DiLieto v. Better Homes Insulation Co.

546 A.2d 957, 16 Conn. App. 100, 1988 Conn. App. LEXIS 338
Connecticut Appellate Court·Decided September 6, 1988·No. 5326·Published·Cited by 9 cases

Opinion

Bieluch, J.

The defendant appeals from the judgment rendered in favor of the plaintiffs in this breach of contract action. The defendant claims that the trial court erred (1) in failing to give effect to the damage limitation provision of the contract between the parties, (2) in assessing damages to the plaintiffs in the amount of $15,000, (3) in improperly limiting the scope of defense counsel’s examination in relation to the defendant’s counterclaim, and (4) in belittling defense counsel and making comments which cast aspersions on the defendant’s counterclaim. We find no error.

The facts relevant to this appeal are as follows. On December 26, 1984, the plaintiffs, Robert T. DiLieto and Michelle DiLieto, entered into a written contract with the defendant, Better Homes Insulation Company, Inc., wherein the defendant agreed to remodel, in a workmanlike manner, the kitchen and porch of the plaintiffs’ residence in New Haven. The contract price of $5748.80 was paid by the plaintiffs to the defendant prior to the commencement of the work.

The plaintiffs discovered serious problems with the manner in which the work was being done, as well as with the quality of the work itself, soon after the remodeling began in early January, 1985. A series of meetings was held between the plaintiffs and the defendant’s representatives in an attempt to resolve [102]*102these problems. When the defendant’s representatives finally refused to acknowledge the validity of the plaintiffs’ complaints and terminated the meetings, this breach of contract action was commenced. The plaintiffs claimed that the defendant had performed the work in such an unworkmanlike manner as to cause the finished work to be substandard and totally unacceptable, requiring total reconstruction. In its answer, the defendant denied the plaintiffs’ claims and, by way of counterclaim, sought money damages for extra work it had allegedly completed.

After a trial, the court found that the “credible evidence clearly sustained the plaintiffs’ claim[s],”1 and that the defendant “totally failed to sustain its burden of proof” on the counterclaim. The court further found that the plaintiffs had “introduced ample and credible evidence as to the cost of correcting the substandard work,” and accordingly awarded the plaintiffs damages in the amount of $15,000. This appeal followed.

The defendant’s first claim is that the trial court erred in failing to give effect to the damage limitation provision of the contract between the parties.2 The defendant states that the plaintiffs introduced into evidence the entire contract, and maintains that although there may be a range of interpretation of the damage limi[103]*103tation provision, the court was not free to ignore it entirely.

The defendant’s argument with regard to this issue is predicated on its initial assumption that the court entirely ignored the contract’s damage limitation provision. The fatal flaw in the defendant’s claim is that no such assumption necessarily flows from the court’s failure to specify its finding on this issue in its memorandum of decision. Furthermore, it was the defendant’s burden to seek an articulation of the court’s finding with regard to the provision in question where the court’s memorandum was silent on that point. See Practice Book § 4051; Spera v. Audiotape Corporation, 1 Conn. App. 629, 632, 474 A.2d 481 (1984).

“ ‘Where the factual basis of the court’s decision is unclear, “proper utilization of the motion for articulation serves to dispel any such ambiguity by clarifying the factual and legal basis upon which the trial court rendered its decision, thereby sharpening the issues on appeal. ‘It remains the appellant’s responsibility to secure an adequate appellate record, and under normal circumstances we will not remand a case to correct a deficiency the appellant should have remedied.’ ” Barnes v. Barnes, 190 Conn. 491, 494, 460 A.2d 1302 (1983). “Since the [defendant] has failed to supply a record presenting the trial court’s rationale, as is [its] burden, we are disinclined to view as clearly erroneous the trial court’s determination .... Nor under these circumstances will we remand the decision for articulation.” Steve Viglione Sheet Metal Co. v. Sakonchick, 190 Conn. 707, 714, 462 A.2d 1037 (1983).’ Pointina Beach Assn., Inc. v. Stella, 1 Conn. App. 341, 343, 471 A.2d 970 (1984).” Stroiney v. Crescent Lake Tax District, 205 Conn. 290, 295-96, 533 A.2d 208 (1987).

An articulation of the trial court’s decision is particularly important in an appeal involving the construe[104]*104tion of a contract. Our review of the trial court’s conclusions in such a case is limited under Practice Book § 4061 to determining whether those conclusions are clearly erroneous. Roban Realty, Inc. v. Faile, 13 Conn. App. 584, 588, 538 A.2d 242 (1988); Lavigne v. Lavigne, 3 Conn. App. 423, 427-28, 488 A.2d 1290 (1985). A trial court’s construction of a written agreement is an issue of fact subject to this limited standard of appellate review. Roban Realty, Inc. v. Faile, supra; Sweeny v. Sweeny, 9 Conn. App. 498, 501, 519 A.2d 1237 (1987); Lavigne v. Lavigne, supra.

Because the defendant failed to meet its burden of providing this court with an adequate record to review its claim that the trial court did not consider the damage limitation provision in construing the contract between the parties, we cannot say that the court’s decision was clearly erroneous. We further decline to remand the court’s decision for articulation where the defendant should have remedied this deficiency. Barnes v. Barnes, supra; Carpenter v. Carpenter, 188 Conn. 736, 739 n.2, 453 A.2d 1151 (1982).

The defendant next claims that the trial court erred in assessing the plaintiffs’ damages in the amount of $15,000. Specifically, the defendant maintains that the court erroneously found for the plaintiffs on certain elements of damage which had not been pleaded and which were therefore not issues before the court. The defendant argues that the consideration by the court, in reaching its judgment, of evidence pertaining to the kitchen-dining room ceiling, a back door, soffits, kitchen countertop height, and trim and tile work constituted error in that such evidence materially varied from the pleadings.

This issue is not properly before this court. The record reveals, and the defendant concedes, that evidence as to the elements of damages now contested on appeal [105]*105was admitted at trial without objection. In fact, the record shows that the defendant cross-examined several witnesses on the issues relating to this evidence. The defendant’s failure to object below constituted a waiver of any variance between the pleadings and the proof.

Free access — add to your briefcase to read the full text and ask questions with AI

DiLieto v. Better Homes Insulation Co., 546 A.2d 957, 16 Conn. App. 100, 1988 Conn. App. LEXIS 338 (Colo. Ct. App. 1988).

546 A.2d 957 (DiLieto v. Better Homes Insulation Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Weinstein v. Weinstein
882 A.2d 53 (Supreme Court of Connecticut, 2005)
Giametti v. Inspections, Inc.
824 A.2d 1 (Connecticut Appellate Court, 2003)
Lyons v. Nichols
778 A.2d 246 (Connecticut Appellate Court, 2001)
Allstate Insurance Company v. Legendre, No. Cv93 004 1985 (Jul. 19, 1994)
1994 Conn. Super. Ct. 6850-H (Connecticut Superior Court, 1994)
A. V. Giordano Co. v. American Diamond Exchange, Inc.
623 A.2d 1048 (Connecticut Appellate Court, 1993)
Cole v. Planning & Zoning Commission
620 A.2d 1324 (Connecticut Appellate Court, 1993)
Besade v. Interstate Security Services
562 A.2d 1086 (Supreme Court of Connecticut, 1989)
Lerner v. Ceslik
553 A.2d 1142 (Connecticut Appellate Court, 1989)
D'Agostino v. Amendola
550 A.2d 1103 (Connecticut Appellate Court, 1988)