Coastal Industries, LLC v. Arkle Constructors

CourtLouisiana Court of Appeal
DecidedSeptember 1, 2022
Docket2021CA0906
StatusUnknown

This text of Coastal Industries, LLC v. Arkle Constructors (Coastal Industries, LLC v. Arkle Constructors) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coastal Industries, LLC v. Arkle Constructors, (La. Ct. App. 2022).

Opinion

STATE OF LOUISIANA

COURT OF APPEAL

FIRST CIRCUIT

2021 CA 0906

COASTAL INDUSTRIES, LLC

VERSUS

ARKEL CONSTRUCTORS, LLC, SMITH LAROCK ARCHITECTURE P. C. AND THE LEFFLER GROUP CONSULTING STRUCTURAL ENGINEERING, INC.

Judgment Rendered: SEP 01 2022

On Appeal from the Nineteenth Judicial District Court In and for the Parish of East Baton Rouge State of Louisiana Docket No. 649, 069

Honorable Wilson Fields, Judge Presiding

Russel W. Wray Counsel for Plaintiff/ Appellant St. Francisville, Louisiana Coastal Industries, LLC

John C. Funderburk Counsel for Defendant/ Appellee Thomas D. Bourgeois, Jr. Arkel Constructors, LLC Baton Rouge, Louisiana

e_" BEFORE: McCLENDON, WELCH, AND THERIOT, JJ. McCLENDON, J.

In this construction contract case, the plaintiff appeals a district court's judgment

that confirmed an arbitration award in favor of the defendant. For the reasons that

follow, we reverse in part and affirm in part.

FACTS AND PROCEDURAL HISTORY

On June 13, 2016, the plaintiff, Coastal Industries, LLC ( Coastal), filed a petition

for damages against Arkel Constructors, LLC ( Arkel), Smith LaRock Architecture P. C.

Smith LaRock), and The Leffler Group Consulting Structural Engineers, Inc., d/ b/ a The

Leffler Group ( Leffler). Coastal sought damages from the three defendants arising from

the construction of a control building at the Marathon Petroleum Company LP

Marathon) plant in Garyville, Louisiana ( the Project). Arkel, the general contractor,

had subcontracted with Coastal to perform certain work on the Project ( the

Subcontract). In its petition, Coastal claimed that Arkel breached the Subcontract

resulting in damages to Coastal in an amount no less than $ 700, 000. 00. Coastal also

alleged that Smith LaRock, the architect, was engaged by Marathon to design the

Project and that Smith LaRock contracted with Leffler to perform the structural

engineering work. Coastal asserted that Smith LaRock and Leffler breached the

standard of care owed to Coastal by providing untimely and incorrect plans,

specifications, and modifications that interfered in Coastal' s work causing damages.

On July 20, 2016, Arkel filed a dilatory exception of prematurity and alternative

motion to stay and compel arbitration, alleging that Coastal' s claims fell within the

scope of an arbitration clause contained in the Subcontract. Thus, Arkel requested that

Coastal' s claims be dismissed.' Additionally, Leffler and Smith LaRock answered the

petition and, thereafter, filed a joint memorandum in support of Arkel' s exception of

prematurity. Leffler and Smith LaRock requested that the district court sustain the

dilatory exception and dismiss Coastal' s claims against Arkel, but reject Arkel' s

alternative motion to stay, arguing that only Coastal' s claims against Arkel were subject

to arbitration. After a hearing held on May 9, 2017, the district court took the matter

1 Coastal had previously filed its own motion to stay the proceedings pending arbitration, but later filed an ex parte motion to withdraw the motion to stay, which the district court granted.

2 under advisement and, on May 16, 2017, issued its ruling, sustaining the exception of

prematurity, ordering arbitration between Coastal and Arkel, and staying the

proceedings as to all other parties. On June 13, 2017, the district court issued an order

memorializing its oral ruling and ordering that the pending arbitration between Arkel

and Coastal be administered by the American Arbitration Association ( AAA).

On June 9, 2017, Coastal initiated arbitration proceedings with the AAA. In the

demand for arbitration, Coastal attached a copy of its previously filed petition, and

stated that "[ t] he arbitrator will be called upon to hear claims for delay, disruption,

extra work, payments due, and de facto termination -for -convenience damages, along

with penalties, interest, and attorney fees in excess of one million dollars."

