In Re the Arbitration Between Atlanta Shipping Corp. & Cheswick-Flanders & Co.

463 F. Supp. 614, 1978 U.S. Dist. LEXIS 6993
CourtDistrict Court, S.D. New York
DecidedDecember 27, 1978
Docket78 Civ. 3517 (CHT)
StatusPublished
Cited by11 cases

This text of 463 F. Supp. 614 (In Re the Arbitration Between Atlanta Shipping Corp. & Cheswick-Flanders & Co.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re the Arbitration Between Atlanta Shipping Corp. & Cheswick-Flanders & Co., 463 F. Supp. 614, 1978 U.S. Dist. LEXIS 6993 (S.D.N.Y. 1978).

Opinion

OPINION

TENNEY, District Judge.

On August 1, 1978, Atlanta Shipping Corp. (“Atlanta”) commenced this action by filing a petition to compel arbitration between it and Cheswick-Flanders & Co. (“Cheswick”). Atlanta subsequently moved pursuant to section 4 of the Federal Arbitration Act, 9 U.S.C. § 4 (the “Act”), for an order compelling the arbitration. Cheswick opposes the motion, but it also demands, in the alternative, arbitration on claims it *616 made in its Answer to the Petition. For the reasons given below, Atlanta’s motion is granted, and it is further ordered that the claims contained in Cheswick’s counterdemand be arbitrated.

Background

Atlanta alleges that on May 31, 1978, as owner of the ILSE SCHULTE, it entered a written contract of voyage charter party (“charter party”) with Cheswick, pursuant to which charter party Atlanta placed the vessel at the disposal of Cheswick at Houston, Texas in June 1977. There the vessel was loaded with corn, which was subsequently carried to Tema, Ghana, where the vessel was delayed for 14 days, 23 hours, and ten minutes beyond the allowable time for discharge of cargo. Atlanta subsequently billed Cheswick $59,861.20 for this delay time (demurrage). Alleging that a failure by Atlanta to comply with the charter party caused the delay in Tema, Cheswick has refused to pay the demurrage charges.

Atlanta further alleges that an arbitration clause was attached to and incorporated in the charter party, by which clause the parties are to refer any dispute between them to arbitrators in New York. 1 Pursuant to that arbitration clause, Atlanta demanded arbitration and appointed its arbitrator. Letter from Philip J. Curtin to Cheswick, dated Feb. 9, 1978, attached as Exhibit B to Notice of Motion. Cheswick then nominated its arbitrator and advised Atlanta that Cheswick would soon select legal counsel. Letter from B. L. Courtman to Zock, Petrie, Reid & Curtin, dated Mar. 14, 1978, attached id. as Exhibit C. Atlanta next advised Cheswick that the third arbitrator had been selected and asked for the name of the latter’s legal counsel so that a date for arbitration could be set. Letter from Philip J. Curtin to Cheswick, dated Apr. 19, 1978, attached id. as Exhibit D. Because Cheswick failed to reply by late May, Atlanta wrote the panel of arbitrators asking them to set a date for the first hearing. Id. Exhibit E.

Correspondence between counsel for the two parties followed. Counsel for Cheswick asked for information and for more time to review the matter, explaining that “we do not often become involved in these types of disputes.” Id. Exhibit F. Counsel for Atlanta provided the information requested and asked Cheswick for a prompt decision on whether to proceed with arbitration. Id. Exhibit G. Finally, Cheswick, by its counsel, responded that it would not submit to arbitration, explaining that the arbitration clause was ambiguous and that it would not be bound by the clause. It would “express no opinion” as to the legal effect of the panel’s having already been selected. Finally, Cheswick alleged that Atlanta breached the charter party because the ship arrived in Tema late, causing infestation of the grain cargo, which in turn allegedly caused claims to be made against Cheswick and resulted in the excess discharge time. Id. Exhibit H.

Atlanta argues that the charter party is a valid contract containing an unambiguous arbitration agreement that falls under section 1 of the Act, that the petition was served on Cheswick pursuant to section 4 of the Act, that Cheswick’s appointment of an arbitrator must be viewed as a voluntary submission of the matter to arbitration, and that, accordingly, Atlanta is entitled to an order directing that arbitration proceed in the manner provided in the charter party. Cheswick responds that the Court lacks the personal and subject matter jurisdiction and venue to issue such an order. It argues further that the Petition fails to allege the existence of a valid charter party and that the Petition must therefore be dismissed. Finally, Cheswick argues that the arbitra *617 tion clause is not valid because it is ambiguous. Cheswick asserts that these last two issues are for the Court to decide, if it has jurisdiction, before it may direct arbitration.

Discussion

Section 4 of the Act entitles “[a] party aggrieved by the alleged failure, neglect, or refusal of another to arbitrate under a written agreement for arbitration” to petition any United States district court with jurisdiction “for an order directing that such arbitration proceed in the manner provided for in such agreement.” The Court has subject matter jurisdiction because this action is one in admiralty. See id. Before ordering the parties to proceed with arbitration, however, the Court must be “satisfied that the making of the agreement for arbitration or the failure to comply therewith is not in issue.” Id. If there is a genuine issue as to whether the controversy is referable to arbitration, the Court must proceed summarily to a trial of the issue. Id.; see, e. g., Interocean Shipping Co. v. National Shipping and Trading Corp., 462 F.2d 673, 676 (2d Cir. 1972); Almacenes Fernandez, S.A. v. Golodetz, 148 F.2d 625, 628 (2d Cir. 1945). Because it is Cheswick’s position that the existence of the alleged agreement is in issue, Memorandum at 8-9, the Court will address this assertion before proceeding to the jurisdictional question. 2

The Contract

To make out a genuine issue as to the existence of an alleged contract, a party must deny unequivocally the existence of the contract, and it should offer some evidence to substantiate the denial. Golodetz, supra, 148 F.2d at 628; accord, Interocean Shipping Co., supra, 462 F.2d at 676. Cheswick has failed to meet that standard. It refers to the fact that it had not signed the charter party. Memorandum at 2. It signature, however, is unnecessary to a finding that a valid contract exists. A/S Custodia v. Lessin International, Inc., 503 F.2d 318, 320 (2d Cir. 1974); Fisser v. International Bank, 282 F.2d 231, 233 (2d Cir. 1960); Starkman v. Seroussi, 377 F.Supp. 518, 522 (S.D.N.Y.1974). Rather, general contract principles are applicable, and the question is whether the parties reached a meeting of the minds. A/S Custodia, supra; Fisser, supra; Starkman, supra.

On these facts, the inescapable conclusion is that the parties had reached a meeting of the minds on some

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
463 F. Supp. 614, 1978 U.S. Dist. LEXIS 6993, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-the-arbitration-between-atlanta-shipping-corp-cheswick-flanders-nysd-1978.