Joe Lemoine Construction, Inc. v. United States

40 Cont. Cas. Fed. 76,953, 36 Fed. Cl. 4, 1996 U.S. Claims LEXIS 102, 1996 WL 325924
CourtUnited States Court of Federal Claims
DecidedJune 12, 1996
DocketNo. 95-489C
StatusPublished
Cited by2 cases

This text of 40 Cont. Cas. Fed. 76,953 (Joe Lemoine Construction, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joe Lemoine Construction, Inc. v. United States, 40 Cont. Cas. Fed. 76,953, 36 Fed. Cl. 4, 1996 U.S. Claims LEXIS 102, 1996 WL 325924 (uscfc 1996).

Opinion

ORDER

MILLER, Judge.

This case is before the court on defendant’s motion for summary judgment. There are two issues to be resolved: 1) whether the contract required completion within 135 calendar days from the date of the contract award, regardless of when the contractor obtained the required performance bonds and the Government approved them; and 2) whether a bilateral modification changing the sequence of work, but providing for no additional time or compensation, prohibits the contractor from claiming for additional time absent reservation of a claim. Argument is deemed unnecessary.

FACTS

The following facts are undisputed, unless otherwise noted. On September 27, 1993, the Naval Facilities Engineering Command (“NAVFAC”) awarded contract No. N62467-[6]*691-C-7223 to Joe Lemoine Construction, Inc. (“plaintiff”). The $123,100.00 contract required plaintiff to renovate and upgrade the bathrooms in Building 602 at the Naval Support Activity East Bank in New Orleans, Louisiana. Specifically, plaintiff was to enlarge Bathroom Area “2A,” a women’s bathroom, and to add a men’s bathroom. Plaintiff was also to renovate Bathroom Area “2C,” consisting of both a men’s and women’s bathroom.

Per Solicitation No. N62467-91-B-7223, the Department of the Navy (the “Navy”) stated that the successful contractor was to begin construction within 10 calendar days of the award and that performance was to be completed within 120 calendar days of the award. Accompanying the solicitation were instructions for potential bidders. These instructions required the submission of payment and performance bonds within 10 days of the contract award. Paragraph 14 of the Instructions to Bidders states: “The contract time for purposes of fixing the completion date, default, and liquidated damages shall begin to run 15 days from the date of award, regardless of when performance and payment bonds are executed.” Section 01010 111.6 of the contract provides:

The work shall be completed within 120 calendar days. For purposes of computing the contract completion date, 15 calendar days will be added to this completion time to allow for mailing of the contract award and the submission and approval of required bonds. The contract completion date will therefore be 135 calendar days from the date of the contract award.

Because the contract was awarded to plaintiff on September 27, 1993, the contract completion date was February 9,1994.

To ensure timely performance, NAVFAC requires that all construction contracts in excess of $25,000.00, other than cost-plus-fixed-fee contracts, or those wherein the contractor cannot control the pace of perfor-manee, include a liquidated damages clause. See NAVFAC’s Contracting Manual, P-68, 1987, Subpart 12.2, 12.203-100. For construction contracts with an estimated cost between $100,00.00-$500,000.00, the liquidated damages are set at $200.00 per calendar day of delay. Section 01010 U 1.7 of the contract set liquidated damages at $200.00 per calendar day of delay.

The September 27, 1993 award letter required plaintiff to contact the Navy to schedule a pre-construction conference. After waiting for over a week, the Navy contacted plaintiff on October 5, 1993, and scheduled a pre-construction conference for October 13, 1993. At this conference the Navy reviewed a list of the required administrative materials, such as the performance and payment bonds, that were required before plaintiff could commence on-site work.1

During this conference the Navy and plaintiff also reviewed the sequence in which plaintiff would perform the contract. As the Navy wanted to ensure that at least one women’s and one men’s bathroom remained fully functional at all times, the contract prohibited the contractor from working on more than one bathroom at once.2 Consequently, the contract was to be completed in four separate phases.

Several weeks after the pre-construction conference, plaintiff had yet to provide the requisite administrative materials that would permit on-site construction to commence. On December 3, 1993, the Navy met with plaintiff to discuss the lack of progress. Subsequently, on December 10, 1993, the Navy sent plaintiff a proposal to modify the contract by permitting plaintiff to work on two bathrooms at once, thus reducing the contract from four phases to two phases. In a counter-proposal plaintiff requested a 76-day time extension. The Navy denied plaintiffs request for an extension, on the ground that the proposed modification would reduce, not add, performance time.

[7]*7On December 27,1993, the parties met and agreed to Modification No. P00001 (“Mod P00001”), which reduced the contract from four phases to two phases.3 Mod P00001 states that “[a]s a result of the Modification agreed to herein, the total contract price is not changed and the contract price remains at $123,100.00. The contract period of performance remains unchanged, as well.” The modification also contains a release which provides:

In consideration of the modification agreed to herein as complete equitable adjustment of the Contractor’s 27 December 1993 “Proposal for Adjustment,” the Contractor hereby releases the Government from any and all liability under this contract for further equitable adjustments attributable to such facts or circumstance giving rise to the “Proposal for Adjustment.”

During the negotiations surrounding Mod P00001, plaintiff finally submitted the performance bonds, which the Navy approved on December 20, 1993.4 Plaintiff received confirmation of the Navy’s acceptance of the bonds during the December 27 meeting regarding Mod P00001.

On February 18, 1994, plaintiff executed Modification No. P00002 (“Mod P00002”), which required plaintiff to remove and replace certain asbestos tiles. Under the terms of the modification, the contract price was increased by $2,733.00 and the performance deadline was extended three calendar days until February 12,1994, Therefore, for purposes of this motion, the completion date is deemed to be February 12,1994.

Construction began on December 28,1993, and was completed on May 19,1994, 96 days beyond the completion date. Therefore, on June 17, 1994, the Navy issued unilateral contract Modification No. P00003, downwardly adjusting the final amount due by the sum of $19,200.00.5

Plaintiff submitted a claim to the Navy on August 26, 1994, seeking return of the liquidated damages withheld for untimely contract completion.6 On March 28, 1995, the contracting officer issued a final decision denying plaintiff’s claim for return of the liquidated damages. On August 1, 1995, plaintiff filed a complaint in the United States Court of Federal Claims seeking payment of $19,-200.00 withheld by the Navy as liquidated damages.

Defendant moved for summary judgment on the ground that the contract expressly required that performance be completed within 135 calendar days from the date of contract award. Defendant maintains that because plaintiff was 96 calendar days late, the Navy properly imposed liquidated damages in the amount of $19,200.00. Plaintiff proffers two arguments. First, plaintiff contends that the contract completion date was not 135 calendar days from the date of the award.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Starflight Boats v. United States
48 Fed. Cl. 592 (Federal Claims, 2001)
Massie v. United States
40 Fed. Cl. 151 (Federal Claims, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
40 Cont. Cas. Fed. 76,953, 36 Fed. Cl. 4, 1996 U.S. Claims LEXIS 102, 1996 WL 325924, Counsel Stack Legal Research, https://law.counselstack.com/opinion/joe-lemoine-construction-inc-v-united-states-uscfc-1996.