Illinois Power Co. v. Illinois Commerce Commission

612 N.E.2d 925, 245 Ill. App. 3d 367, 184 Ill. Dec. 49, 1993 Ill. App. LEXIS 576
CourtAppellate Court of Illinois
DecidedApril 22, 1993
DocketNo. 3-92-0284
StatusPublished
Cited by8 cases

This text of 612 N.E.2d 925 (Illinois Power Co. v. Illinois Commerce Commission) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Illinois Power Co. v. Illinois Commerce Commission, 612 N.E.2d 925, 245 Ill. App. 3d 367, 184 Ill. Dec. 49, 1993 Ill. App. LEXIS 576 (Ill. Ct. App. 1993).

Opinion

JUSTICE BARRY

delivered the opinion of the court:

This proceeding was initiated on May 25, 1988, when the Illinois Commerce Commission (Commission) issued an “Order Commencing Reconciliation Proceedings” pursuant to section 9 — 220 of the Public Utilities Act (Ill. Rev. Stat. 1987, ch. lll2/3, par. 9 — 220 (now 220 ILCS 5/9 — 220 (West 1992) with 1991 amendments not involved herein)). Illinois Power Company (Illinois Power) was directed to reconcile the costs recoverable through its purchased gas adjustment clause (PGA) and fuel adjustment clause (FAC) and the revenues billed under PGA and FAC charges during the 12 months ended December 31, 1987. The Commission also directed Illinois Power to demonstrate that its fuel, power and gas supplies purchased during the reconciliation period were prudently purchased.

After receiving several volumes of evidence, the Commission ruled that certain nuclear fuel decisions were imprudent and led to unnecessary carrying charges of $29,252,437, thereby disallowing those costs. Additional rulings by the Commission concerning the reconciliation of the costs of natural gas and of electric fuel other than nuclear fuel are not at issue on appeal.

Illinois Power originally planned to construct a two-unit nuclear power plant at Clinton, Illinois, at a total cost of $429,438,000 with Unit 1 to be in commercial operation by June of 1980 and Unit 2 to be operational in June of 1982. After the Three Mile Island nuclear plant accident in 1979, nuclear power plant construction came under increasingly stringent requirements. Unit 2 was subsequently can-celled. Numerous construction delays resulted in Unit 1 beginning commercial operations on April 24, 1987, at a final cost of $4,224,600,000, nearly 10 times the original cost forecast.

Some understanding of the nuclear fuel cycle is necessary before reviewing the fuel procurement actions of Illinois Power. As described in the record, the nuclear fuel cycle involves four steps: uranium ore, conversion services, enrichment services, and fabrication services. The first is the production of natural uranium in the form of uranium concentrates produced by a mining and milling process. The second step is the conversion process by which the solid uranium concentrates are converted into a gas (UF6) for the enrichment stage. Enrichment results in the separation and concentration of the fissionable isotope U235 of natural uranium from the nonfissionable isotope U238. Enriched uranium is then converted back to a solid and, at the fabrication facility, is converted into U02 powder, which is first processed into pellets and then loaded into metal rods that are bound together in fuel bundles. The fuel bundles are plant-specific and cannot be sold for use in other facilities. The bundles are then ready to be loaded in the reactor, where they produce energy for at least three years. The average length of time to process uranium into fuel bundles is 12 to 18 months, and under Illinois Power’s contracts, the uranium concentrates were required to be at the conversion facility 12 months before the fuel bundles would be ready for loading into the reactor.

Robert E. Alsop, the fuel buyer for Illinois Power responsible for purchasing nuclear fuel and related services and for administration of fuel contracts, testified as to the company’s nuclear fuel procurement chronology. After the development of fuel specifications, bids were received from five competing suppliers. On December 28, 1972, a contract was signed with General Electric (GE) for fuel fabrication services for the initial core and for reload bundles as well. The schedules in the fabrication contract were based upon a 1980 start-up date for Unit 1 and a 1982 date for Unit 2. The contract also provided for some flexibility in delivery schedules, as follows: (1) at any time more than 30 months before the scheduled delivery date, delivery could be deferred indefinitely; (2) from 30 months to 18 months before scheduled delivery, the delivery date could be deferred for up to three months; (3) from 14 months to 18 months before the scheduled delivery date, delivery could be deferred for up to an additional three months; and (4) within 14 months of the scheduled delivery date, no further delay was allowed.

