Lee v. Paragon Group Contractors, Inc.

337 S.E.2d 132, 78 N.C. App. 334, 1985 N.C. App. LEXIS 4306
CourtCourt of Appeals of North Carolina
DecidedDecember 17, 1985
Docket8518SC401
StatusPublished
Cited by27 cases

This text of 337 S.E.2d 132 (Lee v. Paragon Group Contractors, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lee v. Paragon Group Contractors, Inc., 337 S.E.2d 132, 78 N.C. App. 334, 1985 N.C. App. LEXIS 4306 (N.C. Ct. App. 1985).

Opinion

EAGLES, Judge.

By his sole assignment of error, defendant contends that the trial court erred in granting defendant’s motion to dismiss. We find no error.

*337 The test on a motion to dismiss for failure to state a claim upon which relief can be granted is whether the pleading is legally sufficient. [Citation omitted.] A complaint may be dismissed on motion filed under Rule 12(b)(6) if it is clearly without merit; such lack of merit may consist of an absence of law to support a claim of the sort made, absence of fact sufficient to make a good claim, or the disclosure of some fact which will necessarily defeat the claim. [Citation omitted.] For the purpose of a motion to dismiss, the allegations of the complaint are treated as true. [Citation omitted.]

Leasing Corp. v. Miller, 45 N.C. App. 400, 403-04, 263 S.E. 2d 313, 316, cert. denied, 300 N.C. 374, 267 S.E. 2d 685 (1980) (quoting Industries, Inc. v. Construction Co., 42 N.C. App. 259, 263-64, 257 S.E. 2d 50, 54 (1979)). Plaintiff asserts three alternative legal theories any one of which he contends could sustain the complaint.

a.

Plaintiff seeks to recover as a third-party beneficiary on the agreement entered into between Paragon and P & F on 3 March 1983. To establish a contract claim based on third-party beneficiary doctrine, the complaint’s allegations must show the existence of a valid and enforceable contract between two other persons and that the contract was entered into for the complainant’s direct and not incidental benefit. Leasing Corp. v. Miller, supra; Trust Co. v. Processing Co., 242 N.C. 370, 88 S.E. 2d 233 (1955).

Plaintiff argues that the 3 March 1983 agreement constitutes a new and distinct contract between Paragon and P & F or, alternatively, constitutes a modification of their existing agreement. Plaintiff can recover as a third-party beneficiary only if the contract or modification sued upon is valid and enforceable. An enforceable contract is one supported by consideration. Investment Properties v. Norburn, 281 N.C. 191, 188 S.E. 2d 342 (1972). Moreover, where a contract has been partially performed, as is the case here, a modification of its terms is treated as any other contract and must also be supported by consideration. Brenner v. School House, Ltd., 302 N.C. 207, 274 S.E. 2d 206 (1981), appeal after remand, 59 N.C. App. 68, 295 S.E. 2d 607 (1982), review denied, 307 N.C. 468, 299 S.E. 2d 220 (1983). It is well established that consideration sufficient to support a contract or a modifica *338 tion of its terms consists of “any benefit, right, or interest bestowed upon the promisor, or any forbearance, detriment, or loss undertaken by the promisee.” 302 N.C. at 215, 274 S.E. 2d at 212. Consideration is the “glue” that binds parties together, and a mere promise, without more, is unenforceable. In re Foreclosure of Owen, 62 N.C. App. 506, 509, 303 S.E. 2d 351, 353 (1983).

Under the contract entered into 11 November 1982 between Paragon and P & F, a copy of which plaintiff attached to his complaint, P & F was legally bound to provide to Paragon the painting and drywall work outlined in the contract. The agreement of 3 March 1983 does not expand or extend P & F’s existing obligation to Paragon. The 3 March 1983 agreement recites no new consideration given by P & F to Paragon and plaintiff has alleged none in his complaint. Generally, a promise to perform a preexisting contractual obligation is not adequate consideration in exchange for a new promise by the other party. Penn Compression Moulding, Inc. v. Mar-Bal, Inc., 73 N.C. App. 291, 326 S.E. 2d 280 (1985). Paragon, as promisor, received no benefit, right or interest as a result of the 3 March agreement. Conversely, P & F suffered no detriment or loss. P & F was bound by its contract with Paragon to perform drywall and painting work. It was to do that and nothing more. Without consideration the promise made by Paragon to P & F was not binding in law. Without a valid and enforceable contract or modification of its terms, plaintiff, as a matter of law, cannot recover as a third-party beneficiary.

b.

