Adair Homes, Inc. v. Dunn Carney Allen Higgins & Tongue, LLP

325 P.3d 49, 262 Or. App. 273, 2014 WL 1493321, 2014 Ore. App. LEXIS 566
CourtCourt of Appeals of Oregon
DecidedApril 16, 2014
Docket101217771; A151203
StatusPublished
Cited by18 cases

This text of 325 P.3d 49 (Adair Homes, Inc. v. Dunn Carney Allen Higgins & Tongue, LLP) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Adair Homes, Inc. v. Dunn Carney Allen Higgins & Tongue, LLP, 325 P.3d 49, 262 Or. App. 273, 2014 WL 1493321, 2014 Ore. App. LEXIS 566 (Or. Ct. App. 2014).

Opinion

SERCOMBE, J.

This legal malpractice case arises from a law firm’s representation of a homebuilder in a case asserting breach of contract to construct a home brought by the home’s purchasers. Adair Homes, Inc.,1 entered into a home construction contract with Paul and Renee Haynes and constructed the home. After the home was built, the Hayneses filed breach of contract, breach of warranty, and other claims against Adair Homes. Dunn Carney Allen Higgins & Tongue, LLP (Dunn Carney), represented Adair Homes in that litigation. After the Hayneses prevailed, they sought attorney fees under a fee provision in the construction contract. The contract also contained an arbitration provision. On behalf of Adair Homes, Dunn Carney disputed the amount, but not the Hayneses’ entitlement to attorney fees. The trial court awarded attorney fees to the Hayneses.

Adair Homes then filed a legal malpractice claim against Dunn Carney. It claimed that Dunn Carney negligently failed to assert a viable defense to the attorney fee petition — that the Hayneses failed to comply with the construction contract requirement that they arbitrate the underlying dispute before seeking attorney fees — and that that failure caused it to suffer the damage of paying the attorney fee award.

The parties disagree on the meaning and application of the arbitration clause in the contract. Dunn Carney contends that the provision requires arbitration of “course of construction” disputes under the contract and not the post-construction claims on which the Hayneses prevailed. Adair Homes reads the provision more broadly, as covering all disputes arising from the parties’ contractual relationship, including post-construction claims. After the parties filed cross-motions for summary judgment on the application of the arbitration and attorney fee provisions in the contract, the trial court sided with Dunn Carney, concluding that the contract did not require arbitration as a precondition to filing the post-construction claims and then seeking [276]*276fees for those claims. In light of that construction of the contract, the trial court determined that Dunn Carney’s failure to assert an invalid defense caused Adair Homes no harm, and entered judgment in Dunn Carney’s favor. Adair Homes appeals.

For the reasons we explain below, we conclude that the contract is ambiguous. Moreover, we conclude that the existence of competing extrinsic evidence about the meaning of the ambiguous contract provisions presents a factual question that makes the meaning of the contract inappo-site for resolution on summary judgment. We accordingly reverse the judgment for Dunn Carney and remand the case for further proceedings.

In an appeal from a judgment involving cross-motions for summary judgment, both motions are subject to review if the parties have assigned error to the trial court’s rulings on them. We review the record for each motion in the light most favorable to the party opposing it to determine whether there is a genuine issue of material fact and, if not, whether the moving party is entitled to judgment as a matter of law. ORCP 47 C; Eden Gate, Inc. v. D&L Excavating & Trucking, Inc., 178 Or App 610, 622, 37 P3d 233 (2002).

On appeal, the parties generally reiterate the arguments that they made to the trial court. Briefly, each party contends that the contract is unambiguous and requires judgment in its favor as a matter of law. Adair Homes asserts that the trial court erred in construing the contract. It urges us to construe the contract as unambiguously requiring the arbitration of all disputes and to reverse and remand for entry of judgment in its favor. Dunn Carney argues that the trial court correctly construed the contract as unambiguously not applying to the post-construction disputes on which the Hayneses prevailed. Thus, Dunn Carney would have us uphold the judgment of the trial court in its favor.

Alternatively, Dunn Carney contends that, if we conclude that the contract is ambiguous, we should remand for a trial on all disputed issues, including causation, because the parties offered competing extrinsic evidence bearing on the applicability of the arbitration provision. As to that [277]*277alternative argument, Adair Homes argues that, if we conclude that the contract is ambiguous, we should not reverse and remand for a trial. Instead, Adair Homes contends that we should apply a presumption in favor of arbitrability and conclude, as a matter of law, that the contract requires arbitration of all disputes and, hence, that it was entitled to summary judgment.

