Northern Illinois Gas Co. v. The Illinois Commerce Commission
This text of 2025 IL App (3d) 240093 (Northern Illinois Gas Co. v. The Illinois Commerce Commission) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
2025 IL App (3d) 240093
Opinion filed December 1, 2025 ____________________________________________________________________________
IN THE
APPELLATE COURT OF ILLINOIS
THIRD DISTRICT
NORTHERN ILLINOIS GAS COMPANY, ) Petition for Review of Orders of the d/b/a Nicor Gas Company, ) Illinois Commerce Commission, ) Petitioner, ) Appeal No. 3-24-0093 ) ICC Docket # 23-0066 v. ) ) THE ILLINOIS COMMERCE COMMISSION ) and THE PEOPLE ex rel. KWAME ) RAOUL, Attorney General of the State of ) Illinois, ) ) Respondents. ) ) ____________________________________________________________________________
JUSTICE HETTEL delivered the judgment of the court, with opinion. Justices Peterson and Bertani concurred in the judgment and opinion. ____________________________________________________________________________
OPINION
¶1 Petitioner, Northern Illinois Gas Company, doing business as Nicor Gas Company (Nicor),
appeals from a November 16, 2023, decision issued by the Illinois Commerce Commission
(Commission) in Nicor’s rate case. In its decision, the Commission adopted an imputed capital
structure for Nicor, disallowed portions of Nicor’s proposed pipeline investment costs, and
required Nicor to file a long-term gas infrastructure plan. For the following reasons, we affirm in
part and vacate in part. ¶2 I. BACKGROUND
¶3 A. General Background and Procedural History
¶4 Nicor is a public utility that distributes natural gas to approximately 2.3 million customers
located throughout northern Illinois and operates a distribution system that is approximately
34,000 miles long. As a public utility, Nicor is governed by the Public Utilities Act (Act) (220
ILCS 5/1-101 et seq. (West 2022)) and regulated by the Commission. See id. §§ 3-105, 4-101
(defining the term “public utility” and stating that the Commission has “general supervision” of
all public utilities).
¶5 A public utility is entitled to recover certain operating costs through the rates that it charges
its customers. Citizens Utility Board v. Illinois Commerce Comm’n, 166 Ill. 2d 111, 121 (1995).
The Commission is responsible for setting the rates charged by a utility. United Cities Gas Co. v.
Illinois Commerce Comm’n, 163 Ill. 2d 1, 11 (1994). Generally, a utility seeking a rate increase
must file new schedules or supplements with the Commission that indicate the proposed changes
to be made in the schedule or schedules already in place, as well as the time when the proposed
changes would take effect. 220 ILCS 5/9-201(a) (West 2022). “When a utility files a request for a
rate increase in the form of a new tariff schedule, the Commission has the authority upon complaint
or its own initiative to hear evidence, hold hearings and determine the propriety of the requested
increase.” Business & Professional People for the Public Interest v. Illinois Commerce Comm’n,
146 Ill. 2d 175, 195 (1991).
¶6 On January 3, 2023, Nicor filed tariff sheets with the Commission in which it proposed “a
general increase in rates” effective February 17, 2023. Starting on July 18, 2023, the Commission
conducted an evidentiary hearing, during which written testimony and exhibits were admitted into
the record. Staff of the Commission (Staff) participated in the proceedings, and the Office of the
2 Illinois Attorney General (Attorney General) filed an appearance. Additionally, two groups of
advocates filed petitions to intervene in the proceedings. The first of these groups included Retail
Energy Supply Association; Nucor Steel Kankakee, Inc.; Local Union No. 19 International
Brotherhood of Electrical Workers, AFL-CIO; Walmart Inc.; the Environmental Law & Policy
Center; the Environmental Defense Fund; the Natural Resources Defense Council; and the Illinois
State Public Interest Research Group, Inc. (collectively, “Public Interest Organizations”). The
second group included ExxonMobil Power & Gas Services, Inc., as a member of the Illinois
Industrial Energy Consumers; the Citizens Utility Board; and the Community Development
Corporation of Pembroke-Hopkins Park (collectively, “Ratepayer Advocates”).
¶7 On November 16, 2023, the Commission issued its order in which it rejected parts of
Nicor’s proposed rate increase (Order). Nicor subsequently filed a petition for rehearing, which
the Commission denied.
¶8 B. Nicor’s Proposed Rate Increase
¶9 i. Nicor’s Capital Structure
¶ 10 A public utility may charge rates that allow it to earn a return on the amount of its invested
capital. People ex rel. Madigan v. Illinois Commerce Comm’n, 2011 IL App (1st) 100654, ¶ 76
(citing Citizens Utility Co. of Illinois v. Illinois Commerce Comm’n, 124 Ill. 2d 195, 200-01
(1988)). The amount of a utility’s return is dependent on its capital structure. See Citizens Utility
Board v. Illinois Commerce Comm’n, 276 Ill. App. 3d 730, 743-46 (1995) (explaining the costs
associated with different forms of capital and how a utility’s capital structure impacts the amount
that it recovers in revenue). A utility’s capital structure typically consists of short-term debt, long-
term debt, and equity. See Ameren Illinois Co. v. Illinois Commerce Comm’n, 2013 IL App (4th)
121008, ¶ 22. “Generally, equity is a more expensive form of capital than debt.” Illinois Bell
3 Telephone Co. v. Illinois Commerce Comm’n, 283 Ill. App. 3d 188, 204 (1996). “Therefore, the
more equity in a utility’s capital structure, the higher the [rate of return] must be to cover the cost
of capital.” Id.
¶ 11 When calculating the rates that a public utility may charge its customers, the Commission
considers the company’s operating costs, rate base, and allowed rate of return. Citizens Utility Co.,
124 Ill. 2d at 200. “Recovery of the utility’s operating costs and the return on its rate base is known
as the utility’s annual revenue requirement.” Commonwealth Edison Co. v. Illinois Commerce
Comm’n, 405 Ill. App. 3d 389, 394 (2010). “Generally speaking, a utility determines its revenue
requirement by adding operating costs to invested capital multiplied by the rate of return.” Id. “The
components of the revenue requirement have frequently been expressed in the formula ‘R (revenue
requirement) = C (operating costs) + Ir (invested capital or rate base times rate of return on
capital).’ ” Business & Professional People, 146 Ill. 2d at 195.
¶ 12 1. Capital Structure Proposed by Nicor
¶ 13 Nicor proposed increased rates that would yield a 7.49% rate of return on its capital
investments. To support its proposal, Nicor submitted testimony by Gregory MacLeod, the Finance
Director and Assistant Treasurer for Nicor’s parent company, Southern Company (Southern).
