In re Application of Columbus S. Power Co.

2014 Ohio 462, 8 N.E.3d 863, 138 Ohio St. 3d 448
CourtOhio Supreme Court
DecidedFebruary 13, 2014
Docket2012-0187
StatusPublished
Cited by36 cases

This text of 2014 Ohio 462 (In re Application of Columbus S. Power Co.) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Application of Columbus S. Power Co., 2014 Ohio 462, 8 N.E.3d 863, 138 Ohio St. 3d 448 (Ohio 2014).

Opinions

Lanzinger, J.

I. Summary

{¶ 1} This second appeal stems from the approval by the Public Utilities Commission (“commission” or “PUCO”) of the first electric security plan of the American Electric Power operating companies, Columbus Southern Power Company and Ohio Power Company (collectively, “AEP”). We first reviewed the commission’s approval of the electric security plan in 2011. In re Application of Columbus S. Power Co., 128 Ohio St.3d 512, 2011-Ohio-1788, 947 N.E.2d 655. There, we held that the commission committed reversible error on three issues: (1) granting AEP a retroactive rate increase (but finding that no refund was available), (2) approving the recovery of carrying costs associated with environmental investments without proper statutory authority, and (3) authorizing the provider-of-last-resort (“POLR”) charge without sufficient evidence. We remanded the POLR-charge and carrying-costs issues for further consideration. Id. at ¶ 8-21, 31-35, 22-30.

{¶ 2} On remand, the commission determined that the environmental-investment carrying costs were lawful under R.C. 4928.143(B)(2)(d). In re Application of Columbus S. Power Co., Pub. Util. Comm. Nos. 08-917-EL-SSO and 08-918-EL-SSO, at 14-15 (Oct. 3, 2011) (the “Remand Order”). But the commission [449]*449found that AEP had not presented evidence of its actual POLR costs and directed the company to deduct that charge from its tariff schedules. Id. at 22-24. The commission also rejected a request to recover the amounts of the POLR charge and carrying costs that AEP had collected from April 2009 through May 2011. Id. at 34-36.

{¶ 3} Following rehearing, the Office of Consumers’ Counsel (“OCC”) and Industrial Energy Users-Ohio (“IEU”) filed this appeal, raising numerous challenges to the commission’s remand orders. None has merit. Therefore, we affirm the orders of the commission.

II. Facts and Procedural Background

{¶4} R.C. 4928.141(A) requires electric-distribution utilities to provide to consumers a “standard service offer of all competitive retail electric services necessary to maintain essential electric service to consumers, including a firm supply of electric generation service.” The utility may provide the offer in one of two ways: through a “market rate offer” under R.C. 4928.142 or through an “electric security plan” under R.C. 4928.143.

{¶ 5} AEP chose the second option and filed an application for approval of an electric security plan (“ESP”). The ESP statute permits numerous rate components, R.C. 4928.143(B)(2), but says very little about rate calculation. The only substantive requirement is that the plan must be “more favorable in the aggregate as compared to the expected results” of a market-rate offer. R.C. 4928.143(C)(1).

A. ESP approval and court remand

{¶ 6} On March 18, 2009, the commission issued an opinion and order approving AEP’s first ESP, to be in effect from 2009 to 2011. In re Application of Columbus S. Power Co., Pub. Util. Comm. Nos. 08-917-EL-SSO and 08-918-EL-SSO (Mar. 18, 2009) (the “ESP Order ”). Following two rounds of rehearings, OCC and IEU appealed. We eventually held that the commission had granted AEP a retroactive rate increase of $63 million in violation of R.C. 4928.141(A), as well as the rule established in Keco Industries, Inc. v. Cincinnati & Suburban Bell Tel. Co., 166 Ohio St. 254, 141 N.E.2d 465 (1957). Nevertheless, OCC had not established that it was entitled to its requested remedy of a refund, and that ruling was conclusive of the issue. In re Application of Columbus S. Power Co., 128 Ohio St.3d 512, 2011-Ohio-1788, 947 N.E.2d 655, ¶ 8.

{¶ 7} We also held that the commission erred when it found that AEP could recover environmental-investment carrying costs under R.C. 4928.143(B)(2). We remanded the matter to allow the commission to specifically determine whether [450]*450any of the nine categories of cost recovery under R.C. 4928.143(B)(2)(a) through (i) authorized the recovery of carrying costs. Id. at ¶ 31-35.