To interpret a contractual arbitration provision, we apply ordinary principles of contract interpretation. Gemstone Builders, Inc. v. Stutz, 245 Or App 91, 95, 261 P3d 64 (2011); see also Industra/Matrix Joint Venture v. Pope & Talbot, 341 Or 321, 331, 142 P3d 1044 (2006) (stating same principle in context of contract subject to the Federal Arbitration Act). The goal is to determine whether the parties agreed to arbitrate a particular dispute. Gemstone Builders, Inc., 245 Or App at 95; Industra/Matrix Joint Venture, 341 Or at 331 (“A party cannot be required to submit to arbitration any dispute which it has not agreed so to submit.” (Internal quotation marks and brackets omitted.)); see also Granite Rock Co. v. International Broth. of Teamsters, 561 US 287, 299, 130 S Ct 2847, 177 L Ed 2d 567 (2010) (“Arbitration is strictly a matter of consent.” (Internal quotation marks omitted.)).

A party is entitled to summary judgment only if the terms of the contract are unambiguous on their face. Milne v. Milne Construction Co., 207 Or App 382, 388, 142 P3d 475, rev den, 342 Or 253 (2006). We review for legal error a ruling that a contract is unambiguous. Yogman v. Parrott, 325 Or 358, 361, 937 P2d 1019 (1997); Arlington Ed. Assn. v. Arlington Sch. Dist. No. 3, 196 Or App 586, 595, 103 P3d 1138 (2004).

The threshold to show ambiguity is not high. Milne, 207 Or App at 388; Central Oregon Independent Health Serv. v. OMAP, 211 Or App 520, 529, 156 P3d 97, rev den, 343 Or 159 (2007). A contract term is ambiguous if, when examined in the context of the contract as a whole and the circumstances of contract formation, it is susceptible to more than one plausible interpretation. Id.) see also PGF Care Center, Inc. v. Wolfe, 208 Or App 145, 151, 144 P3d 983 (2006) (a contract provision “is unambiguous only if its meaning is [278]*278so clear as to preclude doubt by a reasonable person” (internal quotation marks omitted)). If a contract’s provisions are internally inconsistent regarding a subject, then the contract is ambiguous regarding that subject. Madson v. Oregon Conf. of Seventh-Day Adventists, 209 Or App 380, 384, 149 P3d 217 (2006).

If a contract is ambiguous, and there is relevant competing extrinsic evidence to resolve the ambiguity, ascertaining the meaning of the contract involves a question of fact and the dispute over the contract’s meaning cannot be resolved on summary judgment. Abercrombie v. Hayden Corp., 320 Or 279, 292, 883 P2d 845 (1994); Dial Temporary Help Service v. DLF Int’l Seeds, 255 Or App 609, 612, 298 P3d 1234 (2013) (“[I]t is the existence of competing extrinsic evidence — and the triable factual issue that the evidence creates — that, as a general rule, makes the resolution of the meaning of an ambiguous contract on summary judgment inappropriate [.]”); see also Madson, 209 Or App at 389, 389 n 3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Verrall
344 Or. App. 752 (Court of Appeals of Oregon, 2025)
Frost v. Jacobs
Court of Appeals of Oregon, 2024
Winamaki v. Umpqua Bank
521 P.3d 846 (Court of Appeals of Oregon, 2022)
Homes Association of Cedar Hills v. Craig
515 P.3d 379 (Court of Appeals of Oregon, 2022)
Cryo-Tech, Inc. v. JKC Bend, LLC
495 P.3d 699 (Court of Appeals of Oregon, 2021)
Eugene Water & Elec. Bd. v. MWH Ams., Inc.
426 P.3d 142 (Court of Appeals of Oregon, 2018)
Alexander v. State
390 P.3d 1109 (Court of Appeals of Oregon, 2017)
Hawkins v. 1000 Ltd. Partnership
388 P.3d 347 (Court of Appeals of Oregon, 2016)
Mid-Valley Resources, Inc. v. Foxglove Properties, LLP
381 P.3d 910 (Court of Appeals of Oregon, 2016)
Graydog Internet, Inc. v. Giller
381 P.3d 903 (Multnomah County Circuit Court, Oregon, 2016)
Delashmutt v. Parker Group Investments, LLC
366 P.3d 769 (Court of Appeals of Oregon, 2016)
Grants Pass Imaging & Diagnostic Center, LLC v. Marchini
346 P.3d 644 (Court of Appeals of Oregon, 2015)
Herrera v. C & M Victor Co.
337 P.3d 154 (Court of Appeals of Oregon, 2014)
Yale Holdings, LLC v. Capital One Bank
326 P.3d 1259 (Court of Appeals of Oregon, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
325 P.3d 49, 262 Or. App. 273, 2014 WL 1493321, 2014 Ore. App. LEXIS 566, Counsel Stack Legal Research, https://law.counselstack.com/opinion/adair-homes-inc-v-dunn-carney-allen-higgins-tongue-llp-orctapp-2014.