MacLeod explained that the rate of return that Nicor sought on its capital investments was based
on a “Test Year” capital structure that consisted of 54.520% of common equity, 42.437% of long-
term debt, and 3.043% of short-term debt. MacLeod further explained that the Test Year capital
structure was “neither hypothetical nor derived for ratemaking purposes only,” but was, instead,
“consistent” with Nicor’s actual capital structure, which had remained the same for “several years”
and the Commission had approved in the past. According to MacLeod, Southern owned all Nicor’s
4 common equity, and Nicor had no authority to issue common equity to an entity other than
Southern.
Free access — add to your briefcase to read the full text and ask questions with AI
2025 IL App (3d) 240093
Opinion filed December 1, 2025 ____________________________________________________________________________
IN THE
APPELLATE COURT OF ILLINOIS
THIRD DISTRICT
NORTHERN ILLINOIS GAS COMPANY, ) Petition for Review of Orders of the d/b/a Nicor Gas Company, ) Illinois Commerce Commission, ) Petitioner, ) Appeal No. 3-24-0093 ) ICC Docket # 23-0066 v. ) ) THE ILLINOIS COMMERCE COMMISSION ) and THE PEOPLE ex rel. KWAME ) RAOUL, Attorney General of the State of ) Illinois, ) ) Respondents. ) ) ____________________________________________________________________________
JUSTICE HETTEL delivered the judgment of the court, with opinion. Justices Peterson and Bertani concurred in the judgment and opinion. ____________________________________________________________________________
OPINION
¶1 Petitioner, Northern Illinois Gas Company, doing business as Nicor Gas Company (Nicor),
appeals from a November 16, 2023, decision issued by the Illinois Commerce Commission
(Commission) in Nicor’s rate case. In its decision, the Commission adopted an imputed capital
structure for Nicor, disallowed portions of Nicor’s proposed pipeline investment costs, and
required Nicor to file a long-term gas infrastructure plan. For the following reasons, we affirm in
part and vacate in part. ¶2 I. BACKGROUND
¶3 A. General Background and Procedural History
¶4 Nicor is a public utility that distributes natural gas to approximately 2.3 million customers
located throughout northern Illinois and operates a distribution system that is approximately
34,000 miles long. As a public utility, Nicor is governed by the Public Utilities Act (Act) (220
ILCS 5/1-101 et seq. (West 2022)) and regulated by the Commission. See id. §§ 3-105, 4-101
(defining the term “public utility” and stating that the Commission has “general supervision” of
all public utilities).
¶5 A public utility is entitled to recover certain operating costs through the rates that it charges
its customers. Citizens Utility Board v. Illinois Commerce Comm’n, 166 Ill. 2d 111, 121 (1995).
The Commission is responsible for setting the rates charged by a utility. United Cities Gas Co. v.
Illinois Commerce Comm’n, 163 Ill. 2d 1, 11 (1994). Generally, a utility seeking a rate increase
must file new schedules or supplements with the Commission that indicate the proposed changes
to be made in the schedule or schedules already in place, as well as the time when the proposed
changes would take effect. 220 ILCS 5/9-201(a) (West 2022). “When a utility files a request for a
rate increase in the form of a new tariff schedule, the Commission has the authority upon complaint
or its own initiative to hear evidence, hold hearings and determine the propriety of the requested
increase.” Business & Professional People for the Public Interest v. Illinois Commerce Comm’n,
146 Ill. 2d 175, 195 (1991).
¶6 On January 3, 2023, Nicor filed tariff sheets with the Commission in which it proposed “a
general increase in rates” effective February 17, 2023. Starting on July 18, 2023, the Commission
conducted an evidentiary hearing, during which written testimony and exhibits were admitted into
the record. Staff of the Commission (Staff) participated in the proceedings, and the Office of the
2 Illinois Attorney General (Attorney General) filed an appearance. Additionally, two groups of
advocates filed petitions to intervene in the proceedings. The first of these groups included Retail
Energy Supply Association; Nucor Steel Kankakee, Inc.; Local Union No. 19 International
Brotherhood of Electrical Workers, AFL-CIO; Walmart Inc.; the Environmental Law & Policy
Center; the Environmental Defense Fund; the Natural Resources Defense Council; and the Illinois
State Public Interest Research Group, Inc. (collectively, “Public Interest Organizations”). The
second group included ExxonMobil Power & Gas Services, Inc., as a member of the Illinois
Industrial Energy Consumers; the Citizens Utility Board; and the Community Development
Corporation of Pembroke-Hopkins Park (collectively, “Ratepayer Advocates”).
¶7 On November 16, 2023, the Commission issued its order in which it rejected parts of
Nicor’s proposed rate increase (Order). Nicor subsequently filed a petition for rehearing, which
the Commission denied.
¶8 B. Nicor’s Proposed Rate Increase
¶9 i. Nicor’s Capital Structure
¶ 10 A public utility may charge rates that allow it to earn a return on the amount of its invested
capital. People ex rel. Madigan v. Illinois Commerce Comm’n, 2011 IL App (1st) 100654, ¶ 76
(citing Citizens Utility Co. of Illinois v. Illinois Commerce Comm’n, 124 Ill. 2d 195, 200-01
(1988)). The amount of a utility’s return is dependent on its capital structure. See Citizens Utility
Board v. Illinois Commerce Comm’n, 276 Ill. App. 3d 730, 743-46 (1995) (explaining the costs
associated with different forms of capital and how a utility’s capital structure impacts the amount
that it recovers in revenue). A utility’s capital structure typically consists of short-term debt, long-
term debt, and equity. See Ameren Illinois Co. v. Illinois Commerce Comm’n, 2013 IL App (4th)
121008, ¶ 22. “Generally, equity is a more expensive form of capital than debt.” Illinois Bell
3 Telephone Co. v. Illinois Commerce Comm’n, 283 Ill. App. 3d 188, 204 (1996). “Therefore, the
more equity in a utility’s capital structure, the higher the [rate of return] must be to cover the cost
of capital.” Id.
¶ 11 When calculating the rates that a public utility may charge its customers, the Commission
considers the company’s operating costs, rate base, and allowed rate of return. Citizens Utility Co.,
124 Ill. 2d at 200. “Recovery of the utility’s operating costs and the return on its rate base is known
as the utility’s annual revenue requirement.” Commonwealth Edison Co. v. Illinois Commerce
Comm’n, 405 Ill. App. 3d 389, 394 (2010). “Generally speaking, a utility determines its revenue
requirement by adding operating costs to invested capital multiplied by the rate of return.” Id. “The
components of the revenue requirement have frequently been expressed in the formula ‘R (revenue
requirement) = C (operating costs) + Ir (invested capital or rate base times rate of return on
capital).’ ” Business & Professional People, 146 Ill. 2d at 195.
