Imco, Inc. v. United States

97 F.3d 1422, 1996 U.S. App. LEXIS 26327, 1996 WL 571470
CourtCourt of Appeals for the Federal Circuit
DecidedOctober 8, 1996
Docket95-5111
StatusPublished
Cited by20 cases

This text of 97 F.3d 1422 (Imco, Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Imco, Inc. v. United States, 97 F.3d 1422, 1996 U.S. App. LEXIS 26327, 1996 WL 571470 (Fed. Cir. 1996).

Opinion

MAYER, Circuit Judge.

IMCO, Inc., appeals the April 28, 1995 judgment of the United States Court of Federal Claims, 33 Fed. Cl. 312 (1995), dismissing its bid protest challenging the Army’s cancellation of a solicitation for dummy missiles and shoe alignment fixtures after IMCO had been proposed for debarment. The court held that because the decision to actually debar IMCO was not arbitrary and capricious, or in violation of applicable law, and was based on substantial evidence; and the remaining bids were unreasonably high, the cancellation was not improper. Because the court’s review should have been limited to whether the proposed debarment was improper, we affirm on the ground that the Army committed no prejudicial error in proposing IMCO for debarment.

Background

In December 1992, the United States Army Missile Command (MICOM) issued Invitation for Bids DAAH01-93-B-0001 (“solicitation” or “IFB”), a small business set-aside, for the production of 127 dummy Hellfire missiles and thirty shoe alignment fixtures. IMCO and fifteen other small businesses submitted bids. MICOM rejected the four lowest bids, putting IMCO’s bid, the fifth lowest, in line for the award. However, the government’s preaward survey team recommended against awarding the contract to IMCO, in part because of the performance risk “evidenced by the number of IMCO contracts that ha[d] been recently cancelled or terminated.” That is, the agency determined that IMCO was not a responsible contractor. See 48 C.F.R. § 9.103 (1995) (contracts shall only be awarded to responsible contractors).

In accordance with the Federal Acquisition Regulation (FAR), the agency referred its determination to the United States Small Business Administration (SBA). Id. § 19.602-1. The SBA’s Atlanta regional office informed MICOM that it planned to issue IMCO a certificate of competency, essentially overruling the determination that IMCO was not responsible. See 15 U.S.C. § 637(b)(7) (1994); 48 C.F.R. Subpart 19.6 (1995). MICOM then appealed the proposed issuance of the certificate to the SBA’s Washington, D.C. office.

Even prior to the preaward survey, however, MICOM had recommended that IMCO be debarred. In August 1993, Diane Land-troop, the Chief of Procurement for Division D at MICOM, who had no responsibility for the procurement at issue, recommended to *1424 the Arrays Procurement Fraud Division that IMCO, its president, and an affiliate, Ikard Manufacturing Co., be debarred from further contracting with the government. More than eight months later, the Procurement Fraud Division recommended to the Army’s debarment official, Brigadier General Thomas Cuthbert, that he debar IMCO.

By letter dated April 13, 1994, General Cuthbert advised IMCO that it was proposed for debarment because it (1) had a history of failure to perform one or more contracts; (2) willfully failed to perform nine purchase orders valued at $106,080; and (3) had attempted to use the performance of those nine purchase orders to obtain payment on unrelated contracts, evincing a lack of integrity. The letter also informed IMCO that it could oppose the proposed debarment, either in person, in writing, or through a representative.

MICOM informed the SBA on April 19, 1994, that IMCO had been proposed for debarment. Because the proposed debarment rendered it ineligible to receive the contract, 48 C.F.R. § 9.405(a), (d)(4) (1995) (firms proposed for debarment are precluded from receiving government contracts), the SBA suspended proceedings concerning IMCO’s entitlement to a certificate of competency.

In the meantime, the sixth lowest bidder had gone out of business. The contracting officer then determined that the remaining bids were unreasonably high and that award to any of those bidders would not be in the government’s best interests. Consequently, MICOM cancelled the solicitation on July 20, 1994.

