Krafcik v. USA Energy Consultants, Inc.

667 N.E.2d 1027, 107 Ohio App. 3d 59
CourtOhio Court of Appeals
DecidedOctober 30, 1995
DocketNo. 68692.
StatusPublished
Cited by36 cases

This text of 667 N.E.2d 1027 (Krafcik v. USA Energy Consultants, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Krafcik v. USA Energy Consultants, Inc., 667 N.E.2d 1027, 107 Ohio App. 3d 59 (Ohio Ct. App. 1995).

Opinion

*61 Per Curiam.

Defendant-appellant USA Energy Consultants, Inc. (“USA”) appeals from the trial court’s order denying a stay of proceedings pending arbitration of a contract dispute arising out of defendant’s installation of foam insulation in the home of plaintiffs-appellees John and Faye Krafcik. We find merit to the appeal and reverse for the reasons hereinafter stated.

This dispute arose from insulation work to be performed by defendant USA pursuant to a written contract with plaintiffs dated March 14,1994.

Upon commencing its work, USA discovered that the walls were defectively constructed in that the drywall was not affixed to the studs in a good and workmanlike fashion. USA notified plaintiffs that remedial work would have to be done before defendant could perform the insulation work. The contract between USA and plaintiffs expressly provided as follows:

“Any controversy or claim arising out of or relating to this contract or breach thereof shall be settled by arbitration in Cleveland, Ohio, in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association, and judgment upon the award rendered by the arbitrator(s) may be entered in any court having a jurisdiction thereof.”

Notwithstanding this provision, plaintiffs filed the instant suit against USA on August 12, 1994. Plaintiffs also named C.P. Chemical Company, the supplier of the insulation foam, as a co-defendant. Plaintiffs alleged that defendant had breached its contract for installation of foam insulation, that they had been fraudulently induced to enter into the contract, and that the insulation manufacturer had sold a defective and unreasonably dangerous product.

On September 7, 1994, defendant USA moved the trial court for a stay of proceedings pending arbitration pursuant to R.C. 2711.02 and for an order enforcing the arbitration agreement. On February 14, 1995, the trial court summarily denied the defendant’s motions without a hearing and this timely appeal ensued.

We will address defendant’s assignments of error in the order presented.

“I. The trial court erroneously denied defendant USA Energy Consultants, Inc.’s, motion to stay court proceedings pursuant to Ohio Rev.Code § 2711.02 where the parties were bound by a valid arbitration agreement.”

R.C. 2711.02 governs the action of the trial court and this court in the circumstances presented:

“If any action is brought upon any issue referable to arbitration under an agreement in writing for arbitration, the court in which the action is pending, *62 upon being satisfied that the issue involved in the action is referable to arbitration under an agreement in writing for arbitration, shall on application of one of the parties stay the trial of the action until the arbitration of the issue has been had in accordance with the agreement, provided the applicant for the stay is not in default in proceeding with arbitration. An order under this section that grants or denies a stay of a trial of any action pending arbitration, including, but not limited to, an order that is based upon a determination of the court that a party has waived arbitration under the arbitration agreement, is a final order and may be reviewed, affirmed, modified, or reversed on appeal pursuant to the Rules of Appellate Procedure and, to the extent not in conflict with those rules, Chapter 2505 of the Revised Code.”

The arbitration provision at issue is extremely broad and unlimited as to the nature of disputes that are subject to arbitration: “Any controversy or claim arising out of or related to the contract, or the breach thereof, shall be settled by arbitration * * *.” Such provisions are to be given a reading in favor of arbitration.

As recently stated in Didado v. Lamson & Sessions Co. (1992), 81 Ohio App.3d 302, 304, 610 N.E.2d 1085, 1086:

“A clause in a contract providing for dispute resolution by arbitration should not be denied effect unless it may be said with positive assurance that the subject arbitration clause is not susceptible to an interpretation that covers the asserted dispute. Independence Bank v. Erin Mechanical (1988), 49 Ohio App.3d 17, 550 N.E.2d 198; Gibbons-Grable Co. v. Gilbane Bldg. Co. (1986), 34 Ohio App.3d 170, 517 N.E.2d 559. In examining such a clause, a court must bear in mind the strong presumption in favor of arbitrability, and any doubts should be resolved in favor of coverage under the arbitration clause. Siam Feather & Forest Prod. Co., Inc. v. Midwest Feather Co. (S.D.Ohio 1980), 503 F.Supp. 239, affirmed (C.A.6, 1981), 663 F.2d 1073; Gibbons-Grable Co., supra; Independence Bank, supra.”

