Jones v. Unibilt Industries., Inc., Unpublished Decision (11-5-2004)

2004 Ohio 5983
CourtOhio Court of Appeals
DecidedNovember 5, 2004
DocketC.A. Case No. 20578.
StatusUnpublished
Cited by6 cases

This text of 2004 Ohio 5983 (Jones v. Unibilt Industries., Inc., Unpublished Decision (11-5-2004)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jones v. Unibilt Industries., Inc., Unpublished Decision (11-5-2004), 2004 Ohio 5983 (Ohio Ct. App. 2004).

Opinion

OPINION
{¶ 1} Roy E. Jones and Jeannie Jones appeal from the trial court's decision and entry sustaining a motion to stay litigation pending arbitration filed by appellee Blair Homes, Inc.

{¶ 2} The Joneses advance two assignments of error on appeal. First, they contend the trial court erred "in limiting the availability of damages by ordering arbitration pursuant to an adhesion contract." Second, they claim the trial court erred "in ordering arbitration pursuant to the terms of an adhesion contract which fails of the essential purpose for which arbitration is permitted under Ohio law."

{¶ 3} The record reflects that the Joneses entered into separate contracts with Unibilt Industries and Blair Homes for the construction of a modular home. Prior to taking possession of the home, the Joneses discovered "active growing mold" in the basement. On December 3, 2003, the Joneses filed a complaint alleging that Unibilt and Blair Homes have failed to remedy the problem and that the mold has rendered the home uninsurable and uninhabitable. The complaint appears to assert claims for breach of contract, breach of warranty, negligence, fraud, and a violation of the Ohio Consumer Sales Practices Act.

{¶ 4} On April 8, 2004, Blair Homes moved to stay litigation pending arbitration. In support of its motion, Blair Homes relied on the following language in paragraph twelve of its purchase contract with the Joneses:

{¶ 5} "ARBITRATION OF DISPUTES. Should any dispute arise between Homebuyers and Builder respecting the meaning of the plans or specifications, material or work done or omitted, the same shall be viewed by two qualified persons, one chosen each by Homebuyers and Builder, respectively; and if they are unable to agree on the disputed matters, these two persons shall name a third person as arbitrator, and the decision of two of such three persons shall be binding to both Homebuyers and Builder on the disputed matters; and, if they determine work or materials were not finished in good and workmanlike manner, they shall indicate the additional work or materials to be finished, and Builder shall complete the same within a reasonable time."

{¶ 6} In opposition to Blair Homes' motion, the Joneses argued that the arbitration clause did not apply to the claims at issue, that the clause was invalid because it did not provide for the "finality" of arbitration, that delaying litigation for arbitration would be improper because the other defendant, Unibilt Industries, was not a party to the contract between the Joneses and Blair Homes and was not bound by the arbitration clause, and that the trial court had the discretion to deny a stay. In one sentence of their memorandum in opposition, the Joneses also argued that "[t]he question of damages is not even included within paragraph 12 of the contract and therefore relief consistent with the Complaint could not possibly be awarded in arbitration."

{¶ 7} The trial court sustained Blair Homes' motion in a May 18, 2004, decision and entry. In rejecting the Joneses' first argument, the trial court observed that the arbitration clause covered "any dispute * * * respecting * * * work done or omitted[.]" The trial court found that the Joneses' claims fit within the scope of this language. As for the alleged lack of finality, the trial court noted that the arbitration clause made any decision "binding to both Homebuyers and Builder on the disputed matters[.]" The trial court also found it irrelevant that Unibilt Industries was not a party to the contract containing the arbitration clause at issue. Finally, the trial court rejected the Joneses' argument that the arbitration clause did not address the issue of damages. The trial court noted that the clause authorized the three decisionmakers to identify "additional work or materials to be done" and obligated Blair Homes to "complete the same within a reasonable time." The trial court reasoned that this language recognized the remedy of specific performance.

{¶ 8} Following the trial court's ruling, the Joneses filed a motion for reconsideration in which they argued that paragraph twelve was not an arbitration agreement because it merely provided for an "inspection" by qualified persons and did not require a quasi-judicial hearing before attorneys. They also argued that paragraph twelve contained an unenforceable limitation-on-remedies provision, namely the specific-performance language cited by the trial court. The Joneses also argued that the trial court was required to hold a hearing before ruling on Blair Homes' motion. The trial court summarily overruled the Joneses' motion for reconsideration, noting that its ruling on the motion to stay litigation was a final, appealable order. This timely appeal followed.

{¶ 9} In their first assignment of error, the Joneses assert that the trial court erred "in limiting the availability of damages by ordering arbitration pursuant to an adhesion contract." Although this wording suggests an argument that the arbitration agreement is an invalid contract of adhesion, the Joneses actually make no such argument. Rather, the sole argument under their first assignment of error is that the arbitration clause is invalid because it contains an unenforceable limitation-onremedies provision. To support this argument, the Joneses first assert that the trial court interpreted the arbitration clause as limiting their remedy to specific performance of the purchase contract. They then insist that such a limitation is invalid for two reasons: (1) the limitation is not sufficiently conspicuous in the parties' written contract and (2) specific performance is an inadequate remedy because Blair Homes' prior attempts to eliminate the mold have failed.

{¶ 10} Upon review, we reject the Joneses' argument that limitation-onremedies language in the arbitration clause renders the clause unenforceable. As an initial matter, the trial court did not hold that specific performance was the only remedy available under the arbitration clause. In their memorandum opposing Blair Homes' motion for a stay pending arbitration, the Joneses advanced a onesentence argument that "[t]he question of damages is not even included within paragraph 12 of the contract[.]" In response, the trial court merely pointed out that the arbitration clause in fact could be read as allowing the remedy of specific performance.

{¶ 11} While we agree that the arbitration clause contemplates specific performance as a possible remedy, we do not read the clause as limiting the Joneses to that remedy. In relevant part, the clause provides that when a dispute arises respecting work done or omitted, "the decision of two of such three [decisionmakers] shall be binding to both Homebuyers and Builder on the disputed matters; and, if they determine work or materials were not finished in good and workmanlike manner, they shall indicate the additional work or materials to be finished, and Builder shall complete the same within a reasonable time."

{¶ 12} In our view, the foregoing language is broad enough that it reasonably may be read as permitting the decision-makers to order a variety of remedies, including but not necessarily limited to recission, money damages, or specific performance. While the portion of the quoted language following the semi-colon addresses specific performance, the language preceding the semi-colon is susceptible to a broader interpretation allowing other remedies.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Younce v. Heartland
2016 Ohio 2965 (Ohio Court of Appeals, 2016)
Wolcott v. Summerville at Outlook Manor, L.L.C.
2016 Ohio 1237 (Ohio Court of Appeals, 2016)
Mill Harbour Condominium Owner's Ass'n v. Marshall
53 V.I. 581 (Supreme Court of The Virgin Islands, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
2004 Ohio 5983, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jones-v-unibilt-industries-inc-unpublished-decision-11-5-2004-ohioctapp-2004.