Javinsky v. Commissioner of Administration

725 N.W.2d 393, 2007 Minn. App. LEXIS 2, 2007 WL 3529
CourtCourt of Appeals of Minnesota
DecidedJanuary 2, 2007
DocketA06-109
StatusPublished
Cited by8 cases

This text of 725 N.W.2d 393 (Javinsky v. Commissioner of Administration) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Javinsky v. Commissioner of Administration, 725 N.W.2d 393, 2007 Minn. App. LEXIS 2, 2007 WL 3529 (Mich. Ct. App. 2007).

Opinion

OPINION

WORKE, Judge.

On appeal in this public-contract dispute, appellant Allen Javinsky argues that (1) the district court improperly denied appellant’s request for mandamus and declaratory relief, and (2) summary judgment was improper on appellant’s promissory-estoppel claim. Because appellant failed to timely appeal the district court’s denial of his mandamus and declaratory relief claims and because he has not provided evidence of reasonable, detrimental reliance in his promissory-estoppel claim, we affirm.

*395 FACTS

In 1999, respondent Commissioner, Minnesota Department of Administration (DOA) began a multi-stage sewer-system replacement project at the Minnesota Correctional Facility-Faribault. At issue here is a contract for project 04-01 to reshape and grout the deep tunnel at the correctional facility. Generally, the DOA is responsible for administering construction projects under Minn. Stat §§ 16B.001-16B.282 (2004) and awards state contracts based on a selection process it coordinates. For certain projects, however, the selection of contractors is made by the State Design Selection Board (SDSB), an independent agency whose authority is defined by Minn.Stat. § 16B.33. Agencies must use the SDSB to select the primary designer on building construction or remodeling projects when estimated costs exceed a certain amount. The SDSB had previously selected the primary designer to perform the sewer-system-replacement project.

In 2003, the DOA decided to have the State Architect’s Office (SAO) rather than the SDSB select an alternate project designer for the final phase of the project. The SAO requested proposals from four design engineers, including appellant, a subcontractor who had worked on the original project. In February 2004, after learning that he had not been chosen as the designer for the project, appellant objected to the selection process and contended that the SDSB, not the SAO, should have made the designer determination, as it had for earlier phases of the sewer-system-replacement project. The SAO reconsidered its decision and agreed, in a letter to the SDSB, that “the authority for selecting an alternative design firm remains with the [SDSB], not the [SAO] ” and stated “[w]e reviewed the statute and agree that, technically, we did not have the authority to solicit proposals and make an alternate selection.” The SDSB then requested proposals for the project and received submissions from appellant and a competitor. In April 2004, the SDSB notified appellant that he had been selected as the designer for the project. After the competitor challenged the SDSB’s selection of appellant, respondent placed the contract process for the project on hold and requested information from the SDSB about its selection criteria and evaluation process.

In September 2004, respondent withdrew the responsibility for selecting a designer for the project from the SDSB because it had not provided the information respondent requested. Respondent ordered the SAO to issue a new request for proposals without further involvement from the SDSB. Respondent stated that “use of the [SDSB] is not statutorily mandated for infrastructure work (see definition of project in [Minn.Stat. § 16B.33, subd. 1(h)]).” Appellant objected to respondent’s decision to reject him as the designer for the project and to withdraw authority from the SDSB.

In October 2004, the SAO issued a request for proposals for the project. In November 2004, appellant sued respondent, seeking a writ of mandamus, declaratory judgment, promissory estoppel, and other relief. Following submissions of proposals in response to the SAO’s request for proposals for the project, the competitor was selected as the designer. Appellant moved for injunctive relief, and the district court conducted a hearing on November 30, 2004.

Because legislative authority for the project was set to expire by December 31, 2004, if there was no contract, the parties agreed to treat the district court’s decision on appellant’s motion for injunctive relief as a summary judgment on his mandamus *396 and declaratory relief claims. On December 16, 2004, the district court denied appellant’s motion for injunctive relief, refusing to issue a writ of mandamus or order a declaratory judgment. The district court found that respondent did not violate Minn.Stat. § 16B.33 by withdrawing the request for the SDSB to select a designer for the project and having the SAO make the selection instead. The district court directed entry of judgment with the determination that “there is no just reason for delay.” Judgment was entered on December 27, 2004. After respondent moved for summary judgment on appellant’s remaining promissory estoppel claim, the district court granted respondent’s motion and entered judgment in favor of respondent, finding that appellant had failed to provide evidence supporting the injustice element of promissory estoppel. This appeal follows.

ISSUES

I. Is appellant’s appeal of the December 2004 judgment timely?

II. Did the district court err in granting summary judgment in favor of respondent on the promissory-es-toppel claim?

ANALYSIS

I.

Appellant argues that he was not required to appeal the December 2004 judgment because it was an interlocutory judgment that did not resolve all of his claims. His notice of appeal only refers to the district court’s judgment entered in November 2005. The district court “may direct the entry of a final judgment as to one or more but fewer than all of the claims of parties only upon an express determination that there is no just reason for delay and upon an express direction for the entry of judgment.” Minn. R. Civ. P. 54.02. It can be inferred from Minn. R. Civ.App. P. 104.01, subd. 1, that timely appeal of a judgment containing rule 54.02 certification is mandatory because rule 104.01 states “the time to appeal from any other judgment entered pursuant to [r]ule 54.02 shall not begin to run until the entry of a judgment which adjudicates all the claims and rights and liabilities of the remaining parties.”

Minn. R. Civ. P. 54.02 is substantively identical to Fed.R.Civ.P. 54(b). The United States Supreme Court explained that federal rule 54(b) was promulgated to provide clarity to the parties when some but not all of the claims at issue have been decided, stating that “[a] party adversely affected by a final decision thus knows that his time for appeal will not run against him until this certification has been made,” i.e., until the district court makes an express determination that there is no just reason for delay and expressly directs entry of judgment. Sears, Roebuck & Co. v. Mackey, 351 U.S. 427, 435-36, 76 S.Ct. 895, 900, 100 L.Ed. 1297 (1956). Similarly, the Minnesota Supreme Court reasoned that a party affected by an order with an express rule 54.02 certification has a right to expect that the expiration of the time for appeal would fully define the parameters of the litigation, promote principles of judicial economy, and afford the affected parties review prior to participating in any further proceedings necessitated by the district court’s order. In re State & Regents Bldg.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carsten James Quinlan v. Fraser, Alissa Puls
Court of Appeals of Minnesota, 2025
Contractors Edge, Inc. v. City of Mankato
863 N.W.2d 765 (Supreme Court of Minnesota, 2015)
Sterling State Bank v. Maas Commercial Properties, LLC
837 N.W.2d 733 (Court of Appeals of Minnesota, 2013)
Meriwether Minnesota Land & Timber, LLC v. State
818 N.W.2d 557 (Court of Appeals of Minnesota, 2012)
Seegert v. Monson Trucking, Inc.
717 F. Supp. 2d 863 (D. Minnesota, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
725 N.W.2d 393, 2007 Minn. App. LEXIS 2, 2007 WL 3529, Counsel Stack Legal Research, https://law.counselstack.com/opinion/javinsky-v-commissioner-of-administration-minnctapp-2007.