In Re Peterson v. Hawaii Electric Light Co.

944 P.2d 1265, 85 Haw. 322, 1997 Haw. LEXIS 75
CourtHawaii Supreme Court
DecidedSeptember 5, 1997
Docket18024
StatusPublished
Cited by50 cases

This text of 944 P.2d 1265 (In Re Peterson v. Hawaii Electric Light Co.) is published on Counsel Stack Legal Research, covering Hawaii Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Peterson v. Hawaii Electric Light Co., 944 P.2d 1265, 85 Haw. 322, 1997 Haw. LEXIS 75 (haw 1997).

Opinions

LEVINSON, Justice.

The complainant-appellant Mark L. Peterson appeals the Public Utilities Commission’s (PUC) Decision and Order (D & 0) No. 13198, filed on April 4, 1994, dismissing his complaint against the Hawai'i Electric Light Company (HELCO) based upon the PUC’s determination that HELCO’s PohoiM Transmission Line No. 2 (PTL No. 2) was in substantial compliance with PUC’s D & 0 No. 10620. On appeal, we are asked to review the PUC’s finding that the PTL No. 2 was in substantial compliance with D & 0 No. 10620. We need not address this issue because we hold that this court lacks appellate jurisdiction to hear a direct appeal from a PUC order dismissing a complaint that merely alleges error in the placement of transmission lines. Accordingly, we dismiss this appeal for lack of appellate jurisdiction.

I. BACKGROUND

This appeal’ arises from HELCO’s construction of two overhead, sixty-nine Mlovolt (kv) transmission lines that interconnect Puna Geothermal Venture’s (PGV) geothermal facility at PohoiM, on the Island of Ha-wai'i, with HELCO’s electric system located near its Puna substation. These lines transmit power generated by PGWs geothermal facility so that the power can be distributed to HELCO’s customers.

In preparation for the construction of the transmission lines, a routing study and an environmental impact statement (EIS) were prepared. The routing study was prepared on HELCO’s behalf by DHM, Inc. (DHM), an engineering consulting firm; in the routing study, DHM located optimum “transmission corridors” based on “opportunities and constraints” pertaining to placement of the lines, such as land use, special conservation restrictions, geographic features, and existing transportation and utility infrastructures. The routing study then located two proposed route alignments within the transmission corridors through further study of environmental, geographic, and economic factors; the placement of one of these route alignments is at the heart of the present dispute.

Portions of the proposed alignments passed through state conservation district and state-owned agricultural land. Because the project proposed the possible use of state lands in those areas, an environmental assessment by the Department of Land and Natural Resources (DLNR) was required pursuant to Hawai'i Revised Statutes (HRS) ch. 343. As part of its assessment, the DLNR determined that an EIS was required. Accordingly, DHM prepared and submitted an EIS on HELCO’s behalf. Thereafter, the DLNR approved the routing of the lines, portions of which passed through the Nánáwale Forest Reserve.

On September 6, 1989, both the routing study and the EIS were submitted in support of HELCO’s application to the PUC for approval of the placement of the transmission lines. Approval by the PUC is required pursuant to (1) HRS § 269-27.5 (1993), which requires PUC approval for the construction of new overhead transmission lines in excess of forty-six kv through residential areas, and (2) PUC General Order No. 7, which requires PUC approval for any expenditure by a utility exceeding $500,000. After the requisite public hearing, the PUC issued D & O No. 10620 on May 8, 1990, approving HELCO’s request to construct the transmission lines. In particular, D & O No. 10620 ruled that

[t]he Commission finds that the construction of the proposed transmissions lines is necessary, if HELCO is to be assured of [325]*325firm capacity from PGV. The capacity to be furnished by PGV is required to improve HELCO’s service reliability in the Puna area. The Commission further finds that the construction of the overhead fines is reasonable, will be safe and prudent, and is in the public interest.

Furthermore, D & 0 No. 10620 contained a general description of the placement of the proposed transmission lines. Specifically, PTL No. 2 was characterized in D & 0 No. 10620 as being

18.2 miles long. It will originate on the northern edge of the geothermal site, cross Kapoho Road, and head northwest across open vacant land to the edge of Nanawale Farm ranch lands. It will then continue along the outside edge of the ranch lands and Nanawale Estates subdivision to the northeast corner of Nanawale Estates subdivision.

