Ryan v. Bay City

125 N.W. 398, 160 Mich. 559, 1910 Mich. LEXIS 806
CourtMichigan Supreme Court
DecidedMarch 22, 1910
DocketDocket No. 28
StatusPublished
Cited by3 cases

This text of 125 N.W. 398 (Ryan v. Bay City) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ryan v. Bay City, 125 N.W. 398, 160 Mich. 559, 1910 Mich. LEXIS 806 (Mich. 1910).

Opinion

Hooker, J.

The plaintiff made a contract to do paving, according to specifications made a part of said contract, with Bay City. He was to furnish all material and labor and have the pavement completed on or before September 22d. In his contract it was provided that:

“ The board of public works of said Bay City shall have the right and power to determine finally all questions as to the proper performance of the contract, and as to the completion of the work of this contract specified, and in case of dilatory, improper or imperfect performance thereof to suspend the work covered by this contract or any unfinished portion thereof, whether from unreasonable delay in performing the work, or other just cause, said board shall deem this contract forfeited. * * *
“ Failure or neglect on the part of the city engineer or his inspector to condemn inferior work or material at any time of its being supplied or done shall not be construed to imply an acceptance of any work. If it becomes evident to the engineer or board, at any time prior to the final acceptance of the work by the city, that improper material had been furnished, or inferior work done upon said improvements, he or the board shall have the right to order the removal of such material and work, and to require that suitable material be supplied and proper work •done in lieu thereof by said contractor, without expense to the city. * * *
“All material and workmanship shall be strictly first class, whether specially set forth herein or not, and shall [561]*561be subject to the inspection and rejection of the city engineer, and all materials condemned by him shall be removed from the work at once. * * *
“ If at any time it should appear to the board of public works that the pavement or any portion thereof is not being executed in a sound and workmanlike manner or with due diligence, or if the contractor shall from bankruptcy, insolvency, or any cause whatever be prevented or delayed in proceeding with the pavement in accordance with his contract and these specifications, it shall be lawful for the said board, after three (3) days’ notice of their intention to do so, to employ any other contractor, workman or other person by contract, day work and otherwise, to proceed with such pavement and complete the same.”

The pavement was not completed until the following spring, when on examination the board of public works claims to have found that the concrete laid the fall before as a foundation for a portion of the pavement was unsuitable to lay brick upon, and was not such a foundation as was contemplated and provided for in the contract, and plaintiff was required to remove it and complete the job according to the contract, and upon his refusal the work was done by another, and the city paid for it. This action was brought by Ryan to recover the balance unpaid him, and defendant made a counterclaim by way of recoupment. The trial resulted in a verdict for the defendant, and plaintiff has appealed.

The first contention is that it was error for the court to permit the defendant to show that the concrete became defective through freezing. This claim is based on the alleged facts:

(а) That the defendant’s inspectors were present and permitted it to be laid.

(б) That it must be assumed that it was approved, because of payments upon estimates which must have included it.

In other words, the contention seems to be that the city took the chances of injury through freezing because it did not prevent the laying, and must be presumed to have [562]*562accepted poor work, or the consequences of unforeseen freezing because it did not withhold more of the plaintiff’s pay. We are of the opinion that the plaintiff took the risk of freezing, unless he was ordered to lay the concrete at that time, of which we find no proof, although the court left the question to the jury. We are also of the opinion that including this concrete in estimates, if this was done, did not estop the city from denying its acceptance of the risk of freezing, or the consequences of concealed defects arising from the nonconformity to specifications. This is not like those cases in which the employer knew of violations of his contract, permitted them to go on without protest, and included them in estimates which were paid by him, as in the case of Schliess v. City of Grand Rapids, 131 Mich. 59 (90 N. W. 700), where it was said:

“ The law would not permit defendant to see this work go on, to ratify it day after day and week after week, to see plaintiff putting in stone not in exact accord with the contract, and then say, when the work is done, ‘ You have not complied with the contract.’ Its time to accept or reject was when the work was being done. It could not lull the plaintiff into the belief that this work was satisfactory, and, when completed, reject it.”

The case is radically different from Schliess v. City of Grand Rapids, supra, where the contract contemplated construction in cold weather and where the work was done in wintry weather under directions of the proper authority.

In the case of Lamson v. City of Marshall, 133 Mich. 250 (95 N. W. 78), the majority opinion turned upon the fact that the plaintiffs acted under explicit orders made by the authorized representative of the city, which they were bound to obey. It was said:

“It is insisted, however, that the provision, ‘Although the engineer may assent to special means of prosecuting work in difficult cases, this will not relieve the contractor of the responsibility of the result,’ imposes upon the plaintiffs in this case the responsibility for the result of the im[563]*563proper method of laying this sewer. In my judgment, this provision is not applicable to this case. If the plaintiffs are right in their claim (and whether they are right or not is a question for the jury), the engineer did more than assent to the means adopted in this case. He positively directed their adoption. * * *
“ The contractors are bound to obey the orders made in good faith by the engineer, whether those orders are advantageous or detrimental to their interests; nor are they exempt from obedience because they believe those orders to be unwise.”

See, also, Barber Asphalt Paving Co. v. Village of Highland Park, 156 Mich. 178, 182 (120 N. W. 621). There is no testimony in the case that has been called to our attention that the representatives of the city knew of any violation of the contract, and stood by and permitted it. On the contrary, counsel are claiming that there was no noncompliance, and that there was no evidence from which it could be inferred.

The following excerpt from the charge is made the basis of alleged error:

“If you find from the testimony that the concrete was in such condition in the spring of 1904, that it could have been covered with brick, and that when so covered it would have made a good substantial pavement, such a pavement as is provided for in the contract and specifications, then the defendant was not justified in causing the concrete to be torn up and preventing the plaintiff from completing his contract, and the plaintiff ought to recover for whatever is due him by reason thereof.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sioux City v. Western Asphalt Paving Corp.
271 N.W. 624 (Supreme Court of Iowa, 1936)
Kanzius v. Jenkins
157 P. 417 (Supreme Court of Kansas, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
125 N.W. 398, 160 Mich. 559, 1910 Mich. LEXIS 806, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ryan-v-bay-city-mich-1910.