Carroll v. Bowersock

164 P. 143, 100 Kan. 270, 1917 Kan. LEXIS 309
CourtSupreme Court of Kansas
DecidedApril 7, 1917
DocketNo. 20,752
StatusPublished
Cited by7 cases

This text of 164 P. 143 (Carroll v. Bowersock) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carroll v. Bowersock, 164 P. 143, 100 Kan. 270, 1917 Kan. LEXIS 309 (kan 1917).

Opinions

The opinion of the court was delivered by

Burch, J.:

The action was one to recover for part performance of a contract to construct a reenforced concrete floor in a warehouse which was destroyed by fire before the floor was completed. The plaintiff recovered and the defendant appeals.

The contract was formed by acceptance of the following proposal:

“We hereby propose to furnish all labor and material, and construct reenforced concrete floor in warehouse with necessary columns and column footings, using Turner System of reenforcing as designed by C. A. P. Turner of Minneapolis, Minnesota. This floor to consist of a 7" rough slab, mix-1-2-4, with a %" finish top, mix-1-2-, for the sum of Eighteen Hundred and Twenty-five ($1825) Dollars.
“This floor to be designed for a working load of 400 lbs. per sq. ft., and a test load of 800 lbs. per sq. ft., and is guaranteed to comply in all respects with these requirements.
“We propose to use the old floor now in place for forms for concrete, but will cut the old floor away from walls and remove all or part of the upper floor, the sub-floor and joists to remain in place. We are to have the use for construction'purposes of any of the old lumber removed.
“We will begin the work when the details are received or within two weeks from this date, and complete same within two weeks after reenforcing steel is received.
“Payment for this work to be made as follows:
“$600.00 when footings and reenforcing steel are in place.
“$600.00 when concrete of floor slab is poured.
“$375.00 when work is completed.
“The balance of $250.00 to be retained for sixty days, and to be due and payable at that time providing contract has been satisfactorily completed.
“It is also agreed that the Lawrence Paper Manufacturing Co. will have the right to test this floor with a superimposed load of 800 lbs. per sq. ft., sixty (60) days after completion of same.”

[272]*272The plaintiff gave testimony abstracted as follows:

“That the first work to do under the contract was putting in concrete footings, then building pillars on these footings, then laying the concrete floor on top; that the columns are given form by building Wooden boxes the desired height, putting in reenforcing rods connected at the bottom with dowels, and pouring the boxds full of concrete; that then the floor rods are so laid so that they come over into a bell on top of the column made by bending the column rods over horizontally in four directions at the top, and running the floor rods into- the bell so formed; that when he last saw the building the footings were all in, the column rods set up and forms made, but no floor rods had been laid; that no cement had been poured in the columns at the time of the fire, and very few floor rods had been put in place; that no lumber was used in the building, exfcept in the temporary forms for columns intended to be later removed; that nails amounting to $4.40 were the only hardware that went into the construction, and this went into the forms; that there should be a credit of $6.40 on the cement bill for returned sacks; that the cement, sand and rock went into the footings; that the upright rods in the columns were wired together, but not fastened to the building; and that some spirals and some column rods were not yet in place.”

The court stated the following findings of fact and conclusion of law:

“FINDINGS OF FACT.
“The plaintiff entered upon the performance of the work in harmony with said contract, and worked for about three weeks. Before commencing the work he procured blue prints to be prepared therefor by an engineer at an expense of................................... $85.00
Prior to the fire hereinafter mentioned he actually used of the steel for reenforcement.................... In value 248.63
Labor for forms for cement........................ “ “ 28.80
Hardware ....................................... “ “ 4.80
Cement .......................................... “ .23.20
Sand and rock.................................... “ “ 17.20
Labor ........................................... “ “ 319.90
Some miscellaneous items.......................... “ “ 3.65
Expended for drayage............................. “ “ 3.15
Blacksmithing .................................... “ “ 6.50
In addition to these he paid freight on tools.......... “ “ 7.25
Railroad fare for men...........‘.................. “ “ 5.95
“The reasonable value of superintending the work and for use of tools is ten per cent of the cost of the material and work actually used in the improvement.
“At the end of the third week, the building was totally .destroyed by fire, without fault of either party to the contract. It was insured in the condition in which it was before the plaintiff commenced work, but there was no insurance upon the improvements made by the plaintiff. The [273]*273defendant collected the insurance, and failed and refused to reconstruct the building upon demand of the plaintiff, so that it was impossible for the plaintiff to complete his contract.
“conclusion of law.
“The plaintiff in this case should recover from the defendant a judgment for $698.09, the same being made up as follows:
Steel actually used......................................... $248.63
Lumber used ............................................ 28.80
Hardware used .......................................... 4.80
Cement used............................................. 23.00
Cost of drayage.......................................... 3.15
Cost of blacksmithing..................................... 6.50
Cost of sand and rock..................................... 17.20
Cost of superintending and use of tools...................... 63.46
Money paid for labor and miscellaneous items................ 323.55
$698.09”

It is apparent that the court permitted recovery for substantially what the plaintiff had done by way of performance of the contract before the fire.

The contract was to place the floor in a specific warehouse. Destruction of the warehouse without fault of either party put an end to construction of a floor in that warehouse. No warehouse except the one destroyed having been contemplated or contracted about, the defendant could not be charged with delinquency for not building another.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ottawa Plumbing, Heating & Air Conditioning, Inc. v. Moore
372 P.2d 1011 (Supreme Court of Kansas, 1962)
OTTAWA PLUMBING, HEATING & AIR CONDITIONING CO v. Moore
372 P.2d 1011 (Supreme Court of Kansas, 1962)
Wilson v. School District No. 40
22 P.2d 433 (Supreme Court of Kansas, 1933)
Robb v. Parten
220 N.W. 610 (Supreme Court of Minnesota, 1928)
F. M. Gabler, Inc. v. Evans Laboratories, Inc.
129 Misc. 911 (New York Supreme Court, 1927)
Fritts v. Quinton
233 P. 1036 (Supreme Court of Kansas, 1925)
Burner v. Northwestern Bible & Missionary Training School
201 N.W. 939 (Supreme Court of Minnesota, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
164 P. 143, 100 Kan. 270, 1917 Kan. LEXIS 309, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carroll-v-bowersock-kan-1917.