¶ 12 1. Capital Structure Proposed by Nicor
¶ 13 Nicor proposed increased rates that would yield a 7.49% rate of return on its capital
investments. To support its proposal, Nicor submitted testimony by Gregory MacLeod, the Finance
Director and Assistant Treasurer for Nicor’s parent company, Southern Company (Southern).
MacLeod explained that the rate of return that Nicor sought on its capital investments was based
on a “Test Year” capital structure that consisted of 54.520% of common equity, 42.437% of long-
term debt, and 3.043% of short-term debt. MacLeod further explained that the Test Year capital
structure was “neither hypothetical nor derived for ratemaking purposes only,” but was, instead,
“consistent” with Nicor’s actual capital structure, which had remained the same for “several years”
and the Commission had approved in the past. According to MacLeod, Southern owned all Nicor’s
4 common equity, and Nicor had no authority to issue common equity to an entity other than
Southern.
¶ 14 MacLeod testified that the Test Year capital structure was reasonable in that it would permit
Nicor to maintain its financial strength and access to the capital markets, rendered Nicor financially
resilient enough to respond to the risks that the company expected to face, was comparable to the
capital structures of other “financially sound” local gas distribution companies, and was based on
the same goals and capital-planning approaches that had underlain Nicor’s past capital structures
that the Commission had approved. As to Nicor’s financial resilience, MacLeod recounted that, in
February 2021, Nicor had incurred “extraordinary and unexpected costs” to service its customers
during Winter Storm Uri, an extreme arctic weather event that lasted days and constrained the gas
supply during a time of high demand, causing the cost of gas to increase. MacLeod explained that
Nicor’s short-term debt and strong credit profile benefited customers by, for example, enabling the
company to quickly and efficiently fund the increased costs of its gas services during Winter Storm
Uri and to amortize its recovery of the costs by only gradually increasing the customers’ rates over
an extended period of time. MacLeod added that Nicor was able to perform these actions “all while
avoiding potential credit downgrades from the rating agencies.”
¶ 15 John Quackenbush, a former utility regulator and advisor to the Commission, testified that
the capital structure of a utility is important to its investors. Quackenbush explained that investors
expect a return on their investment that is proportional to the risk and that an important type of risk
is regulatory risk, which is the risk that certain actions—such as changes in the law or the
imposition of regulations—would materially impact the utility by increasing operating costs,
decreasing the “attractiveness” of an investment, or changing the competitive landscape.
Quackenbush further explained that investors consider a utility’s capital structure when assessing
5 risk because they know that the Commission considers the capital structure when authorizing the
rate of return on a utility’s capital investments.
¶ 16 Next, Quackenbush testified that investors receive information regarding regulatory risks
from credit rating agencies, whose role is to “provide debt capital market[***] participants with
an independent, objective, and forward-looking opinion of creditworthiness [of a debt security].”
Quackenbush stated that credit rating agencies indicate a debt security’s creditworthiness by
assigning the security a letter that corresponds with the relative risk that the debt issuer will default.
He also further elaborated on the grade rating system by adding the following:
“Letters closer to the front of the alphabet indicate higher levels of creditworthiness and a
lower probability of default. When a change in credit quality is perceived, the rating
agencies will change the ratings up or down, thereby upgrading or downgrading the debt.
The rating agencies’ investment grade ratings are ‘AAA’ or ‘Aaa,” followed by ‘AA’ or
‘Aa,’ then ‘A,’ then ‘BBB’ or ‘Baa.’ Every rating beneath ‘BBB’ or ‘Baa’ is considered
below investment grade, junk, speculative, and high yield, with the associated debt carrying
significantly higher probability of default. The rating agencies also use a ‘+’ or ‘1’
designation to indicate a rating in the high portion of a rating category, and ‘-’ or ‘3’
designation to indicate a rating in the low portion of a rating category.”
Quackenbush pointed out that numerous credit rating agencies had assigned Nicor credit ratings
of A2, A-, and A, with the “2” in A2 denoting creditworthiness in the middle of the A category. He
also pointed out that one of these credit rating agencies, Moody’s Investor Service (Moody’s), had
characterized the Illinois regulatory framework as being “credit supportive.”
6 ¶ 17 2. Capital Structure Proposed by Ratepayer Advocates
¶ 18 The Ratepayer Advocates recommended that Nicor’s capital structure consist of 52.0% of
common equity, rather than the 54.520% that the company proposed. Michael Gorman—a public
utility regulation consultant and a Managing Principal with an energy, economic, and regulatory
consulting firm—testified in support of the Ratepayer Advocates that, although he agreed with
MacLeod that a utility’s capital structure “should be adequate to support its financial integrity,
credit standing and access to capital, it should also do so at just and reasonable rates to customers.”
Gorman explained that, “[h]ence, there should be a demonstration that the ratemaking capital
structure is no more expensive than necessary to support [Nicor’s] financial integrity and credit
standing objectives.”
¶ 19 Gorman further testified that MacLeod had failed to demonstrate that Nicor’s proposed
capital structure was as cost-effective as possible in that MacLeod had not provided evidence of
whether a capital structure with less common equity and cost than that proposed by Nicor would
still achieve Nicor’s financial goals. Gorman assessed the reasonableness of Nicor’s proposed
capital structure by reviewing the utility’s credit metric projections, a comparison to industry credit
metric estimates, and the capital structures of other companies. Gorman also considered numerous
factors, such as that Moody’s and Standard & Poor’s (S&P) had stable credit outlooks for Nicor,
that Illinois’s regulatory environment was supportive of Nicor’s credit ratings, and that Nicor had
a “sizable” customer base, which, in turn, suggested that Nicor’s existing investment grade bond
rating would still be supported if the utility’s capital structure were to contain less common equity.
Gorman therefore concluded that Nicor’s proposed capital structure “contain[ed] more equity than
necessary” and was, thus, “more expensive than necessary.”
7 ¶ 20 In surrebuttal, MacLeod testified that Gorman “seem[ed] shortsightedly focused only on
the cost difference between differing sources of capital” and that Gorman had “ignore[d] the
potential negative customer impacts of adding more financial and business risk to [Nicor].”
MacLeod explained that “[f]ocusing exclusively on the near-term rate of return ignores the
customer protection that a strong credit rating provides to customers.” He further explained that if
Nicor were to have a less resilient credit profile, then the utility would have a weakened “ability
to navigate volatile market conditions and provide necessary liquidity in times of financial and
operational stresses,” which would, in turn, “result in increased costs to customers over the longer-
term as [Nicor’s] borrowing rates increase through a combination of lower credit ratings and an
increasing interest rate environment.”
