George Ford Constr. v. Hissong, Unpublished Decision (3-1-2006)

2006 Ohio 919
CourtOhio Court of Appeals
DecidedMarch 1, 2006
DocketC.A. No. 22756.
StatusUnpublished
Cited by14 cases

This text of 2006 Ohio 919 (George Ford Constr. v. Hissong, Unpublished Decision (3-1-2006)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
George Ford Constr. v. Hissong, Unpublished Decision (3-1-2006), 2006 Ohio 919 (Ohio Ct. App. 2006).

Opinions

DECISION AND JOURNAL ENTRY
This cause was heard upon the record in the trial court. Each error assigned has been reviewed and the following disposition is made: {¶ 1} Appellants, Thomas Hissong, et al, appeals the decision of the Summit County Court of Common Pleas granting Appellee's (George Ford Construction, Inc.) motion to stay proceedings and compel arbitration. We affirm.

{¶ 2} Appellants and Appellee had entered into a contract in August of 2003 for the building of a new home. The contract included the following provision:

"Binding Arbitration: If [Appellants] and [Appellees] cannot reach an agreement with respect to any disputed items, upon written request to the Home Builders Association of greater Akron ("HBA") by either [Appellants] or [Appellees], the controversy or claim will be submitted to arbitration under the rules and procedures of the HBA. The arbitration shall be final and binding, and upon any such award rendered by the arbitration board may be entered in any Court having jurisdiction thereof."

{¶ 3} A dispute arose in the fall of 2004, which resulted in Appellee executing and filing an affidavit for a mechanics lien on November 12, 2004. On November 19, 2004, Appellee made a demand for arbitration upon Appellants, and also made and served a demand for arbitration on the Better Business Bureau of Akron, which conducts the arbitrations for HBA. By letter dated November 24, 2004, Appellants' attorney responded to Appellee: "Of course, my clients intend to honor the arbitration provision of the contract as it relates to George Ford Construction, Inc." The letter went on to state that Appellants' attorney intended to file an action against George Ford individually. Thereafter, the parties engaged in settlement negotiations and on November 30, 2004, reached a settlement agreement. Appellants failed to comply with the settlement agreement, and Appellee, on December 2, 2004, filed the underlying lawsuit. On December 8, 2004, Appellee filed a motion to stay proceedings and order arbitration.

{¶ 4} The trial court conducted a hearing on Appellee's motion on February 7, 2005, and by order dated May 31, 2005, granted Appellee's motion. Appellants now appeal, asserting four assignments of error for our review. To facilitate ease of discussion, we will consider some of the assignments of error together and out of order.

ASSIGNMENT OF ERROR I
"The trial court erred as a matter of law by failing to rule on the validity of the arbitration clause before submitting the case to arbitration."

ASSIGNMENT OF ERROR III
"The trial court erred as a matter of law by failing to determine the proper parties to the arbitration agreement as required under R.C. 2711.03(C)."

ASSIGNMENT OF ERROR IV
"The trial court erred as a matter of law by failing to allow the parties to conduct discovery prior to a hearing on the enforceability of the arbitration agreement."

{¶ 5} In their first, third and fourth assignments of error, Appellants argues that the trial court erred by staying the proceedings and compelling arbitration. Specifically, Appellants argue that the trial court erred by failing to rule on the validity of the arbitration clause, by failing to determine the proper parties to the arbitration agreement, and, finally, Appellants maintain that the trial court erred by failing to allow the parties to conduct discovery prior to a hearing on Appellee's motion to stay the proceedings and compel arbitration. Appellee argues that Appellants waived the above arguments by failing to properly raise them before the trial court. We affirm the decision of the trial court.

{¶ 6} As an initial matter, we note that a trial court's decision granting motions to stay proceedings and compel arbitration is reviewed under an abuse of discretion standard.Harsco Corp. v. Crane Carrier Co. (1997), 122 Ohio App.3d 406,410. Under an abuse of discretion standard of review, without a finding that the trial court acted unreasonably, arbitrarily or unconscionably, we will affirm the decision. Blakemore v.Blakemore (1983), 5 Ohio St.3d 217, 219. Questions of law, however, are reviewed under a de novo standard of review.

