Pelletier v. Pelletier Development Co., No. Cv 94-0463671s (Mar. 14, 1996)

1996 Conn. Super. Ct. 2709
Connecticut Superior Court·Decided March 14, 1996·No. No. CV 94-0463671S·Unpublished

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION I. Background

Plaintiffs Gary J. Pelletier and Louise J. Pelletier have CT Page 2710 brought this action against the Defendants Joseph R. Pelletier, Jr. and Christopher A. Pelletier, doing business as Pelletier Development Company ("PDC")1 an unincorporated company, to recover damages for defects to the new home constructed for them by the Defendants. The complaint is in five counts, alleging breach of express and implied warranties under the New Home Warranties Act, General Statutes § 47-116, et seq., breach of contract and violation of the Connecticut Unfair Trade Practices Act ("CUTPA"), General Statutes § 42-110a, et seq. The Defendants have counterclaimed for sums allegedly owed. Both parties have filed numerous special defenses, essentially alleging a denial of liability and placement of blame on the other.

In addition, the Defendants brought a libel action against the Plaintiffs. That action was consolidated for trial with Plaintiffs' lawsuit. The Defendants withdrew their libel action at the close of the evidentiary portion of the Plaintiffs' lawsuit.

Trial covered 13 trial days from November 8, 1995 to December 15, 1995. Post-trial briefs were due by January 12, 1996, and reply briefs by January 26, 1996. Supplemental briefs, limited to the issue of whether the Plaintiffs qualify as a "purchaser" as defined in § 47-116 of the New Home Warranty Act, were due by February 16, 1996.

Plaintiffs presented as witnesses: the Plaintiffs Gary J. Pelletier and his wife Louise J. Pelletier, the testimony of Gary J. Pelletier consuming the better part of four trial days; Frank Borawski, a structural civil engineer; J. P. Langlois, the Rocky Hill Building Inspector; Patrick Aglieco, a general contractor; and Joseph A. Borcynski, a local real estate appraiser. Defendants presented as witnesses: the Defendant Joseph R. Pelletier, Jr.; James D. Buckley, a general contractor; and James Sakonchick, a professional engineer and land surveyor. The parties entered numerous exhibits.

The premises are now known as No. 97 Fox Hill Drive, Rocky Hill. The building lot upon which the subject home was later constructed was purchased unimproved in February 1992 by the Plaintiffs from a bank in the process of liquidating a subdivision. The lot fronts on the crown of a hill, and slopes significantly to the side and rear. There is a 20 to 25 per cent slope from front to rear, amounting to a drop of approximately 22 CT Page 2711 degrees. Plaintiffs' witness J. P. Langlois described the lot as a "tough site." Plaintiffs' first application for a building permit was denied because the proposed grading was "too steep." Defendants' Exhibit N-1.

The Plaintiffs purchased a set of "canned" house plans through the mail from a company in Idaho. The Plaintiff Gary J. Pelletier,2 who had some mechanical engineering and design background, adapted the plans to the site. The plans consist of nine sheets. Plaintiffs' Exhibit 2A. With the assistance of an engineer friend, the Plaintiff had prepared the topographical or "A-2" survey required for construction purposes. Plaintiffs' Exhibit 2B. This survey and the elevations and contours depicted thereon apparently were not field verified, but were based upon relevant maps and surveys on file at the Rocky Hill town offices.

The Plaintiffs met the Defendants at a trade show in the Spring of 1992. The Defendant brothers had started their company in 1989. Their business involved construction of single family custom homes of 2,000 to 3,500 square feet on the customer's land, as well as some renovation, additions and rehab work.

The parties entered into a contract, dated June 22, 1992, for construction of the home in accordance with the foregoing plans. The contract was prepared by the Defendants and set a total contract price with allowances of $193,050.00.3 Certain specialties were not part of Defendants' work. For example, electrical was performed by the Plaintiff, and plumbing and HVAC were separately contracted for by Plaintiffs with other contractors.

Permits, engineering and surveying were the responsibility of the Plaintiffs. The Plaintiffs' revised building permit application had been approved on May 18, 1992. Defendants' Exhibit M. The contract further provided that the Defendants were "to provide structural engineering for foundation due to unusually extreme site conditions." The plans therefor were subsequently prepared by Joseph Sakonchick, an engineer selected by the Defendants, and form part of the contract. Plaintiffs' Exhibit 2C.

