G Urban Companies, Inc. v. Roseville Area Schools ISD 623

CourtCourt of Appeals of Minnesota
DecidedDecember 4, 2023
Docketa230573
StatusUnpublished

This text of G Urban Companies, Inc. v. Roseville Area Schools ISD 623 (G Urban Companies, Inc. v. Roseville Area Schools ISD 623) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
G Urban Companies, Inc. v. Roseville Area Schools ISD 623, (Mich. Ct. App. 2023).

Opinion

This opinion is nonprecedential except as provided by Minn. R. Civ. App. P. 136.01, subd. 1(c).

STATE OF MINNESOTA IN COURT OF APPEALS A23-0573

G Urban Companies, Inc., Appellant,

vs.

Roseville Area Schools ISD #623, Respondent.

Filed December 4, 2023 Affirmed Schmidt, Judge

Ramsey County District Court File No. 62-CV-21-4872

Beau D. McGraw, McGraw Law Firm, P.A., Lake Elmo, Minnesota (for appellant)

Zachary J. Cronen, Squires, Waldspurger & Mace, P.A., Minneapolis, Minnesota (for respondent)

Considered and decided by Ross, Presiding Judge; Schmidt, Judge; and

Halbrooks, Judge. ∗

∗ Retired judge of the Minnesota Court of Appeals, serving by appointment pursuant to Minn. Const. art. VI, § 10. NONPRECEDENTIAL OPINION

SCHMIDT, Judge

Appellant G Urban Companies Inc. (G Urban) challenges the summary-judgment

dismissal of its claims of breach of contract, unjust enrichment, and promissory estoppel

against respondent Roseville Area Schools ISD #623 (the district), arguing that issues of

material fact regarding the bidding process that led to the parties’ contract preclude

summary judgment on all three claims. Because the plain language of the parties’ contract

defeats the breach-of-contract claim and the existence of an enforceable contract precludes

equitable relief, we affirm.

FACTS 1

In mid-2019, the district began a construction project at a middle school that

included work on its track and field. The district’s construction manager solicited bids for

the project, posting plans and specifications for bidding on the platform iSqFt. The bidding

documents were also available in several other locations, including the Minnesota Builders

Exchange (MBEX). The work scope for the project called for “removal of existing track

aggregate as required to install engineered soil.” An addendum to the bidding documents

(Addendum No. 2) also referenced “engineered soil” and included a drawing (C200) that

used shading to show installation of engineered soil as part of the project.

1 Consistent with our review of an order granting summary judgment, our recitation of the facts includes only undisputed facts that we view in the light most favorable to G Urban as the nonmoving party. Trebelhorn v. Agrawal, 905 N.W.2d 237, 241 (Minn. App. 2017).

2 G Urban submitted a bid, offering to complete the work for $1,650,000. In its bid,

G Urban acknowledged that it received and examined the bidding documents and addenda.

After all bids were publicly opened and read at the Roseville Area Schools District Center,

G Urban was revealed to be the lowest bidder. The parties thereafter reviewed the scope

of the project, confirming that it included installation of a new engineered soil track.

G Urban told the district that its bid did not account for installing engineered soil because

it obtained a drawing from MBEX that did “not indicate that engineered soil is required for

the surface of the track.” G Urban asserted that the apparent inconsistency in bidding

documents made the bidding process unfair and requested that the district either award it

the project and later provide for additional compensation for installing engineered soil or

reject all bids and allow for rebidding. The district denied the requests.

Instead, the construction manager explained that the district intended to accept

G Urban’s bid amount as is “with no intention of accepting a change order.” The

construction manager further offered that if G Urban was “not in agreement they may

withdraw their bid.” G Urban responded that it “will not agree to withdraw its bid” and

reiterated its requests for the district to award the contract to G Urban with the additional

cost for the engineered soil or for the district to re-bid the entire project. The district replied

that G Urban will be “expected and required to utilize engineered fill in the track areas.”

The district also noted that it “will strongly oppose any effort by G. Urban, post-award, to

assert a claim of entitlement to additional compensation for such fill.” G Urban did not

withdraw its bid.

3 The district’s school board held a public meeting to award the project. G Urban’s

owner attended the meeting and spoke during the public-comment period, restating the

request for additional compensation for installing engineered soils. The district awarded

the project to G Urban. G Urban and the district thereafter executed a written contract. In

defining the work that G Urban agreed to perform, the construction contract incorporated

numerous bid documents, including Addendum No. 2 and drawing C200, which identify

installation of engineered soil as part of the project. The district agreed to pay G Urban

$1,650,000 for the work. The construction contract states that it “represents the entire and

integrated agreement between the parties hereto and supersedes prior negotiations,

representations or agreements, either written or oral.” The construction contract also

permits modification of the scope of the work and the compensation if the parties agree to

a “change order.”

In early 2020, G Urban wrote to the construction manager requesting an additional

$77,750 as “extra costs” for installing engineered soil, reiterating its position that some

bidding documents did not clearly show that work as part of the project. The construction

manager rejected the request, stating: “The expectation is that because [G Urban] accepted

the project award that engineered fill will be provided throughout the track as shown in the

project documents at no additional cost to the project.” G Urban completed the project,

including installation of engineered soil.

G Urban sued the district, alleging that the construction contract is an “enforceable

agreement,” it requested a change order regarding installation of engineered soil, and the

district breached the contract by “fail[ing] to approve [G Urban’s] change order and

4 refus[ing] to compensate [G Urban] for the use of engineered soils in the track and field

area.” G Urban also asserted claims of unjust enrichment and promissory estoppel based

on the district’s refusal to compensate it for installing engineered soil.

The district moved for summary judgment, arguing that it did not breach the

construction contract by declining to grant a change order because the contract required

installation of engineered soil. The district also argued G Urban cannot receive equitable

relief because a valid contract governs the parties’ actions. The district court agreed,

granted summary judgment, and dismissed the case with prejudice. G Urban appeals.

DECISION

Summary judgment is proper if the moving party shows that “there is no genuine

issue as to any material fact and the movant is entitled to judgment as a matter of

law.” Minn. R. Civ. P. 56.01. On appeal, we review “the record to determine whether

there is any genuine issue of material fact and whether the district court erred in its

application of the law.” Dahlin v. Kroening, 796 N.W.2d 503, 504–05 (Minn. 2011). “We

review a district court’s summary judgment decision de novo.” Riverview Muir Doran,

LLC v. JADT Dev. Grp., LLC, 790 N.W.2d 167, 170 (Minn. 2010). We view the evidence

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Javinsky v. Commissioner of Administration
725 N.W.2d 393 (Court of Appeals of Minnesota, 2007)
Colangelo v. Norwest Mortgage, Inc.
598 N.W.2d 14 (Court of Appeals of Minnesota, 1999)
TRIPLE B & G, INC. v. City of Fairmont
494 N.W.2d 49 (Court of Appeals of Minnesota, 1992)
Riverview Muir Doran, LLC v. JADT Development Group, LLC
790 N.W.2d 167 (Supreme Court of Minnesota, 2010)
Dahlin v. Kroening
796 N.W.2d 503 (Supreme Court of Minnesota, 2011)
Park Nicollet Clinic v. Hamann
808 N.W.2d 828 (Supreme Court of Minnesota, 2011)
Christensen Law Office, PLLC v. Olean
916 N.W.2d 876 (Court of Appeals of Minnesota, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
G Urban Companies, Inc. v. Roseville Area Schools ISD 623, Counsel Stack Legal Research, https://law.counselstack.com/opinion/g-urban-companies-inc-v-roseville-area-schools-isd-623-minnctapp-2023.