Keppel v. BaRoss Builders, Inc.

509 A.2d 51, 7 Conn. App. 435, 1986 Conn. App. LEXIS 980
CourtConnecticut Appellate Court
DecidedMay 20, 1986
Docket3564
StatusPublished
Cited by24 cases

This text of 509 A.2d 51 (Keppel v. BaRoss Builders, Inc.) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Keppel v. BaRoss Builders, Inc., 509 A.2d 51, 7 Conn. App. 435, 1986 Conn. App. LEXIS 980 (Colo. Ct. App. 1986).

Opinion

Hull, J.

The defendant, BaRoss Builders, Inc., appeals from the judgment which a state trial referee, exercising the powers of the Superior Court, rendered in favor of the plaintiffs, Henry E. Keppel, Jr., and Marilyn L. Keppel, on their suit against the defendant based on claimed deficiencies in its construction of a residence for them. The plaintiffs’ amended complaint was in four counts: breach of contract; failure to complete work contracted for, and completion of some of the work in an unworkmanlike manner; negligent performance of services; and breach of implied warranties under General Statutes § 47-118. The defendant filed three special defenses essentially claiming that it tried to make some of the repairs and complete certain work, but that it was refused entry into the plaintiffs’ house to do so. The court found for the plaintiffs on the first, second and fourth counts. It awarded $28,000 to raise the house as required to remedy one of the deficiencies, $3393 for miscellaneous repairs, and $11,890 in interest, for a total judgment of $43,283. We find no error.

The defendant claims two errors: (1) that the trial court incorrectly measured the amount of damages, and improperly awarded interest at 8 percent per year from the return date, November 20,1979, to the date of judgment; and (2) that the state trial referee, Hon. Philip R. Pastore, improperly declined to disqualify himself from hearing the case even though he had previously heard the plaintiffs’ demand and the defendant’s offer, and had previously stated that the defendant’s president was playing fast and loose with the court.

[437]*437The trial court found the following facts. Under a sales agreement dated October 6,1978, the defendant, owner of a parcel of land, agreed to build a house on the lot for the plaintiffs according to certain specifications. The total cost was to be $123,800. The height of the basement should have been seven feet eight inches, as reflected in the building permit the defendant obtained, but instead it varied from six feet eight to six feet nine inches. The greater height was required by the building code if the basement was to be used as a living space. The defendant had reason to know that the plaintiffs intended to so use it. The specifications called for a walk-out glass sliding door and other construction features were consistent with such a use of the basement. The plaintiffs did not become aware of the deficiency in the height of the basement until after taking title. To make the basement height seven feet eight inches would require either the lowering of the basement floor, or the raising of the house. There was expert testimony disapproving the lowering of the floor for reasons including water and construction conditions, and recommending instead the raising of the house to obtain the requisite basement height.

The defendant first claims that the trial court erred in awarding $28,000 for raising the house rather than adopting the cheaper remedy of lowering the floor. By so doing, it is in essence asking us to retry the facts. This we cannot do. Jones v. Litchfield, 1 Conn. App. 40, 42, 467 A.2d 936 (1983), cert. denied, 192 Conn. 802, 470 A.2d 1218 (1984).

The defendant next claims that because its expert testified that $1500 to $2000 represented the reasonable cost of lowering the floor, the court’s award of $28,000 to raise the house constituted unreasonable economic waste. “ ‘As a general rule, in awarding damages upon a breach of contract, the prevailing party is entitled to compensation which will place him in the [438]*438same position he would have been in had the contract been properly performed. Bertozzi v. McCarthy, 164 Conn. 463, 468, 323 A.2d 553 [1973]; Sabo v. Strolis, 148 Conn. 504, 506, 172 A.2d 609 [1961]. Such damages are measured as of the date of the breach. Bachman v. Fortuna, 145 Conn. 191, 194, 141 A.2d 477 [1958]; Lee v. Harris, 85 Conn. 212, 214, 82 A. 186 [1912]; 22 Am. Jur. 2d, Damages § 52. For a breach of a construction contract involving defective or unfinished construction, damages are measured by computing either “(i) the reasonable cost of construction and completion in accordance with the contract, if this is possible and does not involve unreasonable economic waste; or (ii) the difference between the value that the product contracted for would have had and the value of the performance that has been received by the plaintiff, if construction and completion in accordance with the contract would involve unreasonable economic waste.” Restatement, 1 Contracts § 346 (1) (a), p. 573; see annot., 76 A.L.R.2d 805, 812 § 4.’ Levesque v.D & M Builders, Inc., 170 Conn. 177, 180-81, 365 A.2d 1216 (1976).” Barnicoat v. Edwards, 1 Conn. App. 652, 654-55, 474 A.2d 808 (1984).