It cannot be said with “positive assurance” that the dispute over whether structural deficiencies impaired the defendant’s ability to perform the installation is a matter outside the scope of the broad arbitration clause. On the contrary, it seems clear that such a dispute is squarely within the scope of the agreement to arbitrate.

However, plaintiffs raise several arguments that require scrutiny. Plaintiffs contend that the agreement is invalid because of fraud in the inducement of the contract and that the arbitration clause is not binding because of the presence of a co-defendant (C.P. Chemical) who is not a party to the agreement. We do not find these arguments persuasive.

*63 “A claim that the contract containing the arbitration clause was induced by fraud does not defeat a motion to compel arbitration unless the claimant can demonstrate specifically that the arbitration clause itself was fraudulently induced.” Matter of Mgt. Recruiters Internatl., Inc. and Nebel (N.D.Ohio 1991), 765 F.Supp. 419, 420. The rationale supporting this rule is that a broad arbitration clause, such as the one at issue in the present case, necessarily requires that the question of fraud in the inducement of the contract itself be subject to arbitration. Prima Paint Corp. v. Flood & Conklin Mfg. Co. (1967), 388 U.S. 395, 87 S.Ct. 1801, 18 L.Ed.2d 1270. Thus, “in the face of a valid arbitration clause, questions regarding the validity of the entire contract must be decided in arbitration.” Weiss v. Voice/Fax Corp. (1994), 94 Ohio App.3d 309, 313, 640 N.E.2d 875, 878. See, also, Smith v. Snap-On-Tools Corp. (Jan. 6, 1993), Hamilton App. No. C-910902, unreported, 1993 WL 474091.

In Weiss,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barttile Recovery Solutions L.L.C. v. Cleavenger
2025 Ohio 4589 (Ohio Court of Appeals, 2025)
Epps v. State Farm Auto. Ins.
2022 Ohio 4084 (Ohio Court of Appeals, 2022)
Qualls v. Wright Patt Credit Union
2021 Ohio 2055 (Ohio Court of Appeals, 2021)
Sterling Contracting, L.L.C. v. Main Event Entertainment, L.P.
2020 Ohio 184 (Ohio Court of Appeals, 2020)
Zellner v. Prestige Gardens Rehab. & Nursing Ctr.
2019 Ohio 595 (Ohio Court of Appeals, 2019)
Younce v. Heartland
2016 Ohio 2965 (Ohio Court of Appeals, 2016)
Wolcott v. Summerville at Outlook Manor, L.L.C.
2016 Ohio 1237 (Ohio Court of Appeals, 2016)
Sultaana v. Drummond Fin. Servs., L.L.C.
2014 Ohio 938 (Ohio Court of Appeals, 2014)
Marquez v. Koch
2012 Ohio 5466 (Ohio Court of Appeals, 2012)
Gustavus, L.L.C. v. Eagle Invests.
2012 Ohio 1433 (Ohio Court of Appeals, 2012)
White v. Equity, Inc.
945 N.E.2d 536 (Ohio Court of Appeals, 2010)
Murray v. David Moore Builders, Inc.
893 N.E.2d 897 (Ohio Court of Appeals, 2008)
Taylor Building Corp. of America v. Benfield
884 N.E.2d 12 (Ohio Supreme Court, 2008)
Goodwin v. Ganley, Inc., Unpublished Decision (11-29-2007)
2007 Ohio 6327 (Ohio Court of Appeals, 2007)
Corporate Floors v. Harris Const., 88464 (5-31-2007)
2007 Ohio 2631 (Ohio Court of Appeals, 2007)
Coble v. Toyota of Bedford, Unpublished Decision (1-22-2004)
2004 Ohio 238 (Ohio Court of Appeals, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
667 N.E.2d 1027, 107 Ohio App. 3d 59, Counsel Stack Legal Research, https://law.counselstack.com/opinion/krafcik-v-usa-energy-consultants-inc-ohioctapp-1995.