Couch Investments, LLC v. Peverieri

371 P.3d 1202, 359 Or. 125, 2016 Ore. LEXIS 255
CourtOregon Supreme Court
DecidedApril 21, 2016
DocketCC 11CV0285SF; CA A155483; SC S063209
StatusPublished
Cited by13 cases

This text of 371 P.3d 1202 (Couch Investments, LLC v. Peverieri) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Couch Investments, LLC v. Peverieri, 371 P.3d 1202, 359 Or. 125, 2016 Ore. LEXIS 255 (Or. 2016).

Opinion

*127 WALTERS, J.

Leonard and Judith Peverieri and Peverieri Investments, LLC (landlords) appeal from the trial court’s general judgment confirming an arbitration award in favor of Couch Investments, LLC (tenant). Landlords argue that the arbitrator exceeded his powers when he found not only that landlords were liable for the cost of storm water drainage improvements required by the Department of Environmental Quality (DEQ), but also ordered remedies. Landlords contend that the trial court erred in denying their petition to vacate the arbitration award under ORS 36.705 (D(d), 1 and that the Court of Appeals erred in affirming the trial court’s judgment. Couch Investments, LLC v. Peverieri, 270 Or App 233, 346 P3d 1299 (2015). Although our analysis differs from that of the Court of Appeals, we affirm its decision.

The following facts are uncontested. Tenant operated a gas station on landlords’ property. Landlords filed a complaint seeking tenant’s eviction, alleging, among other things, that tenant was in default because tenant had failed to comply with “DEQ regulations pertaining to the capture of storm water from the area surrounding the fueling stations.” Tenant then filed a complaint against landlords, alleging intentional interference with economic relations and breach of the lease agreement and seeking injunctive relief. The two cases were consolidated and the parties signed a “stipulation to arbitrate and limit claims” (stipulation). The stipulation provided:

“1. The Parties have agreed to arbitrate the claims raised in the above actions. The Parties have mutually selected William E. Flinn to serve as the arbitrator. The arbitration is scheduled for December 18, 2012.
“2. The only issue to be resolved through arbitration is whether [tenant], as tenant, or [landlords], as landlord, are liable under the lease that is the subject of the above actions (the ‘Lease’) for the cost of storm water drainage *128 improvements required by the Oregon Department of Environmental Quality (the ‘DEQ Issue’).
“3. The Parties agree that David Cole of the DEQ may testify both through his affidavit and by phone, as well. The Parties disagree whether any other witness can provide relevant testimony on [the] DEQ Issue. The Parties, however, do agree that should the arbitrator allow any testimony to be offered on the DEQ Issue (other than Mr. Cole’s testimony), it will only be testimony of the Parties themselves.
“4. Other than the DEQ issue, all claims raised in the Parties’ pleadings will be dismissed by the Parties with prejudice.
“5. The prevailing party/parties on the DEQ Issue shall be entitled to recover its/their reasonable attorneys’ fees under the terms of the Lease.”

After a hearing, the arbitrator issued a letter opinion concluding that landlords were “liable for the cost of storm water drainage improvements to the leased premises required by the DEQ.” Tenant then submitted a proposed arbitration award, which stated, in part: “[Landlords are] liable for all costs associated with storm water drainage improvements ***. [Landlords] shall complete such improvements to the satisfaction of DEQ on or before [date left blank for the arbitrator to fill in].” Landlords submitted an objection to the proposed award, contending that the proposed award sought relief outside the stipulated agreement.

After hearing oral argument on landlords’ objections, the arbitrator issued a letter overruling the objections. In the letter, the arbitrator addressed the scope of the authority given to him by the parties’ stipulation and Oregon law. The arbitrator stated:

“ORS 36.695(3) says ‘an arbitrator may order such remedies as the arbitrator considers just and appropriate under the circumstances of the proceeding. The fact that such a remedy could not or would not be granted by the court is not a ground for refusing to confirm an award under ORS 36.700 or for vacating an award under ORS 36.705.’ In my opinion, the stipulation and the cited statutes give me the authority to make the following rulings on [landlords’] objections and, also, to make the findings, conclusions and awards found in the enclosed proposed arbitration award.”

*129 After a hearing regarding the cost of the required storm water drainage improvements, at which both sides presented additional evidence, the arbitrator issued an arbitration award. The arbitrator ordered that landlords pay $32,500 into tenant attorney’s client trust account and that tenant complete the necessary improvements and refund any excess funds to landlords with an accounting.

Tenant then filed a petition to enter the arbitration award in the circuit court, and landlords filed a petition to vacate the award on the basis that the arbitrator had exceeded his powers. The circuit court granted tenant’s petition, denied landlords’ petition, and entered a general judgment and money award confirming the arbitration award. Landlords appealed to the Court of Appeals. That court noted that ORS 36.695(3) gives arbitrators broad authority to order remedies unless the parties waive or vary that authority in accordance with ORS 36.610(1). Looking to the parties’ stipulation to arbitrate, the court concluded that because the parties had not explicitly agreed to “waive” or “vary the effect of’ ORS 36.695(3), and because there was no indication that the parties had intended to do so, the arbitrator did not exceed his powers. Couch Investments, LLC, 270 Or App at 235. Therefore, the court affirmed the trial court’s judgment. Id.

Before this court, landlords assert that the trial court erred in upholding the arbitrator’s award because the parties had agreed to limit the arbitrator’s authority to a determination of which party is liable for the costs of the improvements required by the DEQ. Landlords argue that the parties had not agreed to submit an entire claim to arbitration. Instead, they had agreed to submit only the limited issue of liability, and the arbitrator exceeded his powers when he went further and ordered remedies.

Tenant responds that arbitrators have broad authority to order remedies under ORS 36.695(3), which provides, in part:

“[A]n arbitrator may order such remedies as the arbitrator considers just and appropriate under the circumstances of the arbitration proceeding.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wolfston v. Eastside Bend, LLC
Court of Appeals of Oregon, 2023
Floor Solutions, LLC v. Johnson
520 P.3d 902 (Court of Appeals of Oregon, 2022)
Myhre v. Potter
507 P.3d 772 (Court of Appeals of Oregon, 2022)
McKeown v. McKeown
505 P.3d 455 (Court of Appeals of Oregon, 2022)
Creekside Homeowners Assn. v. Creekside Golf Course
505 P.3d 15 (Court of Appeals of Oregon, 2021)
Nieto v. City of Talent
436 P.3d 82 (Court of Appeals of Oregon, 2019)
In re Tucker
428 P.3d 945 (Court of Appeals of Oregon, 2018)
Law v. Zemp
Oregon Supreme Court, 2018
Comcast Corp. IV v. Dept. of Rev. (TC 4909)
22 Or. Tax 442 (Oregon Tax Court, 2017)
Hawkins v. 1000 Ltd. Partnership
388 P.3d 347 (Court of Appeals of Oregon, 2016)
Stonecrest Properties, LLC v. City of Eugene
382 P.3d 539 (Court of Appeals of Oregon, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
371 P.3d 1202, 359 Or. 125, 2016 Ore. LEXIS 255, Counsel Stack Legal Research, https://law.counselstack.com/opinion/couch-investments-llc-v-peverieri-or-2016.