¶ 21 3. Capital Structure Proposed by Staff
¶ 22 Staff recommended that Nicor’s capital structure consists of only 50% common equity,
46.96% long-term debt, and 3.04% short-term debt. In support of Staff’s recommendation, Sheena
Kight-Garlisch, a Senior Financial Analyst for the Commission, testified that an “optimal” capital
structure for a utility would both “minimize the cost of capital and maintain [the] utility’s financial
strength” and that the Commission should not determine a utility’s overall rate of return based on
its actual capital structure “if that capital structure adversely affects the overall cost of capital.”
¶ 23 Kight-Garlisch assessed whether the Commission should have used Nicor’s proposed
capital structure to set the utility’s overall rate of return. During her assessment, Kight-Garlisch
found that Nicor’s proposed capital structure contained “a significantly higher percentage of
common equity” than the two sample groups of gas utilities upon which she had relied and which
each contained an average of 42.51% and 41.56% of common equity, respectively. Kight-Garlisch
further found that Nicor’s proposed common equity ratio was also higher than the average equity
8 ratio of Southern, which was 37.41%. Kight-Garlisch stated that, although a higher percentage of
common equity implies lower risk and Southern was a “riskier” company than Nicor, Nicor’s
proposed equity ratio was “much higher” than Southern’s and the proposed capital structure
contained “more common equity than needed” to support its financial strength and maintain its
credit ratings. Kight-Garlisch thus concluded that the Commission should not use Nicor’s proposed
capital structure to set the utility’s overall rate of return.
¶ 24 In rebuttal, Wendell Dallas, the President and Chief Executive Officer of Nicor, testified
that, in the utility’s “most recent” rate case in 2021, Kight-Garlisch had “supported the use of
[Nicor’s] actual capital structure with some modest adjustments, and testified that an equity ratio
of 54.459% [was] ‘consistent with the common equity ratios of other similar companies in the gas
distribution industry’ and ‘was commensurate with a strong, but not excessive, degree of financial
strength.’ ” Dallas stated that Kight-Garlisch had also found that Nicor’s common equity ratio of
54.459% was consistent with the average common equity ratio of her sample group, which was
47.26%.
¶ 25 Dallas also testified that, in a 2018 rate case, Staff witness Rochelle Phipps concluded that
a common equity ratio of 54.41% “was ‘consistent with the common equity ratios of other
companies in the gas distribution industry’ where the mean common equity ratio for the gas
distribution industry was 46.98% ***.” Additionally, Dallas testified that, in a 2017 rate case,
Phipps separately found that a common equity ratio of 54.206% “ ‘compared favorably with other
companies in the gas distribution industry’ where the mean common equity ratio for the gas
industry was 51.07% ***.”
9 ¶ 26 4. The Commission’s Findings
¶ 27 In its order, the Commission articulated that “[t]he optimal capital structure minimizes the
cost of capital while maintaining a utility’s financial strength” and that the central question in this
case was “whether [Nicor’s] proposal [was] stronger than necessary.” The Commission then found
that Staff and the Ratepayer Advocates had successfully shown that Nicor could maintain its credit
rating with a common equity ratio of 50%; that Nicor’s proposed common equity ratio was “much
higher” than those of the sample gas distributors and Southern, which were all riskier entities; and
that Nicor’s proposed common equity ratio was “significantly greater than those typically
approved by commissions around the country for the past decade.”
¶ 28 The Commission further found that, conversely, Nicor had not shown that its proposed
common equity ratio was needed to support its financial integrity. The Commission remarked that
“[i]t appear[ed] that [Nicor’s] proposed equity ratio [was] high due to its association with non-
regulated affiliates, thus requiring ratepayers to pay higher costs than warranted ***.” Ultimately,
the Commission adopted the imputed capital structure proposed by Staff, which consisted of 50%
common equity, 46.96% long-term debt, and 3.04% short-term debt.
¶ 29 ii. Nicor’s Pipeline Investments
¶ 30 A natural gas utility is required by law to “refurbish, rebuild, modernize, and expand” the
infrastructure of its natural gas system to ensure that it is providing “safe, reliable, and affordable
service” to its customers. 220 ILCS 5/5-111 (West 2022). A public utility may also recover, through
the rates that it charges its customers, “the value of such investment which is both prudently
incurred and used and useful in providing service to public utility customers.” Id. § 9-211.
¶ 31 Nicor uses natural gas pipelines to deliver gas from interstate pipelines, transport gas from
storage fields, move gas within its service territory, and deliver gas to the distribution mains and
10 pipes to serve customers. In this case, Nicor sought to recover for certain investments that it made
to ensure that its natural gas system was safe and reliable.
¶ 32 1. Distribution Investments
¶ 33 Typically, there is a delay between when a natural gas utility invests in its infrastructure
and when it can begin recovering the costs of its investments through a rate case. During the delay,
the investors in the utility must finance the costs, which tends to discourage further investment.
¶ 34 In 2013, to reduce the delay in which natural gas utilities could recover their investment
costs, the General Assembly enacted section 9-220.3 of the Act, which allowed a natural gas utility
to file a tariff for surcharges that would adjust the utility’s rates and charges to allow it to recover
its investment costs in “qualifying infrastructure plant” (QIP), independent of other matters related
to the utility’s revenue requirement. Id. § 9-220.3; see Citizens Utility Board, 166 Ill. 2d at 133.
This cost-recovery method is referred to as a “rider.” See Citizens Utility Board, 166 Ill. 2d at 133.
Section 9-220.3 of the Act was repealed on December 31, 2023, after which Nicor could no longer
recover its investment costs by using a rider. 220 ILCS 5/9-220.3 (West 2022).
¶ 35 a. Nicor’s Proposed Recovery of Distribution Investment Costs
¶ 36 Nicor sought to recover $149.5 million in distribution investment costs that it could have
recovered through a rider, prior to the repeal of section 9-220.3 of the Act. To support Nicor’s
position, Patrick Whiteside, the senior vice president of operations for Nicor, testified that, to
ensure that its gas service was safe and reliable, Nicor had regularly invested in its storage,
transmission, and distribution systems. Whiteside explained that Nicor’s investments in these
systems included “main replacement, system regulator station installations and replacements ***,
rehabilitation and replacement of facilities critical to operating the [c]ompany’s eight storage
11 fields, installation of new main and services [for] new customers, and gas main and service
replacement resulting from public improvements as required by various governmental entities.”