The trial court, in its memorandum of decision, made clear that it was using the reasonable cost of construction and completion in accordance with the contract as the measure of damages. It made no finding, however, as to whether completion of the contract would involve unreasonable economic waste. The defendant did not seek, pursuant to Practice Book § 3082, to have the court articulate its decision in this regard. It is the appellant’s burden to furnish us with an adequate appellate record on which to review the basis of the decision of the trial court. Since the defendant failed to meet this burden, we have no basis on which to find error. Pointina Beach Assn., Inc. v. Stella, 1 Conn. App. 341, 343, 471 A.2d 970 (1984).

[439]*439The defendant also claims error in the trial court’s allowance of interest as an element of damages. This determination is primarily an equitable one. It was, additionally, a matter lying within the discretion of the trial court. Bertozzi v. McCarthy, 164 Conn. 463, 467, 323 A.2d 553 (1973). The defendant does not claim that the court could not award interest on equitable considerations or that its doing so was an abuse of discretion. Rather, it claims that the amount of interest awarded was inequitable because the award of damages for raising the house was improperly measured. This claim of error falls along with the claim on which it depends.

The defendant’s final claim of error is based on the state trial referee’s refusal to disqualify himself after hearing the plaintiffs’ demand and the defendant’s offer, and after stating that the defendant’s president was playing fast and loose with the court. During a hearing on January 15, 1984, counsel for the plaintiffs read into the record that the defendant would transfer to the plaintiffs an attached lot in full satisfaction of the plaintiffs’ claims. Three conditions were attached to this agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State of Washington v. Paul Scott Bickle
Court of Appeals of Washington, 2014
In Re Nathan B.
977 A.2d 224 (Connecticut Appellate Court, 2009)
State v. Herbert
913 A.2d 443 (Connecticut Appellate Court, 2007)
City of New Haven v. Tuchmann
890 A.2d 664 (Connecticut Appellate Court, 2006)
State v. William B.
822 A.2d 265 (Connecticut Appellate Court, 2003)
Overhead Door Co. v. Chere Arch., No. Cv97-014 24 05 S (Mar. 26, 2001)
2001 Conn. Super. Ct. 4664 (Connecticut Superior Court, 2001)
Overhead Door Co. v. Chere Architects, No. Cv97-014 24 05 S (Mar. 8, 2001)
2001 Conn. Super. Ct. 3165 (Connecticut Superior Court, 2001)
Joyner v. Commissioner of Correction
740 A.2d 424 (Connecticut Appellate Court, 1999)
Pelletier v. Pelletier Development Co., No. Cv 94-0463671s (Mar. 14, 1996)
1996 Conn. Super. Ct. 2709 (Connecticut Superior Court, 1996)
Rubin v. Rubin, No. Fa85-064742s (Feb. 18, 1996)
1996 Conn. Super. Ct. 1331-GGG (Connecticut Superior Court, 1996)
Ferris v. Clark, No. Cv93 0133021 S (May 10, 1995)
1995 Conn. Super. Ct. 4957 (Connecticut Superior Court, 1995)
Hovedskou v. Zuccaro, No. Cv 91-0055316s (Nov. 13, 1992)
1992 Conn. Super. Ct. 10142 (Connecticut Superior Court, 1992)
Pergament v. Green, No. Cv86 0084907 S (Jun. 12, 1992)
1992 Conn. Super. Ct. 5875 (Connecticut Superior Court, 1992)
Cahn v. Cahn
603 A.2d 759 (Connecticut Appellate Court, 1992)
Amendola v. Giammattei, No. Cv87-0260230 (Jun. 27, 1991)
1991 Conn. Super. Ct. 5248 (Connecticut Superior Court, 1991)
Ryals v. Pigott
580 So. 2d 1140 (Mississippi Supreme Court, 1990)
DeMatteo v. DeMatteo
575 A.2d 243 (Connecticut Appellate Court, 1990)
DiLieto v. Better Homes Insulation Co.
546 A.2d 957 (Connecticut Appellate Court, 1988)
Barca v. Barca
546 A.2d 887 (Connecticut Appellate Court, 1988)
Katz Realty, Inc. v. Norwalk Fabricators, Inc.
541 A.2d 519 (Connecticut Appellate Court, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
509 A.2d 51, 7 Conn. App. 435, 1986 Conn. App. LEXIS 980, Counsel Stack Legal Research, https://law.counselstack.com/opinion/keppel-v-baross-builders-inc-connappct-1986.