{¶ 8} Finally, we determined that the commission approved more than $500 million in POLR charges over the three years of the plan. Id. at ¶ 22. POLR costs are intended to compensate for the utility’s risks in standing ready to serve customers who purchase generation service from a competitive supplier and then return to the utility for generation service. See Constellation NewEnergy, Inc. v. Pub. Util. Comm., 104 Ohio St.3d 530, 2004-Ohio-6767, 820 N.E.2d 885, ¶ 39, fn. 5. AEP had calculated its POLR costs for the commission using a mathematical formula (called the “Black-Scholes model”) that was created to price stock options. We held that contrary to the commission’s finding, the formula did not reflect the costs to AEP to be the POLR. 128 Ohio St.3d 512, 2011-Ohio-1788, 947 N.E.2d 655, ¶ 25-30.

{¶ 9} The case was remanded to allow the commission the option to consider whether (1) “a non-cost-based POLR charge is reasonable and lawful” or (2) “it is appropriate to allow AEP to present evidence of its actual POLR costs.” Id. at ¶ 30.

B. Remand proceedings

{¶ 10} On remand, the commission issued its May 25, 2011 order, directing that AEP file revised tariffs making the recovery of environmental-investment carrying costs and the POLR charge subject to refund as of the first billing cycle of June 2011. The order provided that if the commission ultimately determines that these charges are to be refunded to customers, interest may be imposed on the amounts collected by AEP in the interim.

{¶ 11} Following a five-day hearing, the commission issued its opinion and order on October 3, 2011. The commission determined that the environmental-investment carrying costs were lawful under R.C. 4928.143(B)(2)(d). Remand Order at 14-15. Because the commission approved the recovery of carrying costs, no refund was ordered of those that were collected during the remand proceedings.

{¶ 12} In addition, because the commission found that AEP had failed to submit any evidence of its actual POLR costs, it ordered AEP to remove the POLR charge from its tariffs. Remand Order at 22-24 and 33. And consistent with its May 25, 2011 order, it also directed AEP to refund to customers the amount of the POLR charges collected during the remand proceedings (i.e., from the first billing cycle in June 2011 until the October 3, 2011 remand order). Id. at 33-34. The ESP was set to expire at the end of 2011, which was two months after the commission’s remand order and two weeks after the final rehearing entry. As a result, AEP was able to collect nearly all of its POLR costs during [451]*451the term of the ESP, except from June 2011 to December 2011 (the end of the ESP).

{¶ 13} During the remand proceedings, OCC and IEU had also requested that the commission allow customers to recover the POLR and environmental-investment carrying charges that AEP had collected from April 2009 through May 2011 (when those charges became subject to refund by order of the commission on remand). In the initial ESP proceedings, the commission had allowed AEP to phase in its rate increase by deferring the recovery of a portion of annual fuel costs incurred during the ESP period.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ori Group, L.L.C. v. Nicols
2025 Ohio 5222 (Ohio Court of Appeals, 2025)
In re Application of Dayton Power & Light Co.
2025 Ohio 2953 (Ohio Supreme Court, 2025)
In re Application of E. Ohio Gas Co.
2023 Ohio 3289 (Ohio Supreme Court, 2023)
Miller v. Mission Essential Group, L.L.C.
2023 Ohio 3077 (Ohio Court of Appeals, 2023)
State v. Wilson
2022 Ohio 3202 (Ohio Supreme Court, 2022)
Shaker House, L.L.C. v. Daniel
2022 Ohio 2778 (Ohio Court of Appeals, 2022)
Ewing v. UC Health
2022 Ohio 2560 (Ohio Court of Appeals, 2022)
Everhart v. Coshocton Cty. Mem. Hosp.
2022 Ohio 629 (Ohio Court of Appeals, 2022)
Diller v. Diller
2021 Ohio 4252 (Ohio Court of Appeals, 2021)
State ex rel. Swanson v. Ohio Dept. of Rehab. & Corr.
2021 Ohio 338 (Ohio Court of Appeals, 2021)
State ex rel. Summers v. Fox (Slip Opinion)
2020 Ohio 5585 (Ohio Supreme Court, 2020)
In re Application of Ohio Power Co. (Slip Opinion)
2020 Ohio 143 (Ohio Supreme Court, 2020)
In re Application of Ohio Edison Co. (Slip Opinion)
2019 Ohio 2401 (Ohio Supreme Court, 2019)
In re Application of Dayton Power & Light Co. (Slip Opinion)
2018 Ohio 4009 (Ohio Supreme Court, 2018)
In re Application of Buckeye Wind, L.L.C. (Slip Opinion)
2016 Ohio 5664 (Ohio Supreme Court, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
2014 Ohio 462, 8 N.E.3d 863, 138 Ohio St. 3d 448, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-application-of-columbus-s-power-co-ohio-2014.