Fraass Surgical Manufacturing Co. v. United States

505 F.2d 707, 20 Cont. Cas. Fed. 83,501, 205 Ct. Cl. 585, 1974 U.S. Ct. Cl. LEXIS 23
CourtUnited States Court of Claims
DecidedNovember 20, 1974
DocketNo. 343-73
StatusPublished
Cited by18 cases

This text of 505 F.2d 707 (Fraass Surgical Manufacturing Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fraass Surgical Manufacturing Co. v. United States, 505 F.2d 707, 20 Cont. Cas. Fed. 83,501, 205 Ct. Cl. 585, 1974 U.S. Ct. Cl. LEXIS 23 (cc 1974).

Opinion

Kunzig, Judge,

delivered the opinion of the court:

In this case involving three defense supply contracts, plaintiff, Fraass Surgical Manufacturing Company, Inc., presents a three-count petition for relief:

Comit I is a request for reformation of contract to relieve plaintiff of liability for destruction of government property lost in a fire on plaintiff’s premises.

Count II seeks mitigation under the contracts of the amount of plaintiff’s alleged liability to the government.

Oount III asserts that the money which plaintiff ultimately paid to defendant was paid under mistake of fact or law and that plaintiff is, accordingly, entitled to repayment.

The case is before us on defendant’s five-pronged motion for summary judgment. We sustain the motion in part, dismissing portions of plaintiff’s Count II and all of Count III. The remainder of the motion is denied.

Plaintiff is a supplier to the United States armed services of tropical survival kits assembled in part from materials [588]*588furnished by the government and in part from items purchased by the contractor from other sources. On January 9, 1967, plaintiff’s premises were almost completely destroyed by fire, and a quantity off government-furnished property (GFP), delivered by defendant and awaiting incorporation into survival kits, was destroyed. Following the fire, defendant informed plaintiff that language included in the proposals for each of three supply contracts negotiated in 1966 obligated plaintiff to assume strict liability for any damage or loss of GFP regardless of whether the contractor was at fault.

By letter of September 8,1967, the Contracting Officer set the final amount of the government demand for reimbursement for lost GFP at $126,220.38. Of this amount, $15,117.10 was attributed to loss of GFP delivered for use under Contract No. DSA-120-67-C-0959 (No. 0959) ; $110,760.25 to lost GFP for Contract No. DSA-120-67-C-1174 (No. 1174) ; and $343.03 to GFP for Contract No. DSA-120-67-C-1222 (No. 1222). In early October 1967, at the insistence of defendant, plaintiff paid, under protest, the proceeds of a $75,000 insurance policy covering the GFP which had been stored on plaintiff’s premises. The remaining $51,220.38 was offset against progress payments on Contract No. 1174.

To recover the $126,220.38 held by defendant, plaintiff filed suit directly in this court September 21, 1973. (No appeal was ever taken from the Contracting Officer’s September 8, 1967 letter to the Armed Services Board of Contract Appeals (ASBCA).)1

Plaintiff’s basic contention in this suit (Oownt I) is that an Armed Services Procurement Regulation (ASPR) in effect when these contracts were negotiated in 1966 relieved plaintiff of liability for loss of GFP. Plaintiff argues that ASPR 13-702 (g) (1964) applied to “negotiated fixed price” defense supply contracts of the type here involved and required to be inserted in the contract proposals a clause “g” which would have imposed liability on the contractor only for loss of GFP caused by the contractor’s “willful mis[589]*589conduct or lack of good faith.” Instead, defendant’s Contracting Officer included in the contract proposals a clause “g” placing risk of loss of GFP on plaintiff regardless of the cause of the loss. Plaintiff contends that this inclusion was both erroneous as a matter of law and contrary to the intentions of the parties. Claiming, too, that the warehouse fire was not caused by elements of contractor misconduct specified in the correct clause “g,” plaintiff seeks from this court reformation of the three contracts involved and return of the $126,320.38.

Plaintiff argues secondly (Count II) that, assuming plaintiff is properly to be held accountable for loss of GFP, the dollar amount recoverable by defendant should be less than the $126,220.38 claimed because the loss was increased by government delay in delivering the property to the contractor. This delay, plaintiff asserts, violated delivery schedules which had been added as modifications to each of the three contracts. As a direct result of this delay, the contractor had more GFP on hand at the time of the fire than it would have had if the deliveries of GFP had been made on schedule.