¶ 37 Whiteside detailed the following regarding Nicor’s method of deciding which distribution
investment projects to prioritize:
“Nicor [***] takes a systematic approach to prioritizing investments eligible for recovery
under [r]ider QIP. Each project category carries a unique set of characteristics that are
evaluated for risks and other factors, including, but not limited to, safety, reliability,
obsolescence, age, and asset integrity. This analysis includes data from Subject Matter
Experts, and the newest requirements for federal pipeline safety and inspections ***. These
prioritizations are conducted on both a holistic basis in determining overall investment
resources and within each qualifying investment category to determine the optimal
deployment of resources. The [c]ompany’s approach also includes consideration of factors
specified in [s]ection 9-220.3 of the Act.”
¶ 38 Additionally, Whiteside testified that, after section 9-220.3 of the Act was enacted, Nicor
completed numerous projects, such as working at an accelerated rate to replace the remaining cast
iron main and known copper services in its systems, which the company fully accomplished in
2018 and 2019. Whiteside explained that, despite this completed work, Nicor had determined that
its gas distribution system still contained future needs, a “significant amount” of which entailed
projects with costs that the company could recover through a rider. Whiteside stated that, in light
of the then impending repeal of section 9-220.3 of the Act, however, Nicor planned to “roll[***]
its QIP investments into rate base as of the end of 2023 *** and recover capital investments that
would have been eligible for recovery under [r]ider QIP through base rates in 2024.”
12 ¶ 39 Whiteside more specifically explained that some of the projects designed to address Nicor’s
future needs included the replacement of “other” qualifying vintage material, which, in turn,
included approximately 1,624 miles of mechanically coupled steel gas mains that were “known to
present enhanced safety risks and [had] been identified as the cause of known industry incidents
and failures.” Whiteside stated that this infrastructure “need[ed] to be addressed in a timely manner
to decrease the probability of a future incident or failure.” He thus concluded that, although Nicor
had not decreased its infrastructure replacement rate, the Commission should nevertheless approve
the company’s proposed recovery of its distribution costs as prudent and reasonable.
¶ 40 b. Attorney General’s Proposed Recovery of Distribution Investment Costs
¶ 41 The Attorney General recommended that the Commission disallow 33%, or $55.1 million,
of Nicor’s proposed distribution investment costs on the grounds that the costs were unreasonable,
lacked sufficient identification and justification, and lacked evidentiary support. Rod Walker, Chief
Executive Officer and President of a management consultancy and technical advisory firm,
analyzed Nicor’s efforts to ensure the safety and reliability of its infrastructure. Walker noted that
Nicor had approximately 33,616 miles of mains and 2,054,463 services in its gas distribution
system, which was the largest in Illinois. Walker further noted that, prior to the enactment of
section 9-220.3 of the Act, there were 488 miles of leak-prone pipe (LPP) mains and 57,588 LPP
services in Nicor’s gas distribution system, but that Nicor had already reduced this inventory to 83
miles of LPP mains and 6,645 LPP services by the end of 2022, which yielded an 83% reduction
in LPP mains and 88.5% reduction in LPP services.
¶ 42 Walker concluded that, “[g]iven the nearly complete replacement of LPP main and services
in the Nicor system as well as other improvements to the system,” it was no longer warranted for
Nicor to work at an accelerated pace to improve its infrastructure. Walker observed, however, that,
13 even though Nicor’s accelerated pace had no longer been warranted, the amount of infrastructure
that the company replaced in 2024 declined by only approximately 0.5% between 2023 and 2024
and service replacement costs were forecasted to increase by approximately 30% in 2024. Walker
explained that, although it appeared that Nicor had been devoting its continued accelerated pace
to “other” main and service replacements, the company had not defined such replacements. Based
on his analysis, Walker concluded that Nicor planned to continue working at an accelerated rate to
improve its infrastructure, even after section 9-220.3 of the Act was repealed and the accelerated
rate was no longer justified.
¶ 43 Separately, David Dismukes, a consulting economist with Acadian Consulting Group,
testified that section 9-220.3 of the Act “was premised on a desire that the mechanism be used to
facilitate the accelerated replacement of aging infrastructure assets to which there was a perceived
growing safety or reliability concern,” but that, according to Nicor, it had already replaced a
“significant” amount of its aging infrastructure assets. Dismukes further testified that, thus, Nicor
would still be able to maintain a safe and reliable gas distribution system if it were to reduce the
amount that it invested to improve the system.
¶ 44 Additionally, Catherine Elder, an employee of Aspen Environmental Group, testified that
the evidence offered by Nicor indicated that the company’s “spending on other ‘qualifying vintage
materials’ [was] merely taking the place of prior QIP spending on copper services, cast iron main
and services, [and] bare steel mains and services.” Elder explained, however, that this showing by
Nicor “downplay[ed]” the fact that Nicor had “dramatically increased” its investment in replacing
other qualifying vintage material. Further, Elder concluded that Nicor had failed to justify the
amount that it had been investing to replace such qualifying vintage material.
14 ¶ 45 c. The Commission’s Findings
¶ 46 In its Order, the Commission acknowledged Nicor’s statutory requirement to show that its
investments were prudently made and its argument that its distribution investments helped ensure
the safety and reliability of the company’s infrastructure. However, the Commission clarified that
the question before it was “not whether pipeline replacements generally improve[d] safety and
reliability, but what types of pipes [were] to be replaced, to what degree safety and reliability
[were] affected, and importantly, at what cost.” The Commission then found that Nicor had failed
to show that the other qualifying vintage material posed similar risks to LPP material, that
replacement of the qualifying vintage material was required in place of other methods of redress,
or that the company needed to replace the other qualifying vintage material at the same rate as it
had the LPP material. The Commission also found that Nicor’s justifications for its distribution
investments lacked meaningful definitions and “concrete” evidentiary support. On these bases, the
Commission adopted the Attorney General’s recommendation to disallow $55.1 million of Nicor’s
proposed distribution investment costs.
¶ 47 2. MAOP Investments
¶ 48 Effective July 1, 2020, section 192.624(b) of the Code of Federal Regulations (49 C.F.R.
§ 192.624(b) (2022)) required all gas utilities to develop and document procedures concerning the
maximum allowable operating pressure (MAOP) of their gas transmission pipelines (MAOP Rule).
Specifically, the MAOP Rule required gas utilities to reconfirm the MAOP of 50% of their
applicable pipelines by July 3, 2028, and 100% of their applicable pipelines by July 2, 2035. Id.
The six methods that a gas utility was permitted to use to reconfirm MAOP were: (1) pressure
testing, (2) pressure reduction, (3) engineering critical assessment, (4) pipe replacement,
15 (5) pressure reduction for pipeline segments with small potential impact radius, and (6) alternative
technology (reconfirmation methods). Id. § 192.624(c).
