GAMBLE ET UX v. Sukut

302 P.2d 553, 208 Or. 480, 1956 Ore. LEXIS 245
CourtOregon Supreme Court
DecidedOctober 24, 1956
StatusPublished
Cited by8 cases

This text of 302 P.2d 553 (GAMBLE ET UX v. Sukut) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
GAMBLE ET UX v. Sukut, 302 P.2d 553, 208 Or. 480, 1956 Ore. LEXIS 245 (Or. 1956).

Opinion

PERRY, J.

The defendant, a building contractor, entered into a written contract with the plaintiffs to construct for them a residence in Portland, Oregon. Article 19 of the contract provided as follows:

“Any disagreement arising out of this contract or from the breach thereof, shall be submitted to *482 arbitration and this agreement shall be specifically enforceable under the prevailing arbitration law, and judgment upon the award rendered may be entered in the highest court of the forum, state or federal, having jurisdiction. It is mutually agreed that the decision of the arbitrators shall be a condition precedent to any right of legal action that either party may have against the other.
“The parties may agree upon one arbitrator; otherwise there shall be three, one named in writing by each party of this contract within five days after notice of arbitration is served by either party upon the other, and a third arbitrator selected by these two arbitrators within five days thereafter. No one shall serve as an arbitrator who is in any way financially interested in this contract or in the affairs of either party thereto.
“At the written request of either party, at anytime prior to the complete appointment of arbitrators, as provided above, or in the event of any default or lapse in the proceeding, the arbitration shall be held under the Standard Form of Arbitration Procedure of The American Institute of Architects or of the Rules of the American Arbitration Association.”

On October 22, 1951, the plaintiffs directed the following letter to the defendant:

“Dear Mr. Sukut,
“Reference is hereby made to the contract between us for the construction of a residence building at 4125 S. W. Bertha Avenue, Portland, Oregon, dated September 21, 1950. The construction was to have been done in accordance with plans and specifications prepared by Halsey Jones, Designer.
“The following work is yet to be done to complete the contract.
“1. Stops installed on bathroom windows.
“2. Chimney opening in roof made weathertight.
*483 “3. Siding on east side of house to he brought to stair line.
“4. Basement walls made watertight.
“5. Screens installed in gutter downspouts.
“6. Leak stopped in east gutter.
“7. The plaster on the bedroom walls is pitting and flaking. As the specifications call for a guarantee against this condition we require this area to be refinished. If the plaster were to be removed and replaced, it would be necessary for us to move out of the house while this work was being done, and the floors would require refinishing at the concusión [sic] of the work. In order to avoid this expense, we will accept canvas covering and repainting.
“8. The plaster on the lavatory, stair hall and stairway walls is pitting and flaking. We require these areas to be refinished in accordance with the specifications, and repainted. We remind you at this time that these areas have been painted twice at our expense.
“9. The plaster on the stairway ceiling is so rough that a true surface has not been obtained in spite of the fact that it has been painted twice. We require that this ceiling be refinished to a true surface and repainted.
“10. The City of Portland through the office of the City Engineer has notified us by letter that the driveway entrance from the street line to the sidewalk is not in conformity with city requirements. We require that this area be torn up and replaced to conform to these requirements.
“In order that we may know our position, and what further action to take regarding the above, if such is required, we ask that you reply to this letter before October 30, 1951.”
*484 On October 27, 1951, tbe defendant acknowledged receipt of the letter, and suggested that the matter be submitted to arbitration in accordance with Article 19 of the contract. On November 2, 1951, the plaintiffs advised the defendant that they were agreeable to arbitration, and that they had selected Mr. George M. Post of Portland as their arbitrator. On December 3, 1951, the plaintiffs, through their attorney, notified the defendant that unless arbitration was commenced at once they would within ten days from the date defendant received the letter petition the circuit court of Multnomah county for an order for specific performance of the arbitration agreement. Thereafter, the plaintiffs commenced this suit under OES 33.230 to compel specific performance of the arbitration agreement provided in Article 19 of the contract. The parties waived trial by jury, and the trial judge, being satisfied “that the making of the contract or submission or the failure to comply therewith is not an issue,” entered an “order directing the parties to proceed to arbitration in accordance with the terms of the contract,” the court’s order reading in part as follows:
“That said three arbitrators shall proceed to investigate the disputes as set forth under the ten items in the files and records herein and resolve said disputed items and the entire controversy by action of two out of three arbitrators.”

The “ten items” referred to in the order of arbitration are the same as those set out in the plaintiffs’ letter dated October 22, 1951, hereinbefore set forth. On October 14, 1953, an arbitration report was made to the trial court as follows:

“We, the undersigned, of the duly authorized Arbitrators designated, and to whom were sub *485 mitted matters in controversy between the parties in the above entitled matter, having been duly sworn, according to law, and having duly heard the proof and allegations, and considered the same, award as follows, in favor of plaintiffs as itemized:
ITEM NO. Material Labor
1 Install stops on bathroom windows $ 3.00 $ ' 7.65
2 Chimney opening in roof made weathertight 11.70 10.00
3 Siding on East Side, etc. 23.00 40.80
4 Basement walls made watertight 25.00 50.00
5 Screens in gutter 10.00 5.00
6 Repair leak in east gutter 5.00 25.00
7-8-9 Repair plaster and re- ' decorate 600.00
10 Complete concrete driveway, etc. 25.00 75.00
$ 702.70 $ 213.45
Total Labor and material Contingent-—-10% $ 916.15 91.61
$1,007.76
Contractor’s Profit— 10% 100,77
$1,108.53

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Couch Investments, LLC v. Peverieri
371 P.3d 1202 (Oregon Supreme Court, 2016)
Couch Investments, LLC v. Peverieri
346 P.3d 1299 (Court of Appeals of Oregon, 2015)
Russell v. Kerley
978 P.2d 446 (Court of Appeals of Oregon, 1999)
Russell v. World Famous, Inc.
767 P.2d 456 (Court of Appeals of Oregon, 1989)
Peter Kiewit Sons' Co. v. Port of Portland
628 P.2d 720 (Oregon Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
302 P.2d 553, 208 Or. 480, 1956 Ore. LEXIS 245, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gamble-et-ux-v-sukut-or-1956.