Industra/Matrix Joint Venture v. Pope & Talbot, Inc.

142 P.3d 1044, 341 Or. 321, 2006 Ore. LEXIS 824
CourtOregon Supreme Court
DecidedSeptember 8, 2006
DocketCC 0112-12723; CA A121936; SC S52674
StatusPublished
Cited by24 cases

This text of 142 P.3d 1044 (Industra/Matrix Joint Venture v. Pope & Talbot, Inc.) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Industra/Matrix Joint Venture v. Pope & Talbot, Inc., 142 P.3d 1044, 341 Or. 321, 2006 Ore. LEXIS 824 (Or. 2006).

Opinion

*323 BALMER, J.

This case requires us to determine whether claims based on breach of contract and quantum meruit must go to arbitration under an agreement between the parties to arbitrate certain matters. Industra/Matrix Joint Venture (plaintiff) initiated this action, seeking $2.6 million in damages from Pope & Talbot, Inc. (defendant). Plaintiff later filed a petition to compel arbitration and to abate the action pending arbitration. Defendant opposed that petition and also filed a motion for summary judgment asserting that plaintiff was statutorily precluded from commencing either litigation or arbitration because plaintiff was not properly licensed by the Oregon Construction Contractors’ Board (CCB). The trial court denied plaintiffs petition and granted defendant’s motion. On appeal, the Court of Appeals reversed and remanded, holding that plaintiffs claims were arbitrable and that legal issues related to plaintiffs claims, including the CCB license issue, should be decided by the arbitrator. Industra/Matrix Joint Venture v. Pope & Talbot, 200 Or App 248, 113 P3d 961 (2005). We allowed defendant’s petition for review and now affirm the decision of the Court of Appeals.

I. FACTS

We take the facts from the Court of Appeals opinion and the record. In March 2000, Matrix Service, Inc. (Matrix), an Oklahoma corporation, and Industra Service Corporation (Industra), a Washington corporation, signed a “Joint Venture Partnership Agreement” to form plaintiff. The joint venture’s limited purpose was to enter into two contracts with defendant for the construction and installation of piping and mechanical equipment at defendant’s pulp mill in Halsey, Oregon. At all times during the performance of those contracts, Matrix and Industra individually held licenses from the CCB; plaintiff, however, did not.

Both construction contracts contain an identical set of “General Conditions” (GC), three of which — GC 5, GC 27, and GC 35 — are relevant here. Under GC 5, the contracts provide for an “Engineer” to be “the interpreter of the requirements of the Contract Documents and the judge of the performance thereunder by both parties.” Accordingly,

*324 “[c]laims, disputes, and other matters in question relating to the performance of the Work or the interpretation of the Contract Documents shall be referred initially to the Engineer in writing for a decision [.]", 1

Under GC 27, respecting “Claims,” plaintiff is required to “immediately notify the Engineer in writing of any occurrence which * * * has caused or might cause, a substantial delay in the progress or completion of the Work.” Additionally, if plaintiff “believes that the alleged delay was occasioned for reasons beyond [its] control, [plaintiff] may also submit a claim to the Engineer to compensate [it] for such delay.” The engineer is then required to review the claim and if, in the engineer’s opinion, the claim is “justified,” issue a work order to cover the cost. If either plaintiff or defendant disputes the engineer’s opinion, then “the validity of the claim will be determined by arbitration.”

GC 35 relates to “Disputes and Arbitration.” It provides, in part:

“Differences between the parties to the Contract as to the interpretation, application, or administration of this Contract or any failure to agree where agreement between the parties is called for (herein collectively called the ‘Dispute’) which are not satisfactorily resolved in the first instance by a decision of the Engineer pursuant to the provisions of GC 5 - Engineer shall be settled in accordance with the provisions of this General Condition.”

GC 35 further provides that, if the party raising the “Dispute” disagrees with the engineer’s decision under GC 5, then that party may give “written notice to the other party” within 30 days of receiving the engineer’s decision that the party “requires the Dispute to be settled in accordance with [GC 35].” After receipt of that notice, the parties are required to “attempt to resolve the Dispute by agreement].]” If they are *325 unable to do so, either party may “refer such matter to arbitration for resolution,” provided that the dispute “is not excluded from the application of arbitration by [six enumerated exceptions.]” That arbitration requirement and the only one of the six exceptions that the parties assert is relevant here provide as follows:

“Except for disputes between [the parties] relating to:
"* * * * *
“35.5.6 The damages to which either [party] may be entitled at law on account of a breach of the Contract by the other of them;
“all disputes between [the parties] which are not settled satisfactorily either by the Engineer or by the agreement of [the parties] shall be resolved by arbitration in accordance with the following procedures [.]”