Arkel filed an answer and counterclaim to Coastal' s arbitration demand,

specifically asserting numerous delays and errors committed by Coastal, as well as

abandonment of the project prior to completion. Arkel further alleged that, as a result,

it terminated the Subcontract with Coastal for default and self -performed Coastal' s

remaining work under the Subcontract. Arkel requested the costs of completing

Coastal' s scope of work after termination and for payments it made on behalf of Coastal

to Coastal' s subcontractors or material suppliers that Coastal failed to pay, which

resulted in deductive change orders. Arkel asserted that it terminated Coastal' s

Subcontract for cause under Section 22. 4 of the Subcontract, which provided that upon

termination, Coastal " shall be liable for all expenses of completing the Subcontract

Work." Arkel also asserted a claim for interest and attorney fees under the

Subcontract.

The AAA arbitration hearing was conducted for nine days in September 2018.

Thereafter, both parties submitted post -hearing briefs, after which the hearing was

deemed closed. 2 On December 11, 2018, the arbitrator issued an Interim Award,

2 In November 2018, the arbitrator reopened the hearing pursuant to AAA rules for additional information requested by the arbitrator. The parties submitted the requested information, and the hearing was again closed.

3 3 addressing the merits and ruling in favor of Arkel. The arbitrator made several

findings, including that Coastal breached its Subcontract with Arkel and that, as a

result, its Total Loss Claim was not reasonable. Accordingly, Coastal' s claim of

972, 278. 72 for Termination Costs was denied. The arbitrator also found that Arkel

had the contractual right to delay or withhold any payments to Coastal when there were

questions or concerns as to compliance with the Subcontract; that Arkel was justified in

delaying or withholding payments to Coastal; that Arkel' s billing and payment methods

to Coastal did not violate the Subcontract; and that Arkel did not breach its Subcontract

with Coastal regarding its payments to Coastal. Thus, the arbitrator denied the claims

made by Coastal for payment of penalties, interest, and attorney fees.

The arbitrator also determined that when Coastal demobilized from the jobsite,

its " scope of work was 95% - 97% complete and invoiced for." As such, the arbitrator

determined that Coastal " substantially performed" its subcontract work under the

Subcontract with Arkel and did not default. The arbitrator found that although Coastal

may have technically breached some provisions of the Subcontract with Arkel, " none of

them, even all together," rose to the level of a " material breach" of the Subcontract.

Accordingly, the arbitrator found no material breach of the Subcontract by either party.

Further, the arbitrator determined that Arkel' s termination of Coastal was a termination

for ' convenience," i.e., a " no fault" termination pursuant to Section 22. 5 of the

Subcontract.4

3 The Interim Award did not include qualification of the amounts to be awarded to Arkel for attorney fees and costs, nor did it include the award of arbitration costs or award of arbitrator fees/ expenses, which were to be addressed in the Final Award.

4 Section 22. 5 of the Terms and Conditions of the Subcontract provides:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Oxford Health Plans LLC v. Sutter
133 S. Ct. 2064 (Supreme Court, 2013)
Firmin v. Garber
353 So. 2d 975 (Supreme Court of Louisiana, 1977)
Leon Angel Constructors v. Kirk Knott Elec.
837 So. 2d 743 (Louisiana Court of Appeal, 2003)
JK DEVELOPMENTS v. Amtek of Louisiana, Inc.
985 So. 2d 199 (Louisiana Court of Appeal, 2008)
Welch v. AG Edwards & Sons, Inc.
677 So. 2d 520 (Louisiana Court of Appeal, 1996)
Lpc v. Larrison Family Health Center
870 So. 2d 575 (Louisiana Court of Appeal, 2004)
National Tea Co. v. Richmond
548 So. 2d 930 (Supreme Court of Louisiana, 1989)
Smith v. State
899 So. 2d 516 (Supreme Court of Louisiana, 2005)
Robert S. Robertson, Ltd. v. State Farm
921 So. 2d 1088 (Louisiana Court of Appeal, 2006)
JK DEVELOPMENTS, LLC v. Amtek of Louisiana, Inc.
983 So. 2d 1276 (Supreme Court of Louisiana, 2008)
Major League Baseball Players Assn. v. Garvey
532 U.S. 504 (Supreme Court, 2001)
Preis Gordon, APLC v. Chandler
191 So. 3d 31 (Louisiana Court of Appeal, 2016)
Lewis v. Louisiana Department of Public Safety & Corrections
228 So. 3d 1226 (Supreme Court of Louisiana, 2017)
Cole v. Hiller
715 So. 2d 451 (Louisiana Court of Appeal, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Coastal Industries, LLC v. Arkle Constructors, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coastal-industries-llc-v-arkle-constructors-lactapp-2022.