The GE contract also required that two-thirds of the enriched uranium be delivered to GE five months before the shipment date for the fabricated assemblies, and the remaining one-third be delivered to GE four months before the shipment date. The original shipment date was August 31, 1979, for Unit 1. As early as November 1973, Illinois Power notified GE that the start-up date of Unit 2 had been delayed one year.

In May of 1974, Illinois Power entered into two long-term fixed commitment uranium enrichment contracts with the only vendor available to utilities within the United States, the Atomic Energy Commission (AEG), later succeeded by the United States Department of Energy (DOE). Each contract required a 10-year fixed commitment for enrichment services with no flexibility to change dates or amounts.

In April of 1975, Illinois Power entered into a contract with Kerr-McGee Nuclear Corporation (Kerr-McGee) for 2,720,000 pounds of uranium and for conversion to 1,041,020 kilograms of UF6. The contract provided for fixed delivery dates with the uranium to be delivered in 1976, 1977, and 1978, and the UF6 to be delivered in 1978 and 1979.

In November of 1974, Unit 1 start-up date was deferred to June 1981, and Unit 2 start-up was deferred to 1984. Additional deferments of the starting dates occurred, as follows:

On December 14,1976, Unit 1 was deferred to December 1981.
On February 11,1977, Unit 2 was deferred to 1988.
On April 13,1978, Unit 1 was deferred to December 1982.
On December 5,1980, Unit 1 was deferred to August 1983.

As these delays occurred, Illinois Power negotiated contractual adjustments to accommodate the postponements of start-up dates. In 1979, the DOE converted the two long-term fixed commitment enrichment contracts to adjustable contracts so that the schedule ran from 1982 to 1986 for Unit 1 and from 1987 to 1991 for Unit 2, thus corresponding with start-up dates of 1982 and 1988, respectively.

By the time the last of these delays was announced (December 5, 1980), Kerr-McGee had already delivered 374,800 kgs. of UF6 to Illinois Power. In April of 1981, Illinois Power made the final deferment allowable under the fabrication contract with GE, changing the shipment date to October 1982 in preparation for a January 1983 fuel load date in advance of the August 1983 date for commercial operation. On October 31, 1981, the 374,800 kgs. of UF6 were sent to DOE for enrichment. GE required the enriched material by May of 1982, and DOE required 180 days’ advance notice before shipment to GE.

Thus the fuel cycle was underway when the first of 10 stop work orders were issued by Illinois Power in January of 1982. As a result, in April of 1982 commercial operation of Unit 1 was deferred to August of 1984, and a year later, the start-up date was deferred to November 1986. In May of 1982, enrichment was completed by DOE, and the enriched UF6 was sent to GE.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

North Shore Gas Co. v. Illinois Commerce Comm'n ex rel Raoul
2026 IL App (2d) 240350-U (Appellate Court of Illinois, 2026)
Northern Illinois Gas Co. v. The Illinois Commerce Commission
2025 IL App (3d) 240093 (Appellate Court of Illinois, 2025)
Northern Illinois Gas Co. v. Illinois Commerce Comm'n
2024 IL App (3d) 230388-U (Appellate Court of Illinois, 2024)
North Shore Gas Co. v. Illinois Commerce Comm'n
2024 IL App (2d) 230229 (Appellate Court of Illinois, 2024)
Illinois Power Co. v. Illinois Commerce Commission
887 N.E.2d 678 (Appellate Court of Illinois, 2008)
Illinois Power Co. v. Illinois Commerce Comm'n
Appellate Court of Illinois, 2003
Illinois Power Co. v. COMMERCE COM'N
612 N.E.2d 925 (Appellate Court of Illinois, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
612 N.E.2d 925, 245 Ill. App. 3d 367, 184 Ill. Dec. 49, 1993 Ill. App. LEXIS 576, Counsel Stack Legal Research, https://law.counselstack.com/opinion/illinois-power-co-v-illinois-commerce-commission-illappct-1993.