellate Division of the Supreme Court of New York, 2003)