Murray v. David Moore Builders, Inc.

893 N.E.2d 897, 177 Ohio App. 3d 62, 2008 Ohio 2960
CourtOhio Court of Appeals
DecidedJune 18, 2008
DocketNo. 23821.
StatusPublished
Cited by19 cases

This text of 893 N.E.2d 897 (Murray v. David Moore Builders, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Murray v. David Moore Builders, Inc., 893 N.E.2d 897, 177 Ohio App. 3d 62, 2008 Ohio 2960 (Ohio Ct. App. 2008).

Opinion

Dickinson, Judge.

INTRODUCTION

{¶ 1} Timothy and Vicki Murray hired David Moore Builders, Inc. to build them a house. They signed a contract that included an arbitration clause. When the Murrays discovered defects in the house, they sued Moore as well as the architect. The architect was not a party to the builder’s contract and had not agreed to arbitrate disputes. After answering the complaint and asserting that a valid arbitration provision applied, Moore moved the trial court for a stay pending arbitration of the Murrays’ claims against it. The trial court denied the motion because “there are other parties and other claims involved that do not fall within the scope of this arbitration provision.” Moore has appealed, arguing that the presence of other claims and parties in the litigation does not defeat its right to compel arbitration under the contract. The Murrays have responded, arguing that disputes with third parties fall outside the scope of the arbitration clause and asserting various alternative grounds for affirming the trial court’s judgment. This court reverses the trial court’s decision denying the stay because the presence of nonarbitrable claims and third parties to the litigation does not deprive Moore of its right to arbitrate under the contract. This court has not reviewed the Murrays’ alternative arguments for affirmance of the trial court’s judgment because they attack the enforceability of the arbitration clause. The trial court has not yet ruled on the enforceability of the provision and resolution of some of the Murrays’ arguments may require factual findings. Therefore, this cause is reversed and remanded.

FACTS

{¶ 2} The Murrays entered into a contract with Moore for the construction of a home in Hudson, Ohio. They separately contracted with Clough & Associates for architectural services. According to the Murrays, after they had lived in the home for about a year, they discovered various structural defects. They sued Moore and its principal for breach of contract, breach of warranty, negligence, breach of implied warranty, and violations of the Magnuson-Moss Warranty Act and the Ohio Consumer Sales Practices Act. They also sued the architectural firm and its principal for breach of contract and malpractice.

{¶ 3} Moore asserted mandatory arbitration as a defense in its response to the Murrays’ complaint and moved the trial court, under R.C. 2711.01 and 2711.02 and Civ.R. 12, to dismiss or stay the proceeding pending arbitration of all claims. *65 Moore argued that the Murrays’ claims “all relate to and arise out of the performance of’ the contract between them and that the contract “requir[es] binding arbitration for ‘claims, disputes or other matters in question between the parties’ ” to the contract and “arising out of [the contract] or the breach thereof.” The Murrays responded with a variety of arguments attacking the applicability and enforceability of the arbitration provision.

{¶ 4} The trial court took the matter under advisement, and the case continued. The Murrays amended their complaint to include a prayer for rescission of the contract, and Moore’s insurer, Cincinnati Insurance Company, intervened in the proceedings. The trial court later denied Moore’s motion to stay the proceeding pending arbitration. In 2006, Moore appealed the denial of the stay. This court reversed the trial court’s decision because it had not specified why it had denied the requested stay. Murray v. David Moore Builders, Inc., 9th Dist. No. 23257, 2006-Ohio-6751, 2006 WL 3734294, at ¶ 11.

{¶ 5} On remand, the trial court again denied the stay, pointing out that only two of the four parties to the lawsuit were subject to the arbitration provision. The trial court held that “these are not disputes that must be arbitrated pursuant to the provision” because “there are other parties and other claims involved that do not fall within the scope of this arbitration provision.”

{¶ 6} Moore has again appealed, arguing that the language of the contract and R.C. 2711.02 require arbitration of the Murrays’ claims against it, regardless of the presence of other parties and claims. In response, the Murrays argue that disputes with third parties fall outside the scope of the arbitration clause and that there are various alternative grounds for affirming the trial court’s decision. See McKay v. Cutlip (1992), 80 Ohio App.3d 487, 491, 609 N.E.2d 1272. This court reverses the denial of the stay because the presence of nonarbitrable claims and third parties to the litigation does not deprive Moore of its right to arbitrate under the contract. As the trial court has not yet ruled on the enforceability of the arbitration clause, the cause is remanded for further proceedings.

