In re Application of Columbus S. Power Co.

2011 Ohio 2383, 129 Ohio St. 3d 46
Ohio Supreme Court·Decided May 24, 2011·No. 2010-1533·Published·Cited by 3 cases

Opinion

Lundberg Stratton, J.

{¶ 1} In the case below, the Public Utilities Commission approved a “program portfolio plan” proposed by the American Electric Power (“AEP”) operating companies. The plan, developed in consultation with a wide array of interested parties, contains a variety of programs that are designed to increase energy efficiency and reduce peak demands on AEP’s system. Such programs are required by law. R.C. 4928.66(A)(1).

{¶ 2} Industrial Energy Users-Ohio (“IEU”) appeals from the commission’s approval of the plan on four grounds. None of its arguments compels reversal, and we affirm.

Background

{¶ 3} Under R.C. 4928.66, electric-distribution utilities must implement programs to increase energy efficiency and to reduce peak demand. R.C. 4928.66(A)(1)(a) and (b). Energy-efficiency measures reduce the amount of *47 energy required to perform tasks. Ohio Adm.Code 4901:l-39-01(L). “Peak demand” refers to the measure of electricity usage at the time when the most energy is being consumed simultaneously. Ohio Adm.Code 4901:l-39-01(R). Reducing peak demand, other things being equal, lowers the price of power and forestalls the need to add new generation plants. See, e.g., Natural Resources Defense Council, Inc. v. Herrington (C.A.D.C.1985), 768 F.2d 1355, 1414 (discussing benefits of peak-demand reductions). The statute imposes annual goals in both categories, R.C. 4928.66(A)(1)(a) and (b), and if an electric-distribution utility does not meet the goals, the law authorizes forfeitures, R.C. 4928.66(C).

{¶ 4} The statute also allows the commission to approve “a revenue-decoupling mechanism.” R.C. 4928.66(D). Such mechanisms separate (or “decouple”) the recovery of fixed distribution costs from the volume of sales. Before it can approve a proposed revenue-decoupling mechanism, the commission must determine two things: first, that the mechanism “provides for the recovery of revenue that otherwise may be foregone by the utility as a result of or in connection with the implementation by the electric distribution utility of any energy efficiency or energy conservation programs,” and second, that the mechanism “reasonably aligns the interests of the utility and of its customers in favor of those programs.” Id.

{¶ 5} On November 12, 2009, the AEP operating companies, Columbus Southern Power (“CSP”) and Ohio Power Company, filed an application seeking approval of a “Three-Year Program Portfolio Plan,” which presented a three-year approach to meeting the companies’ energy-efficiency and peak-demand-reduction goals. The plan had been developed in consultation -with a group of interested parties, and along with the plan, the companies filed a stipulation to help resolve various issues. Among other things, the stipulation provided AEP with a revenue-decoupling mechanism, which the parties expected to run for three years.

{¶ 6} IEU opposed the stipulation. It intervened, lodged objections to the portfolio plan, and sponsored testimony in support of its objections.

{¶ 7} The commission held a hearing on the stipulation on February 25, 2010, and on May 13, it issued an order modifying and approving the stipulation. One of the modifications pertained to the proposed decoupling mechanism. Instead of allowing the mechanism to run for three years (and thus end sometime in 2013), the commission prescribed an end date of January 1, 2011. This limitation on the period in which AEP could recover forgone revenue reflected the commission’s concern whether the companies’ distribution rates — which had last been reviewed in 1991 (CSP) and 1994 (Ohio Power Company) — accurately reflected their costs. The commission “encouraged” the companies “to propose a mechanism to answer the Commission’s concern regarding quantification of fixed costs.”

*48 {¶ 8} IEU filed an application for rehearing, which the commission denied on July 14. This appeal followed. Apparently due to a filing error before the commission, IEU appealed the order only as it pertained to CSP and not to its sister company, Ohio Power Company. CSP has intervened as an appellee.

Discussion

{¶ 9} IEU raises four propositions of law. All lack merit, and accordingly we affirm.

A. IEU has not shown that the commission erred in modifying and approving the revenue-decoupling mechanism

{¶ 10} In its first proposition of law, IEU challenges the commission’s approval of CSP’s requested decoupling mechanism. The commission actually agreed with IEU’s contention that “the record fails to establish what revenue is necessary to provide AEP-Ohio with the opportunity to recover its costs and to earn a fair and reasonable return.” But rather than disapprove the decoupling mechanism altogether, the commission shortened its lifespan from three years to about seven months.

{¶ 11} We agree with IEU that the commission’s reasoning had a serious flaw — which we address below — but at the same time, we do not see that the flaw warrants reversal.

1. The outcome of the order was reasonable and lawful

{¶ 12} IEU’s argument assumes that CSP was required to prove “ ‘what revenue is necessary to provide [it] with the opportunity to recover its costs and to earn a fair and reasonable return.’ ” According to IEU, this cost-of-service evidence is required by R.C. 4928.66(D) and Ohio Adm.Code 4901:l-39-07(A). We disagree.

{¶ 13} We can quickly dispense with the administrative-rule argument made by IEU. Ohio Adm.Code 4901:l-39-07(A) contains no requirement that utilities demonstrate their cost of service. It simply allows “appropriate lost distribution revenues.”

{¶ 14} As for the statute, R.C. 4928.66(D) contains two requirements that an application for a revenue-decoupling mechanism must meet before the commission may approve it, but IEU does not explain which one it alleges was not met, and we fail to see any statutory violation.

{¶ 15} The first requirement is that the decoupling mechanism provide only for “the recovery of revenue that otherwise may be foregone by the utility as a result of or in connection with the implementation by the electric distribution utility of any energy efficiency or energy conservation programs.” This clause does not require the commission to find that the recovery of the lost revenue is necessary *49 to recover costs and to ensure a fair rate of return. In fact, the word “revenue” means the opposite: it means “[gr]ross income or receipts.” (Emphasis added.) Black’s Law Dictionary (8th Ed.2004) 1344. If CSP loses sales, it loses gross income, regardless of its costs, so the first part of subsection (D) does not prohibit recovery. 1

{¶ 16} The second part of R.C. 4928.66(D) requires the commission to find that the decoupling mechanism “reasonably aligns the interests of the utility and of its customers in favor of [energy-efficiency and energy-conservation] programs.” This part of the statute also does not require what IEU says was needed: evidence of the utility’s cost of service.

Free access — add to your briefcase to read the full text and ask questions with AI

In re Application of Columbus S. Power Co., 2011 Ohio 2383, 129 Ohio St. 3d 46 (Ohio 2011).

2011 Ohio 2383 (In re Application of Columbus S. Power Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Minerva Dairy, Inc. v. Minerva
2025 Ohio 902 (Ohio Court of Appeals, 2025)
In re Application of E. Ohio Gas Co.
2023 Ohio 3289 (Ohio Supreme Court, 2023)
In re Application of Ohio Edison Co. (Slip Opinion)
2019 Ohio 4196 (Ohio Supreme Court, 2019)