JAAAT Technical Services, LLC

Armed Services Board of Contract Appeals·Decided October 26, 2020·No. ASBCA No. 62373·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) JAAAT Technical Services, LLC ) ASBCA No. 62373 ) Under Contract No. W912HN-10-D-0063 )

APPEARANCE FOR THE APPELLANT: Andrew T. Bodoh, Esq. Thomas H. Roberts & Associates, P.C. Richmond, VA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Laura J. Arnett, Esq. Engineer Trial Attorney U.S. Army Engineer District, Savannah

OPINION BY ADMINISTRATIVE JUDGE SWEET

On April 28, 2020, the Army Corps of Engineers (Corps) moved to dismiss, or in the alternative, for summary judgment, on the grounds that the complaint of appellant JAAAT Technical Services, LLC (JAAAT) purportedly asserts a claim regarding (1) labor burden costs that is unsupported; (2) its subcontractor’s costs (pass-through claim) that violates the Severin doctrine; (3) permanent power and FEDS-E that is barred by the doctrine of accord and satisfaction; and (4) a permit that is barred by the doctrine of judicial estoppel. In response, JAAAT concedes that its complaint erroneously included labor burden and permanent power claims, and a reference to FEDS-E (app. resp. at 5, 7, 11).1 However, JAAAT disputes the Corps’ arguments that judicial estoppel and the Severin doctrine bar JAAAT’s permit and pass-through claims respectively (id. at 6, 8-11).

As discussed in greater detail below, judicial estoppel and the Severin doctrine do not bar JAAAT’s permit and pass-through claims respectively. Therefore, the Corps’ motion is granted in part, and denied in part. We strike the labor burden and permanent

1 In its motion, the Corps indicates that, in the event that JAAAT removes its labor burden claim, we should grant summary judgment based upon the other asserted grounds (gov’t mot. at 2). JAAAT agreed to the removal of its labor burden claim, so we treat the remainder of the Corps’ motion as a summary judgment motion. power claims, and the reference to FEDS-Es. 2 However, we deny the remainder of the motion.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION 3

I. Background

1. On September 30, 2010, the Corps awarded Contract W912HN-10-D-0063 (0063 Contract)—a multiple award task order contract for design/build or construction type tasks in the South Atlantic Division Area—to JAAAT (R4, tab 3.01 at 1180-82).

2. On June 18, 2012, the Corps awarded Task Order 0002 under the 0063 Contract to JAAAT for $15,315,185 for the design and construction of a sensitive compartmented information facility addition at Fort Gordon, Georgia (Whitelaw Wedge Addition Project) (R4, tab 3.04).

II. Procedural History

3. On January 1, 2017, JAAAT submitted a certified claim (claim) for $3,215,346 and a time extension of 342 days as an equitable adjustment under the Changes Clause (FAR 52.243-4) due to the Corps’ alleged (1) interfering with JAAAT’s ability to obtain a National Pollutant Discharge Elimination Systems (NPDES) permit; (2) furnishing the furniture, fixtures, and equipment (FF&E) design late; (3) increasing JAAAT’s permanent power process costs, and (4) accelerating the schedule. The claim does not seek damages for breach of contract. (R4, tab 2.01 at 151, 153, 232) The claim included a pass-through claim for JAAAT’s subcontractor, Tetra Tech, Inc. (Tetra Tech) (R4, tab 2.01 at 168, 570, 750, 1078, 1164, 1018).

4. On October 11, 2019, the Corps issued a contracting officer’s final decision, which denied the claim (R4, tab 1.02).

5. JAAAT filed an appeal, which we docketed as ASBCA No. 62373. In its complaint, JAAAT seeks the same $3,215,346 and an additional 342 calendar day extension sought in its claim, based upon the grounds asserted in the claim (compl. ¶¶ 1, 5-10, 12).

2 The parties agree that removal of the labor burden and permanent power claims reduces JAAAT’s claim to $2,533,005 (app. resp. at 5 n.1, 7; gov’t reply at 2). It does not appear that any costs are associated with the erroneous reference to FEDS-E. 3 We do not discuss the facts related to the labor burden, permanent power, and FEDS-E

issues because JAAAT concedes those issues.

2 II. Tetra Tech Litigation

6. On February 10, 2017, Tetra Tech filed an action against JAAAT in a state court in Georgia for breach of contract and unjust enrichment regarding the Whitelaw Wedge Addition Project (Tetra Tech Litigation). JAAAT successfully moved to remove that action to the United States District Court for the Southern District of Georgia (District Court). (R4, tab 8.04 at 4,702)

7. On April 7, 2017, JAAAT filed its answer, affirmative defenses, and counterclaim in the Tetra Tech Litigation, which alleged that Tetra Tech “[f]aile[d] to timely obtain and support the issuance of the NPDES Permit” (R4, tab 8.04 at 4,750).

8. In early November 2017, JAAAT, Tetra Tech, Tetra Tech Tesoro, Inc., 4 and the project sureties—which had satisfied claims brought by subcontractors and suppliers of JAAAT and Tetra Tech Tesoro under the payment bond—subsequently settled several outstanding lawsuits, including the Tetra Tech Litigation and Tetra Tech Tesoro’s lawsuits against the sureties (gov’t reply ex. B at 2). Under the terms of the settlement agreement, the parties executed a release in exchange for JAAAT paying the sureties $2.8 million, and Tetra Tech guaranteeing that payment (id. at 4-6). The settlement agreement stated that “[n]othing in this Agreement shall be construed as an admission of liability by any of the Parties to this Agreement” (id. at 7).

9. On January 5, 2018, the parties submitted a joint stipulation of dismissal with prejudice to the District Court, which indicated that “[n]either Party will be deemed a prevailing party” (gov’t memo. ex. 4b at 1).

10. On January 8, 2018, the District Court dismissed the Tetra Tech Litigation with prejudice (gov’t memo. ex. 4a at 1).

DECISION

Contrary to the Corps’ arguments, judicial estoppel and the Severin doctrine do not bar JAAAT’s permit and pass-through claims respectively as a matter of law.

I. Standard of Review

Summary judgment is appropriate only if there is no genuine issue as to any material fact, and the moving party is entitled to judgment as a matter of law. Celotex Corp. v. Catrett, 477 U.S. 317, 322-23 (1986). A material fact is one that may affect the outcome of the decision. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248-49 (1986).

4 Tetra Tech Tesoro was a subsidiary of Tetra Tech, and a major subcontractor performing and managing the subcontract (R4, tab 8.04 at 4749-50).

3 There is a “genuine” dispute as to such a fact if “the evidence is such that a reasonable [fact-finder] could return a verdict for the nonmoving party.” Id.

II. Judicial Estoppel Does Not Bar JAAAT’s Permit Claim

Judicial estoppel does not bar JAAAT’s permit claim as a matter of law because, since it is undisputed that the parties settled the Tetra Tech Litigation, JAAAT did not succeed in persuading the District Court to accept its earlier position that Tetra Tech “[f]aile[d] to timely obtain and support the issuance of the NPDES Permit” (SOF ¶ 7). “The doctrine of judicial estoppel is that where a party successfully urges a particular position in a legal proceeding, it is estopped from taking a contrary position in a subsequent proceeding where its interests have changed.” Data General Corp. v. Johnson, 78 F.3d 1556, 1565 (Fed. Cir. 1996).

Free access — add to your briefcase to read the full text and ask questions with AI

JAAAT Technical Services, LLC, (asbca 2020).

JAAAT Technical Services, LLC (JAAAT Technical Services, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related