International Underwater Contractors, Inc. v. New England Telephone & Telegraph Co.

393 N.E.2d 968, 8 Mass. App. Ct. 340, 1979 Mass. App. LEXIS 934
CourtMassachusetts Appeals Court
DecidedSeptember 12, 1979
StatusPublished
Cited by53 cases

This text of 393 N.E.2d 968 (International Underwater Contractors, Inc. v. New England Telephone & Telegraph Co.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
International Underwater Contractors, Inc. v. New England Telephone & Telegraph Co., 393 N.E.2d 968, 8 Mass. App. Ct. 340, 1979 Mass. App. LEXIS 934 (Mass. Ct. App. 1979).

Opinion

Brown, J.

The plaintiff, International Underwater Contractors, Inc. (IUC), appeals from the entry of summary judgment for the defendant, New England Telephone and Telegraph Company (NET).

The plaintiff, which had entered into a written contract with the defendant to assemble and install certain conduits under the Mystic River for a lump sum price of $149,680, to be paid semimonthly in instalments in proportion to the progress of the work, seeks additional compensation in a total amount of $811,816.73 for a major change in the system from that specified in the contract. [341]*341The plaintiff asserts that the change, which was necessitated by delays caused by the defendant, forced the work to be performed in the winter months instead of during the summer, as originally bid, making the equipment originally specified unusable. This major change was made, the plaintiff alleges, at the direction of the defendant, and upon the defendant’s assurances that it would pay the resulting additional costs.

The defendant moved for summary judgment with a supporting affidavit, wherein it argued in defense a release signed by the plaintiff settling the additional claim for a total sum of $575,000. The plaintiff, which submitted countervailing affidavits in opposition to the motion, argues that the release is not binding because it was signed under economic duress.

A special master appointed to hear summary judgment motions found that "as a matter of law, the economic duress required to vitiate the subject release was not present.” Summary judgment was entered for the defendant, and the plaintiffs motions for reconsideration and to vacate judgment were denied. The instant appeal ensued.

Summary judgment is properly entered "if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits ... show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Mass.R.Civ.P. 56(c), 365 Mass. 824 (1974). Community Natl. Bank v. Dawes, 369 Mass. 550, 553 (1976). "[Gjranting summary judgment is error when the party opposing the motion has alleged facts relating to the transaction on which suit has been brought which raise issues entitling him to a trial.” Id. at 556. A. John Cohen Ins. Agency, Inc. v. Middlesex Ins. Co., ante 178,182 (1979).

We must, therefore, examine the standard for economic duress and the pleadings and affidavits in this case to determine whether issues of material fact have been raised, and whether the facts set forth by the plaintiff, if true, would show economic duress invalidating the release.

[342]*342A release signed under duress is not binding. Shewan & Sons v. United States, 73 Ct. Cl. 49, 83-94 (1932). "Coercion sufficient to avoid a contract need not, of course, consist of physical force or threats of it. Social or economic pressure illegally or immorally applied may be sufficient.” Struck Constr. Co. v. United States, 96 Ct. Cl. 186, 220 (1942). See Dana v. Kemble, 17 Pick. 545 (1836); Governor Apartments, Inc. v. Carney, 342 Mass. 351, 354-355 (1961).

To show economic duress (1) a party "must show that he has been the victim of a wrongful or unlawful act or threat, and (2) such act or threat must be one which deprives the victim of his unfettered will.” 13 Williston, Contracts § 1617, at 704 (3d ed. 1970). "As a direct result of these elements, the party threatened must be compelled to make a disproportionate exchange of values.” Id.

The elements of economic duress have also been described as follows: "(1) that one side involuntarily accepted the terms of another; (2) that circumstances permitted no other alternative; and (3) that said circumstances were the result of coercive acts of the opposite party.” Urban Plumbing & Heating Co. v. United States, 408 F.2d 382, 389 (Ct. Cl. 1969), cert, denied, 398 U.S. 958 (1970), quoting from United States v. Bethlehem Steel Corp., 315 U.S. 289, 301 (1942). "Merely taking advantage of another’s financial difficulty is not duress. Rather, the person alleging financial difficulty must allege that it was contributed to or caused by the one accused of coercion.” 13 Willis-ton, supra § 1617, at 708. Thus "[i]n order to substantiate _ the allegation of economic duress or business compulsion ... [tjhere must be a showing of acts on the part of the defendant which produced [the financial embarrassment]. The assertion of duress must be proved by evidence that the duress resulted from defendant’s wrongful and oppressive conduct and not by plaintiffs necessities.” W.R. Grimshaw Co. v. Nevil C. Withrow Co., 248 F.2d 896, 904 (8th Cir. 1957).