¶ 49 a. Nicor’s Proposed Recovery of MAOP Investment Costs
¶ 50 Nicor sought to recover $57.7 million in MAOP reconfirmation investment costs and
submitted a 15-year plan to complete MAOP reconfirmation. Whiteside testified that Nicor had “a
comprehensive process to analyze pipeline segments requiring reconfirmation to determine
appropriate actions to achieve reconfirmation.” Whiteside explained that, as part of this process,
Nicor performed a records research and review to determine compliance with “49 CFR Part 192
regulations,” identified pipeline segments that required MAOP reconfirmation, and then selected
one of the six reconfirmation methods to address the pipelines that required MAOP reconfirmation.
Whiteside also added that “[f]urther risk and prioritization criteria” was based on factors such as
Nicor’s ability to reduce pressure, Nicor’s ability to take the pipeline segment out of service,
impact to customers, and financial impact. According to Whiteside, Nicor was on course to achieve
50% compliance with the MAOP Rule by 2023, five years in advance of the 2028 compliance
deadline.
¶ 51 b. The Attorney General’s Proposed Recovery of MAOP Investment Costs
¶ 52 The Attorney General recommended that the Commission deny 75%, or $43.3 million, of
Nicor’s proposed MAOP reconfirmation investment costs. Walker testified that Nicor had
identified approximately 368 miles of pipeline in its gas transmission system that were subject to
the MAOP Rule, and that, after initiating a records review, the company had determined that 67
miles of pipeline required remediation. Walker explained that Nicor had not completed its records
review and that he estimated that there would be a total of 93 miles of pipeline that would require
remediation. Walker stated that Nicor had indicated that, of the six reconfirmation methods, the
16 company intended to make pressure testing and replacement its two primary means of MAOP
reconfirmation.
¶ 53 Walker expressed that he was concerned about the pace of Nicor’s MAOP reconfirmation
plan. He noted that, when Nicor was asked its reasons for frontloading its MAOP reconfirmation
work, the company stated that it did not have a time-based plan for replacement and refused to
state the year in which it would achieve 100% compliance with the MAOP Rule. Walker thus
concluded that Nicor had frontloaded its MAOP reconfirmation costs without justification.
¶ 54 Walker testified that he was also concerned that Nicor was replacing too many of its
pipelines that required remediation, rather than using one of the other reconfirmation methods. He
explained that the Pipeline and Hazardous Materials Safety Administration (PHMSA) had
estimated that only 300 miles, or 0.18%, of the 168,000 miles of onshore transmission pipelines
installed prior to the 1970 requirement of hydrostatic pressure testing would need to be replaced
to conform with the MAOP Rule. Walker further explained that if this ratio were applied to Nicor’s
gas transmission system, then the company would be expected to replace less than one quarter of
one mile of its pipeline, which it had exceeded. Walker thus ultimately recommended that the
Commission disallow $43.3 million of Nicor’s proposed MAOP reconfirmation investment costs.
¶ 55 Bradley Cebulko, senior manager at Strategen Consulting and a witness for the Public
Interest Organizations, testified that Nicor had not demonstrated that its MAOP reconfirmation
investment costs were prudent, partly in that “the [c]ompany did not appear to have evaluated all
six MAOP reconfirmation methods *** and the [c]ompany mistakenly claim[ed] that the lack of
records prevent[ed] reconfirmation through means other than pipeline replacement.” Cebulko
stated that Nicor also did “not appear to have instituted an Engineering Critical Assessment (ECA)
process, one of the six MAOP reconfirmation methods, suggesting that the [c]ompany’s existing
17 methodology may not be comprehensive.” Cebulko explained that the fact that Nicor did not have
an ECA process also increased the risk that the company was reconfirming pipeline segments using
less cost-effective measures such as replacement.
¶ 56 c. The Commission’s Findings
¶ 57 In its order, the Commission found that the Attorney General had presented sufficient
evidence to show that Nicor might have been frontloading its MAOP reconfirmation work for the
2035 compliance period. The Commission separately noted that Nicor had provided “no basis for
the 2024 budget increase other than the number of miles it believe[d] still need[ed] remediation”
and that Nicor had already achieved 50% compliance ahead of the 2028 MAOP reconfirmation
deadline and had “nearly 12 years” to achieve full compliance with the MAOP Rule. The
Commission then stated that, because “Nicor *** [was] well ahead of its MAOP reconfirmation
and [had] not sufficiently demonstrated the reasonableness of the 2024 MAOP budget, including
identifying specific projects and scope of work, the Commission believe[d] a pause was necessary
until the Company [had] properly planned and justified its MAOP costs.”
¶ 58 Based on its findings, the Commission adopted the Attorney General’s recommendation to
disallow $43.3 million of Nicor’s MAOP reconfirmation investment costs. The Commission also
directed Nicor to submit an MAOP and Records Compliance Plan (Compliance Plan) to assist the
Commission in assessing whether Nicor was “fairly” considering its options regarding MAOP
reconfirmation work.
¶ 59 3. Transmission Pipeline Investments
¶ 60 Nicor’s gas distribution system contains intrastate transmission pipelines that transport gas
from interstate pipelines to the company’s delivery points. At the time when it filed its January 3,
2023, tariff sheets, Nicor planned to complete eight future projects on four of its transmission lines.
18 Each project entailed the replacement of pipes between 20 inches and 36 inches in diameter along
segments ranging from 1 mile to 19.2 miles long. The parties contested issues regarding four out
of Nicor’s eight planned projects (contested projects).
¶ 61 a. Nicor’s Proposed Recovery of Transmission Pipeline Investment Costs
¶ 62 Nicor sought to recover approximately $394.5 million in transmission pipeline investment
costs related to its eight future projects. Whiteside testified that three out of Nicor’s four contested
projects were each a phase of the company’s broader Crawford Line project, which involved the
replacement of three miles of a 20-inch pipeline near Crawford Avenue in the southern suburbs of
Chicago. Whiteside explained the following regarding Nicor’s reasons for deciding to replace the
pipeline involved in the Crawford Line project:
“Crawford is a vintage line that was installed in 1950. This line has other limiting
factors such as the inability to reduce pressure, the inability to take the pipeline out of
service, the inability to run in-line inspections, and missing material property data and
pressure test records. This line runs through a developed area primarily down the middle
of major roadways with shallow depth of cover. It is not piggable and relies on costly direct
assessment techniques for integrity management. It is common for third party utilities to
encroach upon and be in contact with the line. With mechanical damage commonly found
on this line during direct assessment digs and the densely populated area this line is in, risk
was a major factor in deciding to replace the line. Given the age, condition, and limitations
on this line, the only other alternative was to do nothing which was not an acceptable
alternative.”
