Jones v. Summit Limited Partnership Five

635 N.W.2d 267, 262 Neb. 793, 2001 Neb. LEXIS 174
CourtNebraska Supreme Court
DecidedNovember 9, 2001
DocketS-00-630
StatusPublished
Cited by52 cases

This text of 635 N.W.2d 267 (Jones v. Summit Limited Partnership Five) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jones v. Summit Limited Partnership Five, 635 N.W.2d 267, 262 Neb. 793, 2001 Neb. LEXIS 174 (Neb. 2001).

Opinion

Hendry, C.J.

INTRODUCTION

This case arises from a contract dispute between Sammie Jones (Jones) and The Summit Group, Inc., a general contractor *794 affiliated with Summit Limited Partnership Five (collectively The Summit Group). After the dispute was submitted to arbitration, The Summit Group requested that the district court modify or correct the arbitrator’s award pursuant to Neb. Rev. Stat. § 25-2614(a)(l) (Reissue 1995). The district court denied the request and confirmed the award. The Summit Group appealed.

FACTUAL BACKGROUND

Jones, an individual doing business as Jones Drywall, contracted to do painting and drywalling on a hotel owned by The Summit Group in Lincoln, Nebraska. The Summit Group was displeased with Jones’ work and his staffing of the job, and eventually terminated its contractual relationship with Jones.

On July 30, 1998, Jones filed a construction lien against the hotel and a construction lien foreclosure petition and praecipe in Lancaster County District Court. The parties thereafter filed a joint stipulation to arbitrate the dispute and agreed to stay the district court proceedings pending the outcome of the arbitration. The district court ordered the stay.

The parties arbitrated their dispute. The record before this court regarding the proceedings before the arbitrator includes only the two-page arbitration award and the one-page order of the arbitrator denying modification. The arbitrator entered his award on February 25, 1999. In the award, the arbitrator awarded Jones $40,195.47, itemized as follows:

Drywall Contract Damages Total $31,031.59
Painting Contract Damages Total 9.163.88
Total $40,195.47

The arbitrator also awarded The Summit Group $10,019.40, itemized as follows:

Custom Drywall Systems $ 11,453.00
E&K Drywall 21,112.00
Performance Coatings 18,800.00
Payment to Tim Rogers 600.00
Extra staff to clean paint and texture from Fixtures, tubs, etc. 1,092.00
Sub-total $53,057.00
Less Contract Amounts
Not Paid to Jones <43.037.60>
Total $10,019.40

*795 In sum, the arbitrator found $40,195.47 in damages to Jones and $10,019.40 in damages to The Summit Group, resulting in an award of $30,176.07 to Jones.

On March 17, 1999, Jones applied to the district court for confirmation of the arbitration award. That same day, The Summit Group filed an application for modification of the award with the arbitrator in accordance with Neb. Rev. Stat. § 25-2610 (Reissue 1995). The arbitrator refused to modify the prior award and denied the application.

The Summit Group then filed a motion in the district court, requesting modification or correction of the arbitrator’s award pursuant to § 25-2614(a)(l). The Summit Group asserted that the arbitrator granted Jones a double recovery by awarding Jones $40,195.47 for “Drywall Contract Damages” and “Painting Contract Damages,” while deducting $43,037.60 for “Contract Amounts Not Paid to Jones” from The Summit Group’s award. The district court denied The Summit Group’s motion and confirmed the arbitrator’s $30,176.07 award to Jones. The court found there was not an “evident miscalculation of figures” under § 25-2614(a)(l).

The Summit Group appealed to the Nebraska Court of Appeals, which, in Jones v. Summit Group, Inc., 8 Neb. App. lxvii (case No. A-99-1090, Jan. 18, 2000), dismissed the appeal without opinion and remanded to the district court for reasons unrelated to this appeal. Jones thereafter moved for summary judgment in the district court requesting that court to enter a final judgment in the amount of the arbitration award. The district court entered judgment for Jones. The Summit Group appealed.

ASSIGNMENTS OF ERROR

The Summit Group assigns that the district court erred as a matter of fact and law in refusing to alter or amend the arbitrator’s award.

STANDARD OF REVIEW

In reviewing a district court’s decision to vacate, modify, or confirm an arbitration award under Nebraska’s Uniform Arbitration Act, this court is obligated to reach a conclusion independent of the trial court’s ruling as to questions of law. However, the trial court’s factual findings will not be set aside *796 on appeal unless clearly erroneous. See Dowd v. First Omaha Sec. Corp., 242 Neb. 347, 495 N.W.2d 36 (1993).

ANALYSIS

Question of Law

The Summit Group asserts that the arbitrator’s award contains an “evident miscalculation of figures” under § 25-2614(a)(l), justifying a modification or correction of the arbitrator’s award. Under Nebraska’s Uniform Arbitration Act, a district court may modify or correct an arbitration award when one of the limited grounds listed in § 25-2614 exists. The Summit Group relies on § 25-2614(a)(l), which states, “[T]he court shall modify or correct the award when: (1) There was an evident miscalculation of figures.”

This court has not previously addressed what constitutes an “evident miscalculation of figures” under § 25-2614(a)(1). However, § 25-2614(a)(l) is similar to 9 U.S.C. § 11(a) (1994) of the federal Arbitration Act (“evident material miscalculation of figures”) and identical to the Unif. Arbitration Act § 13(a)(1), 7 U.L.A. 409 (1997) (“evident miscalculation of figures”), which has been adopted in other states. Accordingly, we look to federal and state decisions interpreting similar portions of the Uniform Arbitration Act and the federal Arbitration Act for guidance in construing § 25-2614(a)(l). See, e.g., Father Flanagan’s Boys’ Home v. Agnew, 256 Neb. 394, 590 N.W.2d 688 (1999) (in interpreting state statute, court may look to federal court decisions construing similar federal statute); FirstTier Bank v. Triplett, 242 Neb. 614, 497 N.W.2d 339 (1993) (stating that other jurisdictions’ opinions were persuasive in case of first impression in Nebraska under Uniform Commercial Code).

Various courts have defined what constitutes an evident miscalculation in the context of reviewing an arbitrator’s decision. In the federal courts, the Eighth Circuit has defined an “evident material miscalculation of figures” under 9 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Nebraska Assn. of Pub. Employees
984 N.W.2d 103 (Nebraska Supreme Court, 2023)
Sutey Oil v. Monroe's High Country
2022 MT 50 (Montana Supreme Court, 2022)
Signal 88 v. Lyconic
310 Neb. 824 (Nebraska Supreme Court, 2022)
City of Omaha v. Professional Firefighters Assn.
309 Neb. 918 (Nebraska Supreme Court, 2021)
State v. Henderson
762 N.W.2d 1 (Nebraska Supreme Court, 2009)
Aramark Uniform & Career Apparel, Inc. v. Hunan, Inc.
757 N.W.2d 205 (Nebraska Supreme Court, 2008)
Hartman v. City of Grand Island
657 N.W.2d 641 (Nebraska Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
635 N.W.2d 267, 262 Neb. 793, 2001 Neb. LEXIS 174, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jones-v-summit-limited-partnership-five-neb-2001.