G Urban Companies, Inc. v. Roseville Area Schools ISD 623

Court of Appeals of Minnesota·Decided December 4, 2023·No. a230573·Unpublished

Opinion

This opinion is nonprecedential except as provided by Minn. R. Civ. App. P. 136.01, subd. 1(c).

STATE OF MINNESOTA

IN COURT OF APPEALS

A23-0573

G Urban Companies, Inc.,

Appellant,

vs.

Roseville Area Schools ISD #623, Respondent.

Filed December 4, 2023

Affirmed

Schmidt, Judge

Ramsey County District Court File No. 62-CV-21-4872

Beau D. McGraw, McGraw Law Firm, P.A., Lake Elmo, Minnesota (for appellant)

Zachary J. Cronen, Squires, Waldspurger & Mace, P.A., Minneapolis, Minnesota (for respondent)

Considered and decided by Ross, Presiding Judge; Schmidt, Judge; and Halbrooks, Judge. ∗

Retired judge of the Minnesota Court of Appeals, serving by appointment pursuant to Minn. Const. art. VI, § 10.

NONPRECEDENTIAL OPINION

SCHMIDT, Judge Appellant G Urban Companies Inc. (G Urban) challenges the summary-judgment dismissal of its claims of breach of contract, unjust enrichment, and promissory estoppel against respondent Roseville Area Schools ISD #623 (the district), arguing that issues of material fact regarding the bidding process that led to the parties’ contract preclude summary judgment on all three claims. Because the plain language of the parties’ contract defeats the breach-of-contract claim and the existence of an enforceable contract precludes equitable relief, we affirm.

FACTS 1

In mid-2019, the district began a construction project at a middle school that included work on its track and field. The district’s construction manager solicited bids for the project, posting plans and specifications for bidding on the platform iSqFt. The bidding documents were also available in several other locations, including the Minnesota Builders Exchange (MBEX). The work scope for the project called for “removal of existing track aggregate as required to install engineered soil.” An addendum to the bidding documents (Addendum No. 2) also referenced “engineered soil” and included a drawing (C200) that used shading to show installation of engineered soil as part of the project.

1 Consistent with our review of an order granting summary judgment, our recitation of the facts includes only undisputed facts that we view in the light most favorable to G Urban as the nonmoving party. Trebelhorn v. Agrawal, 905 N.W.2d 237, 241 (Minn. App. 2017).

G Urban submitted a bid, offering to complete the work for $1,650,000. In its bid, G Urban acknowledged that it received and examined the bidding documents and addenda. After all bids were publicly opened and read at the Roseville Area Schools District Center, G Urban was revealed to be the lowest bidder. The parties thereafter reviewed the scope of the project, confirming that it included installation of a new engineered soil track. G Urban told the district that its bid did not account for installing engineered soil because it obtained a drawing from MBEX that did “not indicate that engineered soil is required for the surface of the track.” G Urban asserted that the apparent inconsistency in bidding documents made the bidding process unfair and requested that the district either award it the project and later provide for additional compensation for installing engineered soil or reject all bids and allow for rebidding. The district denied the requests.

Instead, the construction manager explained that the district intended to accept G Urban’s bid amount as is “with no intention of accepting a change order.” The construction manager further offered that if G Urban was “not in agreement they may withdraw their bid.” G Urban responded that it “will not agree to withdraw its bid” and reiterated its requests for the district to award the contract to G Urban with the additional cost for the engineered soil or for the district to re-bid the entire project. The district replied that G Urban will be “expected and required to utilize engineered fill in the track areas.” The district also noted that it “will strongly oppose any effort by G. Urban, post-award, to assert a claim of entitlement to additional compensation for such fill.” G Urban did not withdraw its bid.

