Cole v. Hiller

715 So. 2d 451, 1998 La. App. LEXIS 729, 1998 WL 159031
CourtLouisiana Court of Appeal
DecidedApril 8, 1998
DocketNos. 30397-CA, 30398-CA
StatusPublished
Cited by5 cases

This text of 715 So. 2d 451 (Cole v. Hiller) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cole v. Hiller, 715 So. 2d 451, 1998 La. App. LEXIS 729, 1998 WL 159031 (La. Ct. App. 1998).

Opinion

hMARVIN, Chief Judge.

In these consolidated actions for judicial review of an arbitrator’s $12,000 award in favor of the homeowners against the building contractor, and after the arbitrator denied the parties’ joint request to amend the award for mathematical reasons, the homeowners sought to have the award confirmed and the contractor moved for modification of the award. La. R.S. 9:4209, 4211. The contractor’s motion was filed more than three months after the award was initially made, causing the homeowners to assert that the motion was untimely under La. R.S. 9:4213.

The trial court modified the award to reflect a net recovery of $10,000 by the contractor against the homeowners, on findings that the contractor’s motion was timely and that the arbitrator’s award contained an “evident material miscalculation of figures,” one of the limited grounds for judicial modification of an arbitrator’s award under § 4211.

On this record, we affirm.

ARBITRATION CLAIMS

The contractor, Kirby Cole, and the homeowners, Dr. and Mrs. Laurence Hiller, agreed in their 1993 building contract to submit any disputes arising under the contract to arbitration. In his demand for arbitration filed in May 1996, Cole sought $16,310 for “nonpayment of construction re-tainage” and $16,711 for “painting overage,” for a total of $33,021.

The Hillers filed a counterclaim seeking $50,000 in damages for the “inconvenience, frustration and loss of favorable interest rate” caused by Cole’s delay in completing construction of their home. These demands, along with the demands of the architect, Ben Patterson, against the Hillers, were submitted to an arbitrator associated with the American Arbitration Association’s Construetion |2Industry Arbitration Tribunal, who conducted a three-day hearing in the fall of 1996.

ARBITRATOR’S AWARD

In his award dated October 31, 1996, the arbitrator ordered the Hillers to pay their architect, Patterson, $24,000. That award is not at issue in this appeal.

[453]*453Addressing Cole’s claim against the Hillers for $33,021 in construction costs, the arbitrator found that Cole was entitled to roughly one-third of the amount claimed, or $10,063. This amount consisted of $6,000 for “Painting Overage” (out of Cole’s total claim of $16,711) and $4,063 for “Retainage” (initial claim of $16,310, less two credits totaling $12,247: $5,900 for “Lumber Allowance” and $6,347 for “Punch List Items”).

After denying in its entirety the Hillers’ claim against Cole for damages associated with the construction delays, the only demand asserted in the Hillers’ counterclaim according to this record, the arbitrator determined that Cole owed the Hillers $22,958 “for their counterclaim.” Two of the three sums comprising this award consist of the same sums credited to the Hillers in calculating the award to Cole: $5,900 for “Lumber allowed reduction in contract amount” and $6,347 for “Punch List costs allowed.” The remaining $10,711 of the award to the Hillers was determined to be for “Painting Overage allowed,” and represents the difference between Cole’s total painting overage claim of $16,711 and Cole’s $6,000 recovery for this item.

Subtracting the $10,063 award in Cole’s favor from the $22,958 award in favor of the Hillers, the arbitrator ordered Cole to pay the Hillers $12,895 “for their counterclaim.” This award, like the $24,000 award in favor of the architect Patterson, was to be paid “on or before thirty (30) days from the date of this Award,” October 31,1996.

|3We reproduce and supplement with bracketed notations the arbitrator’s itemization of the respective amounts determined to be owed by the Hillers to Cole and by Cole to the Hillers:

$10,063.27 owed by the Hillers to Cole, consisting of: •
$ 6,000.60 Painting Overage [out of Cole’s total claim of $16,-711.60], and
[4,062.67 Construction Retainage, calculated as follows:]
$16,309.67 Retainage [total amount claimed]
- 5,900.00 Less Lumber Allowance
- 6,347.00 [Less] Punch List Items.
$ 22,958.00 owed by Cole to the Hillers:
Denied The request for compensation due to November closing in lieu'of Spring 1994
Denied The request for paying closing costs twice
$ 6,347.00 Punch List costs allowed
5,900.00 Lumber allowed reduction in contract amount, and
10,711.00 Painting Overage allowed [difference between Cole’s total claim of $16,711.60 and above award of $6,000.60 to Cole].

JOINT REQUEST FOR MODIFICATION BY ARBITRATOR

On November 20, 1996, Cole and the Hil-lers, through their respective attorneys, sent a letter to the American Arbitration Association jointly requesting that the arbitrator review his award, which the parties described as “quite confusing,” and amend the award “for mathematical reasons.” The letter explained:

The “award” as originally drafted gave the Hillers credit for the lumber allowance of $5,900.00, and the punch list items of $6347.50 [sic] [should be $6347.00] twice. Also, as originally drafted, the “award” in favor of Cole for the “painting overage” was only $6,060.00 [sic] [should be $6,000.60] yet provided a credit to the Hil-lers for “painting overage allowed” of $10,-711.00. The Hillers did not pay any of the painting allowance at all.
If this is what [the arbitrator] intended, then the net result would be an award in favor of Kirby Cole in the,amount of $10,-063.27 [the amount determined to be owed by the Hillers to Cole], with there being no award in Lfavor of the Hillers in excess of the credits given [in calculating the award to Cole],
... With a desire to clear up any confusion and to ascertain [the arbitrator’s] true intentions, we are requesting that the original award be reviewed to correct any possible defects in it.
(Italics in original; boldface supplied.)

The letter did not question the arbitrator’s calculation of the $24,000 owed by the Hillers to Patterson, the architect, but noted that that sum was to be paid within 30 days of the October 31, 1996 award, and requested the arbitrator’s “immediate attention ... to see if the confusion surrounding [the Cole-Hiller] award can be cleared before this 30 day period has run.” Emphasis in original; brackets supplied.

On January 24,1997, the arbitrator formally denied “the request for modification of the Award,” without reasons. Notice of the deni[454]*454al was sent to counsel for all parties on the same day.

COURT PROCEEDINGS

La. R.S. 9:4211 allows a court to modify or correct an arbitrator’s award on limited grounds, including “Where there was an evident material miscalculation of figures ... in the award.” Notice of a motion to modify or correct an award “shall be served upon the adverse party or his attorney within three months after the award is filed or delivered, as prescribed by law for service of a motion in an action ....” § 4213; emphasis supplied.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coastal Industries, LLC v. Arkle Constructors
Louisiana Court of Appeal, 2022
TURQUOISE PROPERTIES GULF, INC. v. Hugh OVERMYER
81 So. 3d 1250 (Supreme Court of Alabama, 2011)
Leon Angel Constructors v. Kirk Knott Elec.
837 So. 2d 743 (Louisiana Court of Appeal, 2003)
Jones v. Summit Limited Partnership Five
635 N.W.2d 267 (Nebraska Supreme Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
715 So. 2d 451, 1998 La. App. LEXIS 729, 1998 WL 159031, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cole-v-hiller-lactapp-1998.