Defendants commenced work in late September 1992. Their scheduled start two months earlier was aborted because the Plaintiffs had insufficient fill on site. Plaintiffs had been obtaining fill gratis from the MDC. During construction the CT Page 2712 relationship of the parties had its ups and downs, but not to the extent where either party defaulted the other. The Plaintiff was constantly on site, and videotaped construction progress. His videotape, with audio added, was entered into evidence. Plaintiffs' Exhibit 33.

By May 1993, Defendants' work was substantially completed, to the point where Plaintiffs apparently were preparing to convert their construction financing to a permanent mortgage. The relationship then broke down. First, Plaintiffs had unilaterally withheld one-half of a $48,000.00 payment due Defendants under the contract. Although that issue had been temporarily resolved by a modified payment schedule, Plaintiffs' Exhibit 10, the controversy was such that Defendants ceased work on May 17, 1993.

Under date of May 20, 1993, Plaintiffs sent Defendants a six-page memo of claimed punch list items and claimed contract price adjustments. Plaintiffs' Exhibit 8. On May 27, 1993, Defendants executed and filed a mechanics lien in the amount of $40,336.67. On May 28, 1993, the parties and their attorneys met at the office of Plaintiffs' attorneys. Plaintiffs produced a four-page document setting forth their then claimed construction deficiencies, essentially punch list items, Plaintiffs' Exhibit 14, and Defendants produced a four-page document, Plaintiffs' Exhibit 20, in support of their lien claims.

At that settlement meeting the parties agreed in part as follows: (1) Plaintiffs would pay PDC $17,141.25; (2) the mechanics' lien would be released and a Lien Waiver document would be delivered; and (3) Defendants would deliver to the residence, but not install, a previously ordered carpet for the second floor. However, Plaintiffs refused to accept the carpet when delivered on the ground that it was the wrong color, and by deducting the $2,163.00 cost therefor, paid PDC only $14,978.25. The issue of this carpet is the basis of Defendants' counterclaim.

The settlement was not documented by a signed agreement, nor did the parties exchange releases. Accordingly, each offers a different version of what was agreed concerning the scope of Defendants' obligation, if any, for future corrective work. Defendants contend that the settlement negated any further obligation on their part excepting only for "major catastrophic defects." The Plaintiffs concede that the settlement obviated any further obligation of the Defendants for the items listed on CT Page 2713 Plaintiffs' Exhibits 8 and 14 punch lists, but that Defendants were not released from any defects or issues that might subsequently arise.

The Court finds that the disagreement is one of semantics rather than of substance.

Free access — add to your briefcase to read the full text and ask questions with AI

Pelletier v. Pelletier Development Co., No. Cv 94-0463671s (Mar. 14, 1996), 1996 Conn. Super. Ct. 2709 (Colo. Ct. App. 1996).

1996 Conn. Super. Ct. 2709 (Pelletier v. Pelletier Development Co., No. Cv 94-0463671s (Mar. 14, 1996)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Lar-Rob Bus Corp. v. Town of Fairfield
365 A.2d 1086 (Supreme Court of Connecticut, 1976)
Levesque v. D & M BUILDERS, INC.
365 A.2d 1216 (Supreme Court of Connecticut, 1976)
Beckman v. JALICH HOMES, INC.
460 A.2d 488 (Supreme Court of Connecticut, 1983)
State v. Grant
404 A.2d 873 (Supreme Court of Connecticut, 1978)
Barnicoat v. Edwards
474 A.2d 808 (Connecticut Appellate Court, 1984)
Fava v. Arrigoni
402 A.2d 356 (Connecticut Superior Court, 1979)
Frank Towers Corp. v. Laviana
97 A.2d 567 (Supreme Court of Connecticut, 1953)
City of Groton v. Yankee Gas Services Co.
620 A.2d 771 (Supreme Court of Connecticut, 1993)
Tessmann v. Tiger Lee Construction Co.
634 A.2d 870 (Supreme Court of Connecticut, 1993)
Elliot v. Sears, Roebuck & Co.
642 A.2d 709 (Supreme Court of Connecticut, 1994)
Concept Associates, Ltd. v. Board of Tax Review
642 A.2d 1186 (Supreme Court of Connecticut, 1994)
Keppel v. BaRoss Builders, Inc.
509 A.2d 51 (Connecticut Appellate Court, 1986)
Krawiec v. Blake Manor Development Corp.
602 A.2d 1062 (Connecticut Appellate Court, 1992)