SCOPE OF ARBITRATION PROVISION

{¶ 7} The primary question in this case is whether the Murrays’ claims against Moore are arbitrable. “The arbitrability of a claim is a question of law, and we review the arbitrability of a claim de novo.” McManus v. Eicher, 2d Dist. No. 2003-CA-30, 2003-Ohio-6669, 2003 WL 22927749, at ¶ 11, citing Gaffney v. Powell (1995), 107 Ohio App.3d 315, 319, 668 N.E.2d 951; Church v. Fleishour Homes, Inc., 172 Ohio App.3d 205, 2007-Ohio-1806, 874 N.E.2d 795, at ¶ 19; see also St. Marys v. Auglaize Cty. Bd. of Commrs., 115 Ohio St.3d 387, 2007-Ohio-5026, 875 N.E.2d 561, at ¶ 38 (“Contract interpretation is a matter of law, and questions of law are subject to de novo review on appeal”); Cohen ex rel. Estate *66 of Ginsburg v. PaineWebber, Inc. (Jan. 18, 2002), 1st Dist. No. C-010312, 2002 WL 63578, at *2.

{¶ 8} Ohio’s public policy favoring arbitration is codified at R.C. Chapter 2711. Under R.C. 2711.01(A), a written arbitration clause “shall be valid, irrevocable, and enforceable, except upon grounds that exist at law or in equity for the revocation of any contract.” If a party moves to stay proceedings pending arbitration, pursuant to “an agreement in writing for arbitration,” the court must first satisfy itself “that the issue involved in the action is referable to arbitration” under the agreement. R.C. 2711.02(B).

{¶ 9} In this case, there is no dispute that a written contract containing an arbitration clause governed the building of the Murrays’ house. The contract called for Moore to provide home construction services to the Murrays. It contained an arbitration provision including the following language:

In the event that any disputes arise between the parties as to the meaning or interpretations of any provisions of this agreement and the exhibits attached or if any disputes arise as to the proper performance of any part of the work in budding the house and the parties are unable between themselves to resolve such disputes, it is mutually agreed that the parties will submit said disputes for arbitration. Any such arbitration proceeding shall be completely binding on the parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Paradie v. Turning Point Builders, Inc.
2021 Ohio 2178 (Ohio Court of Appeals, 2021)
Mascher v. Basement Care, Inc.
2020 Ohio 3582 (Ohio Court of Appeals, 2020)
Zellner v. Prestige Gardens Rehab. & Nursing Ctr.
2019 Ohio 595 (Ohio Court of Appeals, 2019)
Jones v. Carrols, L.L.C.
2019 Ohio 211 (Ohio Court of Appeals, 2019)
Alford v. Arbors at Gallipolis
123 N.E.3d 305 (Court of Appeals of Ohio, Fourth District, Gallia County, 2018)
Vickers v. Canal Pointe Nursing Home & Rehab Ctr.
2016 Ohio 3244 (Ohio Court of Appeals, 2016)
Younce v. Heartland
2016 Ohio 2965 (Ohio Court of Appeals, 2016)
Raber v. Emeritus at Marietta
2016 Ohio 1531 (Ohio Court of Appeals, 2016)
Wolcott v. Summerville at Outlook Manor, L.L.C.
2016 Ohio 1237 (Ohio Court of Appeals, 2016)
Cline v. Stein
2015 Ohio 2979 (Ohio Court of Appeals, 2015)
Jarvis v. Lehr
2014 Ohio 3567 (Ohio Court of Appeals, 2014)
Maclin v. Greens Nursing & Assisted Living, L.L.C.
2014 Ohio 2538 (Ohio Court of Appeals, 2014)
Rippe & Kingston Co., PSC v. Kruse
2014 Ohio 2428 (Ohio Court of Appeals, 2014)
Varga v. Drees Co.
2014 Ohio 643 (Ohio Court of Appeals, 2014)
Marquez v. Koch
2012 Ohio 5466 (Ohio Court of Appeals, 2012)
VIS Sales, Inc. v. KeyBank, N.A.
2011 Ohio 1520 (Ohio Court of Appeals, 2011)
Duncan v. Wheeler
2010 Ohio 4836 (Ohio Court of Appeals, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
893 N.E.2d 897, 177 Ohio App. 3d 62, 2008 Ohio 2960, Counsel Stack Legal Research, https://law.counselstack.com/opinion/murray-v-david-moore-builders-inc-ohioctapp-2008.