Plaintiff’s Count III alleges that its payments to defendant were made under mistake of fact or law and that plaintiff is accordingly entitled to repayment of $126,220.38.2

In its dispositive motion, defendant does not address the merits of plaintiff’s contentions, hut instead moves for summary judgment on the following grounds:

(A) all of plaintiff’s claims are barred by the statute of limitations,
(B) all of plaintiff’s claims should be barred by laches,
(C) plaintiff’s Count II claim for mitigation of contractor’s liability is barred by an accord and satisfaction with respect to Contracts No. 0959 and No. 1174,
(D) plaintiff has failed to exhaust its administrative remedies under Contract No. 1222 on its Count II claim, and
(E) plaintiff’s Count III, alleging payment under mistake of fact or law, either (a) is duplicative of plaintiff’s [590]*590Oount I claim for reformation or (b) fails to state a claim upon which, relief can be granted.

For reasons detailed below, we remand this case to the trial division for resolution of a factual dispute concerning when the statute of limitations began to run and, if then necessary, for decision of the substantive issues raised in plaintiff’s Oount I. Defendant’s laches argument fails as a matter of law. Plaintiff’s Oount II claim on Contracts No. 0959 and No. 1174 is dismissed as barred by an accord and satisfaction. We hold, however, that plaintiff’s omission to pursue contractual remedies with respect to Contract No. 1222 is excused by failure of the Contracting Officer to issue a proper “final decision” apprising plaintiff of its appeal rights. The remaining portion of plaintiff’s Oownt II (Contract No. 1222) is remanded to the trial division along with plaintiff’s Oownt I. Plaintiff’s Oownt III is redundant and is, accordingly, dismissed.

(A) Statute of Limitations

This suit was brought September 21, 1973. In its motion for summary judgment, defendant argues that plaintiff’s action is barred by the statute of limitations, 28 U.S.C. § 2501, because all of the events fixing the alleged liability of the defendant and entitling plaintiff to institute an action occurred more than six years before the date plaintiff filed its petition. Defendant contends the statute of limitations began to run either on September 8,1967, when plaintiff was notified by certified mail of the final amount of the government claim, or on September 15, 1967, when the first $12,382.02 was allegedly withheld from the first partial payment due plaintiff under Contract No. 1174.

Defendant asserts the statute of limitations began to run from September 8,1967, when defendant made an “authoritative demand” for reimbursement by a letter of the Contracting Officer setting the final dollar amount of the government claim for lost GFP.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Navcom Defense Electronics, Inc. v. England
53 F. App'x 897 (Federal Circuit, 2002)
Statesman Savings Holding Corp. v. United States
41 Fed. Cl. 1 (Federal Claims, 1998)
Joe Lemoine Construction, Inc. v. United States
40 Cont. Cas. Fed. 76,953 (Federal Claims, 1996)
Spirit Leveling Contractors v. United States
36 Cont. Cas. Fed. 75,770 (Court of Claims, 1989)
Travelers Indemnity Co. v. United States
35 Cont. Cas. Fed. 75,607 (Court of Claims, 1988)
Pathman Construction Co. v. United States
33 Cont. Cas. Fed. 74,394 (Court of Claims, 1986)
Research, Analysis, & Development, Inc. v. United States
32 Cont. Cas. Fed. 73,471 (Court of Claims, 1985)
Nrm Corporation v. Hercules Incorporated
758 F.2d 676 (D.C. Circuit, 1985)
S.E.R., Jobs for Progress, Inc. v. United States
759 F.2d 1 (Federal Circuit, 1985)
Grad Partnership v. United States
31 Cont. Cas. Fed. 72,051 (Court of Claims, 1984)
Standard Oil Co. of California v. United States
685 F.2d 1322 (Court of Claims, 1982)
Craddock v. United States
29 Cont. Cas. Fed. 82,568 (Court of Claims, 1982)
Sumner v. United States
678 F.2d 202 (Court of Claims, 1982)
American Ship Building Co. v. United States
654 F.2d 75 (Court of Claims, 1981)
Laka Tool & Stamping Co. v. United States
639 F.2d 738 (Court of Claims, 1980)
Fraass Surgical Mfg. Co. v. United States
571 F.2d 34 (Court of Claims, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
505 F.2d 707, 20 Cont. Cas. Fed. 83,501, 205 Ct. Cl. 585, 1974 U.S. Ct. Cl. LEXIS 23, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fraass-surgical-manufacturing-co-v-united-states-cc-1974.