The district’s school board held a public meeting to award the project. G Urban’s owner attended the meeting and spoke during the public-comment period, restating the request for additional compensation for installing engineered soils. The district awarded the project to G Urban. G Urban and the district thereafter executed a written contract. In defining the work that G Urban agreed to perform, the construction contract incorporated numerous bid documents, including Addendum No. 2 and drawing C200, which identify installation of engineered soil as part of the project. The district agreed to pay G Urban $1,650,000 for the work. The construction contract states that it “represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreements, either written or oral.” The construction contract also permits modification of the scope of the work and the compensation if the parties agree to a “change order.”

In early 2020, G Urban wrote to the construction manager requesting an additional $77,750 as “extra costs” for installing engineered soil, reiterating its position that some bidding documents did not clearly show that work as part of the project. The construction manager rejected the request, stating: “The expectation is that because [G Urban] accepted the project award that engineered fill will be provided throughout the track as shown in the project documents at no additional cost to the project.” G Urban completed the project, including installation of engineered soil.

G Urban sued the district, alleging that the construction contract is an “enforceable agreement,” it requested a change order regarding installation of engineered soil, and the district breached the contract by “fail[ing] to approve [G Urban’s] change order and

refus[ing] to compensate [G Urban] for the use of engineered soils in the track and field area.” G Urban also asserted claims of unjust enrichment and promissory estoppel based on the district’s refusal to compensate it for installing engineered soil.

The district moved for summary judgment, arguing that it did not breach the construction contract by declining to grant a change order because the contract required installation of engineered soil. The district also argued G Urban cannot receive equitable relief because a valid contract governs the parties’ actions. The district court agreed, granted summary judgment, and dismissed the case with prejudice. G Urban appeals.

DECISION

Summary judgment is proper if the moving party shows that “there is no genuine issue as to any material fact and the movant is entitled to judgment as a matter of law.” Minn. R. Civ. P. 56.01. On appeal, we review “the record to determine whether there is any genuine issue of material fact and whether the district court erred in its application of the law.” Dahlin v. Kroening, 796 N.W.2d 503, 504–05 (Minn. 2011). “We review a district court’s summary judgment decision de novo.” Riverview Muir Doran, LLC v. JADT Dev. Grp., LLC, 790 N.W.2d 167, 170 (Minn. 2010). We view the evidence “in the light most favorable to the party against whom judgment was granted.” Trebelhorn, 905 N.W.2d at 241.

I. The plain language of the construction contract defeats G Urban’s breach-ofcontract claim.

To prevail on a breach-of-contract claim, a plaintiff must prove three elements: “(1) formation of a contract, (2) performance by plaintiff of any conditions precedent to [its] right to demand performance by the defendant, and (3) breach of the contract by defendant.” Park Nicollet Clinic v. Hamann, 808 N.W.2d 828, 833 (Minn. 2011).

Free access — add to your briefcase to read the full text and ask questions with AI

G Urban Companies, Inc. v. Roseville Area Schools ISD 623, (Mich. Ct. App. 2023).

G Urban Companies, Inc. v. Roseville Area Schools ISD 623 (G Urban Companies, Inc. v. Roseville Area Schools ISD 623) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Javinsky v. Commissioner of Administration
725 N.W.2d 393 (Court of Appeals of Minnesota, 2007)
Colangelo v. Norwest Mortgage, Inc.
598 N.W.2d 14 (Court of Appeals of Minnesota, 1999)
TRIPLE B & G, INC. v. City of Fairmont
494 N.W.2d 49 (Court of Appeals of Minnesota, 1992)
Riverview Muir Doran, LLC v. JADT Development Group, LLC
790 N.W.2d 167 (Supreme Court of Minnesota, 2010)
Dahlin v. Kroening
796 N.W.2d 503 (Supreme Court of Minnesota, 2011)
Park Nicollet Clinic v. Hamann
808 N.W.2d 828 (Supreme Court of Minnesota, 2011)
Christensen Law Office, PLLC v. Olean
916 N.W.2d 876 (Court of Appeals of Minnesota, 2018)