[343]*343Here the affidavit submitted in behalf of the defendant stated that amendments to the agreement were executed in January and February, 1974, which provided for "additional compensation for certain additional work,”1 and that "[a]fter IUC submitted billings totalling approximately $811,816.73, substantially more than any amount previously agreed to by NET, a series of meetings were had between representatives of IUC and NET in an attempt to resolve the matter.” In contrast, affidavits submitted on behalf of the plaintiff stated that "the commencement of the work contracted to be performed by IUC was delayed by [NET] because of permits, changed conditions, etc., forcing the work to be performed in the winter months in lieu of the summer months as bid”; that, as a result, "[NET] required a complete redesign of the procedure for installing this duct bank system and its appurtenances”; that "IUC could no longer perform this work for the same price”; and that "commitments, assurances and promises were made by [NET] that a full settlement would be made of all audited amounts (reviewed by [NET]).” The plaintiffs affidavits further asserted that twice in March, 1974, "agreement was reached [with representatives of NET] for the monies due for the work performed to date and assurances were given that an amendment to the contract would be issued” and that at those meetings "IUC made known the fact that it had already expended large amounts of money for which it had not been paid by [NET] and was suffering hardships in meeting its financial obligations”; that IUC and representatives of NET "repeatedly reached agreements as to amounts and methods for payment, and each time [NET] Administration rejected these agreements”; that during this period, for almost an entire year, NET urged IUC to continue the work, stating that a resolution of the dispute over price would be forthcoming and "that it was not [344]*344[NET] policy to have its contractors lose money”; and that in reliance on these assurances IUC continued the work to completion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Okoli v. Okoli
963 N.E.2d 737 (Massachusetts Appeals Court, 2012)
Reynolds v. Bank of Canton (In Re Reynolds)
455 B.R. 312 (D. Massachusetts, 2011)
Boston Medical Center Corp. v. Secretary of Executive Office of Health & Human Services
28 Mass. L. Rptr. 105 (Massachusetts Superior Court, 2010)
Charara v. Yatim
937 N.E.2d 490 (Massachusetts Appeals Court, 2010)
Ward v. Ward
26 Mass. L. Rptr. 434 (Massachusetts Superior Court, 2010)
FAMM Steel, Inc. v. Sovereign Bank
571 F.3d 93 (First Circuit, 2009)
Laudani v. Tribeca Lending Corp. (In Re Laudani)
401 B.R. 9 (D. Massachusetts, 2009)
In RE McMILLEN
390 B.R. 1 (D. Massachusetts, 2008)
McMillen v. Kadis (In re McMillen)
390 B.R. 1 (D. Massachusetts, 2008)
31-35, LLC v. Zucco
2008 Mass. App. Div. 14 (Mass. Dist. Ct., App. Div., 2008)
Cabot Corp. v. AVX Corp.
863 N.E.2d 503 (Massachusetts Supreme Judicial Court, 2007)
SEC v. Happ
392 F.3d 12 (First Circuit, 2006)
Happ v. Corning, Inc.
466 F.3d 41 (First Circuit, 2006)
Creative Marine, Inc. v. Zaccai
21 Mass. L. Rptr. 363 (Massachusetts Superior Court, 2006)
Biliouris v. Biliouris
852 N.E.2d 687 (Massachusetts Appeals Court, 2006)
Citizens Bank v. Business Products Online, Inc.
20 Mass. L. Rptr. 507 (Massachusetts Superior Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
393 N.E.2d 968, 8 Mass. App. Ct. 340, 1979 Mass. App. LEXIS 934, Counsel Stack Legal Research, https://law.counselstack.com/opinion/international-underwater-contractors-inc-v-new-england-telephone-massappct-1979.