Kanzius v. Jenkins

157 P. 417, 98 Kan. 94, 1916 Kan. LEXIS 23
CourtSupreme Court of Kansas
DecidedMay 6, 1916
DocketNo. 20,167
StatusPublished
Cited by10 cases

This text of 157 P. 417 (Kanzius v. Jenkins) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kanzius v. Jenkins, 157 P. 417, 98 Kan. 94, 1916 Kan. LEXIS 23 (kan 1916).

Opinion

The opinion of the court was delivered by

Johnston, C. J.:

The board of county commissioners of Barton county contracted with the Jenkins Construction Company, composed of E. N. Jenkins and George E. Sheldon, to build and repair seven bridges which had been destroyed or injured by the floods of 1912. The construction company furnished a bond for the faithful performance of the contract, signed by the Western Casualty & Guaranty Insurance Company as surety. The construction company failed to carry out its contract, and persons who furnished labor and materials to the construction company brought six separate suits against the construction company and its surety. . As some money was still due to the construction company for work done upon the completed bridges, the board was made a defendant in each of the suits. For the purposes of the trial, all the cases were consolidated and’ tried as a single action without a jury. The court made findings of the amount; due to each plaintiff, and gave judgment for the amounts against the construction company and the guaranty company.

It appears that three of the bridges, viz., the Drew, Vierthaler and Straub, were unfinished when the default occurred, and the principal dispute between the parties herein is in respect to the kind of abutments agreed to be built for the [96]*96Straub bridge. Under the agreement, seven of the bridges were to be built and spans of wrecked bridges were to be taken from the beds of streams, the whole to be done for $13,294. In a schedule attached to the contract, the price of each piece of work was stated, and the price named for the Straub bridge was $1200. It was stipulated that the bridges named should “have one roadway, 18 feet in clear width, and to be built with center line of roadway at right angles to abutments or piers, and to be constructed according to the annexed specifications and plans, which are made a part of this contract.” The plans and specifications referred to were contained in a document designated as instructions to bidders and general specifications, and this was in the hands of the construction company when it submitted its bid and when the parties entered into the contract, and it was in the hands of the guaranty company when it executed its bond. In this document special reference was made to the Straub bridge as follows: “Bridge is a four panel sixty-nine foot span, built about 20 years ago. Abutment to be rebuilt of concrete and old bridge replaced. Bridge in fairly good shape, excepting part of the top chord which is badly twisted, county to furnish new lumber needed, either at Claflin or Gt. Bend.” No detailed plans were made for the Straub bridge, nor indeed for any of the bridges. Two drawings or blue prints were made and used, and on the side of one of them there was an indorsement, “Design of bridge at Drew and Vierthaler crossings,” and on the other, “Proposed bridge for Mud Creek.” In each of these plans the abutments were represented to have wing walls. There was testimony to the effect that a separate drawing was not made for the Straub bridge, because it was a repair job, and also that the drawings made were intended to be guides for the work on all the bridges, including the Straub bridge. Testimony, too, was given to the effect that Sheldon, who was associated with Jenkins at the time, had gone over-all the features of the work with the board, and was informed and understood that the abutments of the Straub bridge, as well as the others, were to be built with wing walls. There was a provision, too, in the instructions to bidders, that in case any question arose as to the meaning of the plans and specifications the interpretation of the board [97]*97should control, and bidders were requested to satisfy themselves as to the meaning of the plans and specifications, as they would be firmly held to the interpretation placed upon them by the board.

The guaranty company contends that the contract is entire, that the drawings or plans with reference to abutments had no application to the Straub bridge, and that the meaning of the term “rebuilt,” used in the specifications, meant to replace the abutments in the form and dimensions of the old ones, and that, therefore, the requirement of wing walls was without justification. The contract in respect to the abutments was plain enough as to the material to be used, but was ambiguous as to the size and form of the same. The Straub bridge was to be built according to the plans and specifications annexed to the contract, and as the only plans made and considered by the parties provided for wing walls the court, we think, was warranted in holding that the bridge was to be rebuilt with wing walls.

The contract appears to have been an entirety, but as between the different parties contending here, it is deemed unimportant whether it is to be regarded as entire or severable. The whole work was to be done for $13,294, and completed at a stated time. It was stipulated that bids must cover the work as a whole, and none of the conditions of the contract indicate that the contractor could be relieved from the obligar tions of the agreement by anything short of full performance of the entire work. The schedule attached, stating prices for each piece of work, was probably intended as a basis for carrying out the provision that eighty-five per cent of the cost price should be paid to the contractor as each piece of work was fully completed. The contract, although ambiguous, was valid, and the ambiguity was cleared up to some extent by extrinsic circumstances, such as the acts and declarations of the parties. Where there is ambiguity in a written agreement parol evidence may be received, not to contradict the writing but to aid in its interpretation. To that end, the circumstances under which the contract was made and the practical construction put upon it by the parties themselves may be received. (Baxter Springs v. Light Co., 64.Kan. 591, 68 Pac. 63; Mayberry v. Beck, 71 Kan. 609, 81 Pac. 191; Parks v. [98]*98Baker, 81 Kan. 351, 105 Pac. 439; Riley v. Foster, 95 Kan. 213, 148 Pac. 246.) In its decision, the trial court stated that .as the case was before the court alone, some testimony was received relative' to what transpired in connection with the letting of the contract, as an aid to an understanding of its provisions. However, the court stated that this testimony did not control its judgment nor lead to a variance or alteration of any part of the contract. After finding what was due to each of the claimants, the court found that there was due from the board to the construction company, for work that had been completed before the default, the sum of $3055.09, which it was required to pay into court for distribution among the claimants.

The court charged back against the board certain items expended by it in the completion of the contract. These findings are challenged on a cross-appeal which has been taken by the board. When the default occurred and the guaranty company declined to complete the contract the board., employed the Missouri Valley Bridge & Iron Company to finish the work. It agreed to give that company the actual cost with ten per cent added for profit. In arriving at actual cost the customary method was adopted of taking the actual cost of material and labor and general expenses and upon the whole of these adding ten per cent for profit. A dispute has arisen as to what may be properly tréated as general expenses.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weiner v. Wilshire Oil Co.
389 P.2d 803 (Supreme Court of Kansas, 1964)
Thompson Construction Co. v. Schroyer
298 P.2d 239 (Supreme Court of Kansas, 1956)
Barton v. Hackney
208 P.2d 590 (Supreme Court of Kansas, 1949)
Mosher v. Kansas Coöperative Wheat Marketing Ass'n
15 P.2d 421 (Supreme Court of Kansas, 1932)
Mayse v. Grieves
285 P. 630 (Supreme Court of Kansas, 1930)
Road Supply & Metal Co. v. Bechtelheimer
240 P. 846 (Supreme Court of Kansas, 1925)
Swaller v. Williamson Milling Co.
226 P. 1001 (Supreme Court of Kansas, 1924)
Carlisle v. Farmers Elevator & Business Ass'n
180 P. 280 (Supreme Court of Kansas, 1919)
Carroll v. Bowersock
164 P. 143 (Supreme Court of Kansas, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
157 P. 417, 98 Kan. 94, 1916 Kan. LEXIS 23, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kanzius-v-jenkins-kan-1916.