As a substitute for the want of consideration, plaintiff relies on the doctrine of promissory estoppel. Promissory estoppel has its roots in the nineteenth century as a generalized theory of recovery based on reliance, where gratuitous promises were first recognized as a basis for recovery. A. Farnsworth, Contracts Section 2.19 (1982). See J. Calamari & J. Perillo, The Law of Contracts Sections 6-1 to -7 (2d ed. 1977). While the first use of the term “promissory estoppel” is attributed to Williston, in Boyer, Promissory Estoppel: Requirements and Limitations of the Doctrine, 98 U. Pa. L. Rev. 459 (1950), in 1933 the American Law Institute promulgated Section 90 of the Restatement of Contracts defining detrimental reliance as a substitute for consideration. Although never denominated as the doctrine of “promissory *339 estoppel,” Section 90 became the Restatement’s most notable and influential rule. Farnsworth, supra. It states, in terms generally applicable to all promises, the following principle:

A promise which the promisor should reasonably expect to induce action or forbearance of a definite and substantial character on the part of the promisee and which does induce such action or forbearance is binding if injustice can be avoided only by enforcement of the promise. [Emphasis added.]

Restatement of Contracts Section 90 (1932).

As originally drafted, promissory estoppel was applied only to two-party situations. The Restatement required that the reliance be “on the part of the promisee.” However, this requirement was changed with the revision of Section 90 in the Restatement (Second) of Contracts adopted in 1979. The following version now appears as Section 90:

(1) A promise which the promisor should reasonably expect to induce action or forbearance on the part of the promisee or a third person and which does induce such action or forbearance is binding if injustice can be avoided only by enforcement of the promise. The remedy granted for breach may be limited as justice requires. [Emphasis added.]
(2) A charitable subscription or a marriage settlement is binding under Subsection (1) without proof that the promise induced action or forbearance.

Restatement (Second) of Contracts Section 90 (1979).

With the change of Section 90 to allow a third person, not the promisee, to assert promissory estoppel as a substitute for consideration the question becomes: Does the third party have the right to assert his own reliance to enforce a gratuitous promise made for his benefit? Since there was no consideration and consequently no contract created between promisor and promisee, the beneficiary’s rights are more tenuous than in cases where consideration passed from promisee to promisor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shepenyuk v. Abdelilah
Court of Appeals of North Carolina, 2023
McGUIRE v. LORD CORP.
2020 NCBC 11 (North Carolina Business Court, 2020)
Higgins v. Synergy Coverage Sols., LLC
2020 NCBC 4 (North Carolina Business Court, 2020)
Aym Techs., LLC v. Rodgers
2019 NCBC 63 (North Carolina Business Court, 2019)
Wm. T. Burnett Holding LLC v. Berg Bros. Co.
175 A.3d 876 (Court of Special Appeals of Maryland, 2017)
Abbington Spe, LLC v. U.S. Bank, Nat'l Ass'n
352 F. Supp. 3d 508 (E.D. North Carolina, 2016)
Tai Sports, Inc. v. Hall
2012 NCBC 62 (North Carolina Business Court, 2012)
NRC Golf Course, LLC v. JMR Golf, LLC
731 S.E.2d 474 (Court of Appeals of North Carolina, 2012)
Fairfield Harbour Property Owners Ass'n v. Midsouth Golf, LLC
715 S.E.2d 273 (Court of Appeals of North Carolina, 2011)
Elliott v. Enka-Candler Fire & Rescue Department, Inc.
713 S.E.2d 132 (Court of Appeals of North Carolina, 2011)
Berry v. WORLDWIDE LANGUAGE RESOURCES, INC.
716 F. Supp. 2d 34 (D. Maine, 2010)
Sonic Auto., Inc. v. Mercedes-Benz USA, LLC
2010 NCBC 10 (North Carolina Business Court, 2010)
Franco v. Liposcience, Inc.
676 S.E.2d 500 (Court of Appeals of North Carolina, 2009)
Inland Construction Co. v. Cameron Park II, Ltd.
640 S.E.2d 415 (Court of Appeals of North Carolina, 2007)
Watson Electrical Construction Co. v. Summit Companies, LLC
587 S.E.2d 87 (Court of Appeals of North Carolina, 2003)
Sessler v. Marsh
551 S.E.2d 160 (Court of Appeals of North Carolina, 2001)
Raritan River Steel Co. v. Cherry, Bekaert & Holland
398 S.E.2d 889 (Court of Appeals of North Carolina, 1990)
Labarre v. Duke University
393 S.E.2d 321 (Court of Appeals of North Carolina, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
337 S.E.2d 132, 78 N.C. App. 334, 1985 N.C. App. LEXIS 4306, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lee-v-paragon-group-contractors-inc-ncctapp-1985.