Whiteside also explained that Nicor’s decision to replace the pipeline in the Crawford Line project
was further motivated by the fact the company was obligated to consider the pipeline “to be of the
19 lowest yield strength because [Nicor] did not have the records to verify this information.”
Whiteside thus characterized Nicor’s decision to replace the pipeline in the Crawford Line project
as “prudent.”
¶ 63 The fourth of the contested projects was the Bensenville project, which involved 0.8 miles
of a 20-inch pipeline in Bensenville that Nicor sought to replace because it conflicted with certain
storm sewer installation that was associated with a separate tollway relocation project. Whiteside
testified that, as was similarly so with respect to the Crawford Line project, Nicor needed to
consider the pipeline in the Bensenville project to “be of the lowest yield strength because the
[c]ompany [did] not have the records to verify this information.” Whiteside explained that
applicable code required the performance of additional integrity inspections of the pipeline in the
Bensenville project and that, because this pipeline, which ran through a populated area, was of
unknown yield strength, it was at high risk for potential failure. Whiteside also explained that the
Bensenville project was prioritized “based on the tollway relocation” and stated that replacement
of the pipeline would allow for the establishment of records and MAOP.
¶ 64 b. The Attorney General’s Proposed Recovery of Transmission Pipeline Investment Costs
¶ 65 The Attorney General recommended that the Commission disallow $28.4 million of
Nicor’s proposed transmission pipeline investment costs for the four contested projects. In support
of this recommendation, Walker testified that he performed an industry-standard cost analysis of
the Crawford Line and Bensenville projects. He also explained the following regarding the
methodology that he employed in conducting this industry-standard cost analysis:
“The industry-standard method employed utilizes the concept of financial
measurement based on a pipeline size-relative constant developed using a statistically
significant number of similarly situated pipeline projects. The constant is a multiplier,
20 developed using a regression analysis that takes into account significant pipeline data and
statistics such as physical measurements and regional cost differences to produce a cost-
determination constant based upon Diameter-Inches-Miles (Dia-inch-Miles). This constant
can then receive a regional cost amplification multiplier. Further, accommodations for
urban versus rural siting, and cost escalation to coincide value and time can also be
appropriate. Once a cost-determination constant has been established, comparative
benchmarking of Nicor’s proposed transmission pipeline costs and budgets can be made.
Utilizing the nominal diameter of the pipeline and the pipeline’s length as
multipliers to the [dollar] per Dia-in-Mile cost-determination constant results in a base cost
budget for the pipeline project. Following the determination of the base cost budget, the
application of regional cost and financial cost alignment amplification multiples can be
made that result in a reasonable estimate of the natural gas pipeline cost that is then used
to compare with the proposed cost budget ***.”
¶ 66 Walker testified that, upon conducting the industry-standard cost analysis, he calculated a
benchmark of $262,701 per Dia-inch-Mile. Walker also testified that he concluded that the four
contested projects had a per Dia-inch-Mile cost that was “significantly higher” than the calculated
benchmark and that Nicor’s proposed transmission pipeline investment costs were unreasonable.
¶ 67 In rebuttal, Whiteside testified that Walker’s industry-standard cost analysis was faulty in
numerous respects. Whiteside pointed out that, first, Walker had made “a fundamental mistake in
the selection of the projects that he call[ed] ‘similarly situated projects.’ ” Whiteside explained that
“[a]bout the only thing in common” between the contested projects and those that Walker had
deemed similarly situated were the pipeline diameters. Whiteside also asserted that the contested
projects were shorter than those to which Walker had compared them and that Walker had failed
21 to account for the “ ‘economies of scale for a large project’ versus the high degree of friction costs
*** for a small project.’ ” Additionally, Whiteside pointed out that the contested projects were
located in urban areas, which encompass geographical and other challenges that substantially
increase costs, unlike the rural projects upon which Walker had relied to establish his benchmark.
Whiteside also pointed out that the costs for two of the contested projects were based on
competitive bidding and that the costs for all four contested projects were based on Chicagoland
pricing rather than on rural pricing.
¶ 68 In his own rebuttal, Walker testified that he “accept[ed Nicor’s] position regarding the
increased costs of construction in an urban environment and added ten percent to the revised costs
in [his] analysis.” Walker testified that he also “included an additional conservative modifier in
[his] benchmarking analysis to account for these incremental costs in the amount of $300,000 per
project.” Walker explained that, by making these additions, he then accounted for “six different
factors” that added costs to his benchmark basis and that his approach incorporated “many” of the
variables that both he and Nicor had earlier identified.
¶ 69 In surrebuttal, Whiteside testified that Walker’s act of adding 10% to his calculated
benchmark was inadequate to address the differences between rural and urban pricing and did not
“cure its deficiencies.” Whiteside explained that this was partly because Walker had made an
unreasonable and inaccurate assumption that the 10% addition would fully account for the cost
differentials between urban and rural projects. Whiteside further explained that urban projects
could cost two to five times more than rural projects of the same length.
¶ 70 c. The Commission’s Findings
¶ 71 In its Order, the Commission detailed the evidence presented by both Nicor and the
Attorney General and found that Nicor had not met its burden of establishing that the transmission
22 investment costs for the contested projects were reasonable and prudent. The Commission stated
that “[s]imply presenting actual incurred or budgeted costs [was] not evidence of prudence and
[could] not absolve [Nicor] of its statutory obligation to demonstrate prudence and used-and-
usefulness.” The Commission pointed to the fact, for example, that Nicor had alleged that certain
work could cost more for smaller projects, but then did not identify the specific costs for such work
in relation to its own projects. The Commission also pointed out that, although Nicor had further
alleged that some of the costs for the contested projects were “budgeted or bid,” the company made
no showing that it selected the lowest bids. Additionally, the Commission found that Nicor had
inadequately shown that the 10% increase that Walker added to his calculated benchmark
insufficiently accounted for Nicor’s work in urban areas, especially considering that Nicor’s
service area also included cities, towns, and suburban areas in addition to urban areas. The
Commission consequently adopted the Attorney General’s recommendation to disallow $28.4
million of Nicor’s proposed transmission pipeline investment costs.
¶ 72 iii. Long-Term Gas Infrastructure Plan
¶ 73 The Public Interest Organizations recommended that the Commission require Nicor to file
a long-term gas infrastructure plan (infrastructure plan) every two years. Cebulko testified that
“comprehensive, public planning [could] discipline Nicor’s spending, help[***] the Commission
assess risk to customers and the utility ***, manage the pace of the [c]ompany’s investments ***,
and limit customer bill impacts ***.” Cebulko stated that he assumed that Illinois gas utilities
engaged in planning, but that no utility plans longer than a year were made available to the public
or Commission or contained sufficient detail. Cebulko explained that, consequently, it was difficult
for one to determine whether the utility was choosing the “least-cost, least-risk” solution to address
customer needs and whether the utility’s assumptions regarding the future were reasonable.