{¶ 7} Ohio public policy favors enforcement of arbitration provisions. Harrison v. Toyota Motor Sales, U.S.A., Inc., 9th Dist. No. 20815, 2002-Ohio-1642, at ¶ 9. If the subject of a dispute arguably falls within an arbitration provision, a presumption arises favoring arbitration. Id. "[U]nless it may be said with positive assurance that the subject arbitration clause is not susceptible to an interpretation that covers the asserted dispute[,]" a court should require arbitration per the contract.Neubrander v. Dean Witter Reynolds, Inc. (1992),81 Ohio App.3d 308, 311.

{¶ 8} Appellants' first assignment of error alleges that the trial court was required to, and erred by failing to, determine the validity of the agreement since they had raised a violation of the Consumer Sales Protection Act. Appellants do not cite to any case law in support of their argument that a trial court must make a specific finding that an arbitration clause is valid before compelling arbitration. In support of their argument, Appellants cite to Eagle v. Fred Martin Motor Co.,157 Ohio App.3d 150, 2004-Ohio-829. In Eagle, we noted that despite granting Appellee's motions to stay and compel arbitration, the trial court "did not make an explicit finding that the arbitration clause itself was either enforceable or conscionable." Eagle at ¶ 22. In that case we inferred from "fact that the court granted [Appellee's] motions to stay and compel, * * * [that] the trial court implicitly concluded that the arbitration clause [wa]s not unconscionable," and thus, was enforceable. Id.

{¶ 9} In this case, as in Eagle, the trial court did not specifically mention that the arbitration clause was enforceable and conscionable, however, we may infer that it implicitly made such a finding as it granted Appellee's motions to stay and compel discovery. Unlike the appellant in Eagle, Appellants did not specifically raise issues of unconscionability and enforceability before the trial court. The issue of unconscionability is a question of law. Bank One NA v.Borovitz, 9th Dist. No. 21042, 2002-Ohio-5544, at ¶ 12. However, since Appellants did not specifically raise the issue of unconscionability in the lower court, they waived their right to do so on appeal. Accordingly, we overrule Appellants' first assignment of error.

{¶ 10} In their third assignment of error, Appellants maintain that the trial court erred by failing to determine the proper parties to the arbitration agreement pursuant to the requirements of R.C. 2711.03. We disagree.

{¶ 11} Appellants' argument regarding the trial court's failure to determine the proper parties to the arbitration agreement revolves around their desire to add George Ford individually, as a party. This Court has previously held that R.C. 2711.03

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State ex rel. Lloyd v. Wiest
2023 Ohio 869 (Ohio Court of Appeals, 2023)
State v. Leyman
2016 Ohio 59 (Ohio Court of Appeals, 2016)
State v. Codeluppi
2012 Ohio 5812 (Ohio Court of Appeals, 2012)
Wayne Cty. Sheriff v. Ohio Patrolmen's Benevolent Assn.
2011 Ohio 2707 (Ohio Court of Appeals, 2011)
Ward v. Summa Health System
920 N.E.2d 421 (Ohio Court of Appeals, 2009)
Discover Bank v. Cummings, 08ca009453 (4-13-2009)
2009 Ohio 1711 (Ohio Court of Appeals, 2009)
Strickler v. First Ohio Banc Lending, 08ca009416 (3-30-2009)
2009 Ohio 1422 (Ohio Court of Appeals, 2009)
Ault v. Parkview Homes, 24375 (2-11-2009)
2009 Ohio 586 (Ohio Court of Appeals, 2009)
Pesic v. Pezo, 90855 (11-6-2008)
2008 Ohio 5738 (Ohio Court of Appeals, 2008)
Murray v. David Moore Builders, Inc.
893 N.E.2d 897 (Ohio Court of Appeals, 2008)
First Resolution Invest. Corp. v. Salem, 24049 (5-28-2008)
2008 Ohio 2527 (Ohio Court of Appeals, 2008)
Tomovich v. USA Waterproofing, Unpublished Decision (11-26-2007)
2007 Ohio 6214 (Ohio Court of Appeals, 2007)
Brunke v. Ohio State Home Servs., Inc., 06ca008947 (6-25-2007)
2007 Ohio 3119 (Ohio Court of Appeals, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
2006 Ohio 919, Counsel Stack Legal Research, https://law.counselstack.com/opinion/george-ford-constr-v-hissong-unpublished-decision-3-1-2006-ohioctapp-2006.