After receiving two extensions, IMCO submitted a written response to its proposed debarment on July 14,1994, challenging it on several grounds. After notifying IMCO that it was entitled to present testimony, which it declined, and extending the time within which to make a decision for “good cause,” General Cuthbert informed IMCO on September 16, 1994, that he had found no genuine dispute of material fact and that it was debarred through April 13,1997.

On October 24, 1994, IMCO filed suit in the Court of Federal Claims seeking to overturn the debarment and reinstate the IFB. The parties filed cross-motions for summary judgment. The court framed three issues pertinent to our inquiry: (1) whether IMCO’s procedural due process rights were violated in the actual debarment proceedings; (2) whether General Cuthbert’s debarment decision was arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law; and (3) whether MICOM’s cancellation of the solicitation breached its duty to fairly and honestly consider IMCO’s bid. 33 Fed. Cl. at 316. The court resolved these issues against IMCO, which appealed.

At oral argument, a question arose about the Court of Federal Claims’ jurisdiction to review the propriety of the actual debarment in the course of a bid protest. We ordered supplemental briefing to address the following three questions: whether the trial court’s jurisdiction was limited to a review of the proposed debarment; if so, whether the government committed prejudicial error in proposing IMCO for debarment; and what effect, if any, an error in the proposed debarment had on the disposition of this case.

Discussion

We must always examine not only our own jurisdiction, but also that of the court from which an appeal is taken. Adkins v. United States, 68 F.3d 1317, 1321 (Fed.Cir.1995); Coastal Corp. v. United States, 713 F.2d 728, 730 (Fed.Cir.1983). Initially then, we must determine whether, in the context of a bid protest, the Court of Federal Claims exceeded its jurisdiction in reviewing the propriety of the actual debarment, when only the proposed debarment rendered IMCO ineligible for contract award. Jurisdiction being a matter of law, our review is de novo. Reflectone, Inc. v. Dalton, 60 F.3d 1572, 1575 (Fed.Cir.1995) (in banc).

The United States “is immune from suit save as it consents to be sued, and the terms of its consent to be sued in any court define that court’s jurisdiction to entertain the suit.” United States v. Sherwood, 312 U.S. 584, 586, 61 S.Ct. 767, 770, 85 L.Ed. 1058 (1941) (citations omitted); see also Hercules Inc. v. United States, — U.S. -, -, 116 S.Ct. 981, 985, 134 L.Ed.2d 47 (1996).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Monbo v. United States
Federal Claims, 2025
Emiabata v. United States
Federal Claims, 2020
Neie, Inc. v. United States
Federal Claims, 2013
Med Trends, Inc. v. United States
101 Fed. Cl. 638 (Federal Claims, 2011)
FAS Support Services, LLC v. United States
93 Fed. Cl. 687 (Federal Claims, 2010)
Global Computer Enterprises, Inc. v. United States
88 Fed. Cl. 52 (Federal Claims, 2009)
Salazar v. Merit Systems Protection Board
292 F. App'x 32 (Federal Circuit, 2008)
Advanced Systems Technology, Inc. v. United States
69 Fed. Cl. 474 (Federal Claims, 2006)
Vincent Schickler, TMD U.S.A., Inc. v. United States
54 Fed. Cl. 264 (Federal Claims, 2002)
Lion Raisins, Inc. v. United States
51 Fed. Cl. 238 (Federal Claims, 2001)
Phoenix Air Group, Inc. v. United States
46 Fed. Cl. 90 (Federal Claims, 2000)
Glazer Const. Co., Inc. v. United States
50 F. Supp. 2d 85 (D. Massachusetts, 1999)
Medina Construction, Ltd. v. United States
43 Cont. Cas. Fed. 77,458 (Federal Claims, 1999)
Aero Corp., S.A. v. United States
41 Cont. Cas. Fed. 77,144 (Federal Claims, 1997)
Graphicdata, LLC v. United States
41 Cont. Cas. Fed. 77,110 (Federal Claims, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
97 F.3d 1422, 1996 U.S. App. LEXIS 26327, 1996 WL 571470, Counsel Stack Legal Research, https://law.counselstack.com/opinion/imco-inc-v-united-states-cafc-1996.