Peterson purchased certain real property in September 1990, several months after the PUC authorized the placement of HELCO’s transmission fines. As constructed, PTL No. 2 skirted Peterson’s property, at its closest point, by approximately 150 feet. The sellers of Peterson’s property had not informed him of then-ongoing negotiations, in which HEL-CO was involved, to acquire an easement over the property, or of any imminent threat of condemnation. Apparently, it was only in November 1992 that it became evident to Peterson that HELCO had entered into an agreement with a neighboring landowner to locate the transmission fine on the parcel adjacent to Peterson’s property. Thus, as constructed, PTL No. 2 did not follow the precise route described in D & O No. 10620. However, except for those portions near Peterson’s property and the Puna substation, PTL No. 2 followed the general route described in D & O No. 10620.

On December 8, 1992, Peterson filed a formal complaint with the PUC alleging that HELCO had violated D & O No. 10620 when it failed to construct PTL No. 2 in exact conformity therewith. On April 6, 1994, after an extensive hearing, the PUC issued D & O No. 13198, dismissing his complaint. In its order, the PUC concluded that the description of PTL No. 2 contained in D & O No. 10620 was not meant to dictate final placement of the fine, but, rather, was a “proposed” alignment. Furthermore, the PUC determined that the deviations from D & O No. 10620 were not substantial and were only a result of negotiations with the landowner over whose property the fine was intended to pass. Thus, because the final alignment of PTL No. 2 was understood to be subject to negotiations for rights-of-way with affected landowners, the PUC concluded that HELCO was not required to obtain additional PUC approval for the final alignment of PTL No. 2. Therefore, inasmuch as the final alignment of PTL No. 2 substantially followed the general route described in D & O No. 10620, Peterson’s complaint was dismissed.

Peterson filed his notice of appeal from D & O No. 13198 on May 4,1994.

II. DISCUSSION

A. Principles Of Appellate Jurisdiction

Peterson primarily relies upon HRS § 269-16 as the jurisdictional basis for his appeal of D & O No. 13198. HRS § 269-16 (1993) provides in relevant part:

Regulation of utility rates; ratemak-ing procedures, (a) All rates, fares, charges, classifications, schedules, rules, and practices made, charged, or observed by any public utility ..., shall be just and reasonable and shall be filed with the public utilities commission....
To the extent that the contested case proceedings referred to in chapter 91[1] are required in any rate proceeding ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rosehill v. State of Hawai'i.
556 P.3d 387 (Hawaii Supreme Court, 2024)
State v. Bowman
346 P.3d 249 (Hawaii Intermediate Court of Appeals, 2015)
Asato v. Procurement Policy Board, State of Hawaii.
322 P.3d 228 (Hawaii Supreme Court, 2014)
Alohacare v. Department of Human Services, State of Hawaii.
276 P.3d 645 (Hawaii Supreme Court, 2012)
In re Tawhiri Power LLC
269 P.3d 777 (Hawaii Intermediate Court of Appeals, 2012)
Davis v. FOUR SEASONS HOTEL LTD.
810 F. Supp. 2d 1145 (D. Hawaii, 2011)
HUI MALAMA I NA KUPUNA O NEI v. Wal-Mart
223 P.3d 236 (Hawaii Intermediate Court of Appeals, 2009)
Save Diamond Head Waters LLC. v. Hans Hedemann Surf, Inc.
211 P.3d 74 (Hawaii Supreme Court, 2009)
State v. Nakamura
214 P.3d 1107 (Hawaii Intermediate Court of Appeals, 2009)
In Re TC
214 P.3d 1082 (Hawaii Intermediate Court of Appeals, 2009)
HAWAII MEDICAL SERVICE ASS'N v. Adams
209 P.3d 1260 (Hawaii Intermediate Court of Appeals, 2009)
State v. Woodfall
206 P.3d 841 (Hawaii Supreme Court, 2009)
County of Kaua'i v. Office of Information Practices
200 P.3d 403 (Hawaii Intermediate Court of Appeals, 2009)
County of Kauai v. OIP
200 P.3d 403 (Hawaii Intermediate Court of Appeals, 2009)
State v. Kim
196 P.3d 323 (Hawaii Intermediate Court of Appeals, 2008)
State v. Heggland
193 P.3d 341 (Hawaii Supreme Court, 2008)
State v. Bayly
185 P.3d 186 (Hawaii Supreme Court, 2008)
Right to Know Committee v. City Council
175 P.3d 111 (Hawaii Intermediate Court of Appeals, 2008)
Kamaka v. Goodsill Anderson Quinn & Stifel
176 P.3d 91 (Hawaii Supreme Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
944 P.2d 1265, 85 Haw. 322, 1997 Haw. LEXIS 75, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-peterson-v-hawaii-electric-light-co-haw-1997.