Finally, the “procedures” enumerated in GC 35 provide, among other things, that “The Arbitration Act of Oregon, for the time being in force, shall apply to any arbitration hearings.”

Due to various problems encountered during construction, plaintiff did not complete the project until after the scheduled completion date, and both parties incurred unanticipated expenses. Each party contends that the other is responsible for the delay and the resulting expenses.

II. PROCEEDINGS BELOW

In December 2001, plaintiff initiated this action for breach of contract and quantum meruit. Plaintiff alleged, among other things, that it had “incurred additional costs and expenses” due to “major delays and inefficiencies in performing the work” caused by defendant’s failure to perform under the contracts. Quoting GC 27, plaintiff also alleged in its complaint that the construction agreement between the parties provides that the validity of its claims “ ‘will be determined by arbitration.’ ”

Subsequently, the parties engaged in discovery in preparation for trial. On January 3,2003, plaintiff filed a second amended complaint, seeking $2.6 million in damages— the amount that plaintiff claimed that it had expended in *326 labor, materials, and equipment ($5 million) reduced by the amount that defendant had paid to plaintiff ($2.4 million)— and a petition to compel arbitration and to abate the action pending arbitration. See former ORS 36.310 (2001) (providing procedure for party to seek court order compelling arbitration); former ORS 36.315 (2001) (authorizing court to abate action of issue referable to arbitration). 2 On January 17, 2003, defendant filed a motion for summary judgment on the grounds that plaintiffs claims were barred by ORS 701.065

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lewis v. Varde
521 P.3d 522 (Court of Appeals of Oregon, 2022)
Bush v. City of Prineville (A165637)
457 P.3d 324 (Court of Appeals of Oregon, 2020)
Amalgamated Transit Union v. Tri-County Metro. Transp. Dist. of Or.
447 P.3d 50 (Court of Appeals of Oregon, 2019)
Alexander Loop, LLC v. City of Eugene
444 P.3d 1116 (Court of Appeals of Oregon, 2019)
Eugene Water & Elec. Bd. v. MWH Ams., Inc.
426 P.3d 142 (Court of Appeals of Oregon, 2018)
Lumm v. CC Servs., Inc.
414 P.3d 454 (Court of Appeals of Oregon, 2018)
Huntsinger v. BNSF Railway Co.
398 P.3d 403 (Court of Appeals of Oregon, 2017)
Butler Family Ltd. Partnership v. Butler Bros., LLC
388 P.3d 1135 (Court of Appeals of Oregon, 2017)
Couch Investments, LLC v. Peverieri
371 P.3d 1202 (Oregon Supreme Court, 2016)
Gozzi v. Western Culinary Institute, Ltd.
366 P.3d 743 (Court of Appeals of Oregon, 2016)
Delashmutt v. Parker Group Investments, LLC
366 P.3d 769 (Court of Appeals of Oregon, 2016)
Adair Homes, Inc. v. Dunn Carney Allen Higgins & Tongue, LLP
325 P.3d 49 (Court of Appeals of Oregon, 2014)
Gemstone Builders, Inc. v. Stutz
261 P.3d 64 (Court of Appeals of Oregon, 2011)
Harnisch v. College of Legal Arts, Inc.
259 P.3d 67 (Court of Appeals of Oregon, 2011)
Citigroup Smith Barney v. Henderson
250 P.3d 926 (Court of Appeals of Oregon, 2011)
VULCAN POWER CO. v. Munson
252 P.3d 511 (Colorado Court of Appeals, 2011)
Columbia Helicopters, Inc. v. Carson Helicopters, Inc.
407 F. App'x 89 (Ninth Circuit, 2010)
Snider v. Production Chemical Manufacturing, Inc.
230 P.3d 1 (Oregon Supreme Court, 2010)
Livingston v. METROPOLITAN PEDIATRICS, LLC
227 P.3d 796 (Court of Appeals of Oregon, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
142 P.3d 1044, 341 Or. 321, 2006 Ore. LEXIS 824, Counsel Stack Legal Research, https://law.counselstack.com/opinion/industramatrix-joint-venture-v-pope-talbot-inc-or-2006.