23 Cebulko believed that public planning could help mitigate this “inherent information asymmetry”
between utilities and the Commission and public and, in turn, help the Commission ensure that
utilities’ decisions resulted in safe, affordable, and reliable service to their customers.
¶ 74 Cebulko further recommended that Nicor identify in each of its infrastructure plans “the
lowest societal cost gas distribution system investments necessary to meet customer demand and
comply with public policy objectives.” He also recommended that Nicor include information such
as its proposed system expenditures and investments, a demonstration that the infrastructure plan
would minimize rate impacts on customers, a showing that the plan would comply with all
applicable rules and requirements, and mapping that shows area of risk and the locations of planned
projects.
¶ 75 In its order, the Commission agreed with Cebulko that Nicor likely engaged in planning
and that the fact that the company did not share its plans with the public created an information
asymmetry between the company and the Commission. The Commission expressed that Nicor’s
lack of public planning made it difficult for the Commission, as well as the company’s customers
and investors, to determine whether Nicor was prioritizing investments that were likely to be used
and useful. The Commission further expressed that, “to aid in [its] informed review of this and
future rate increases,” it would adopt some of the reporting recommendations made during the
case. The Commission ultimately ordered Nicor to file an infrastructure plan every two years,
beginning on July 1, 2025.
¶ 76 II. ANALYSIS
¶ 77 A. Standards of Review
¶ 78 Section 9-101 of the Act states that “[a]ll rates or other charges made, demanded or received
*** shall be just and reasonable.” 220 ILCS 5/9-101 (West 2022). Relatedly, section 9-201(c) of
24 the Act states that, “[i]f the Commission enters upon a hearing concerning the propriety of any
proposed rate or other charge, *** [then] the Commission shall establish the rates or other charges
*** which it shall find to be just and reasonable.” Id. § 9-201(c).
¶ 79 “The Commission is not merely an arbitrator between the utility and parties opposing a rate
change[;] it is an investigator and regulator of utilities[,] responsible for the setting of just rates for
all affected by the rates.” (Internal quotation marks omitted.) Citizens Utility Board v. Illinois
Commerce Comm’n, 2018 IL App (1st) 170527, ¶ 25. Thus, when setting rates, the Commission
must balance the interests of the utility and the utility’s investors and customers. See Business &
Professional People, 146 Ill. 2d at 208 (“The Commission is charged by the legislature with setting
rates which are ‘just and reasonable’ not only to the ratepayers but to the utility and its
stockholders.” (Emphasis in original.)). Specifically, this court has articulated the following:
“The Commission has the responsibility of balancing the right of the utility’s investors to
a fair rate of return against the right of the public that it pay no more than the reasonable
value of the utility’s services. While the rates allowed can never be so low as to be
confiscatory, within this outer boundary, if the rightful expectations of the investor are not
compatible with those of the consuming public, it is the latter which must prevail.” Camelot
Utilities, Inc. v. Illinois Commerce Comm’n, 51 Ill. App. 3d 5, 10 (1977).
¶ 80 The utility bears the burden of proving that its proposed rates are just and reasonable. 220
ILCS 5/9-201(c) (West 2022). To prove this, “the utility must show that its operating costs are
reasonable, its rate base is the reasonable value of its property used for serving the public, and its
rate of return on capital is the reasonable cost of the capital needed to provide the services.”
Citizens Utility Board, 276 Ill. App. 3d at 746.
25 ¶ 81 The Commission “must allow the utility to recover costs prudently and reasonably
incurred.” Citizens Utility Board, 166 Ill. 2d at 121 (citing 220 ILCS 5/1-102(a)(iv) (West 1992)).
“ ‘Prudence is that standard of care which a reasonable person would be expected to exercise under
the same circumstances encountered by utility management at the time decisions had to be made.’ ”
Illinois Power Co. v. Illinois Commerce Comm’n, 339 Ill. App. 3d 425, 428 (2003) (quoting Illinois
Power Co. v. Illinois Commerce Comm’n, 245 Ill. App. 3d 367, 371 (1993)). “[T]he prudence
standard recognizes that reasonable persons can have honest differences of opinion without one or
the other necessarily being ‘imprudent.’ ” Id. at 435. “[T]he Commission should disallow recovery
of any cost of capital in excess of that reasonably necessary for the provision of services.” Citizens
Utility Board, 276 Ill. App. 3d at 746.
¶ 82 Judicial review of final orders issued by the Commission “involves the exercise of special
statutory jurisdiction and is constrained by the provisions of the [Act].” Commonwealth Edison
Co. v. Illinois Commerce Comm’n, 2019 IL App (2d) 180504, ¶ 51. Section 10-201(d) of the Act
states that the “rules, regulations, orders or decisions of the Commission shall be held to be
prima facie reasonable” and that the burden of proof upon all issues raised by an appeal from an
order issued by the Commission is upon the party appealing from that order. 220 ILCS 5/10-201(d)
(West 2022). A reviewing court is required to give substantial deference to the orders of the
Commission because of the Commission’s expertise and experience in the area of setting rates.
Commonwealth Edison Co. v. Illinois Commerce Comm’n, 398 Ill. App. 3d 510, 514 (2009). Thus,
a Commission regulation may be set aside “only if it is clearly arbitrary, capricious, or
unreasonable.” Central Illinois Public Service Co. v. Illinois Commerce Commission, 268 Ill. App.
3d 471, 476-77 (1994).
26 ¶ 83 When reviewing a Commission order, courts are limited to determining the following four
issues: “(1) whether the Commission acted within the scope of its authority, (2) whether the
Commission made adequate findings in support of its decision, (3) whether the Commission’s
decision was supported by substantial evidence in the record, and (4) whether constitutional rights
have been violated.” Id. at 476. “Substantial evidence” is “evidence that a reasonable mind might
accept as adequate to support a conclusion” and is “more than a scintilla of evidence but *** less
than a preponderance of the evidence.” (Internal quotation marks omitted.) Save Our Illinois Land
v. Illinois Commerce Comm’n, 2022 IL App (4th) 210008, ¶ 37. If reasonable minds could differ
as to where the weight of the evidence lies, then a reviewing court should defer to the
Commission’s finding of fact. Id. “The substantial-evidence standard is the same as the manifest-
weight standard.” Id.
¶ 84 “The findings and conclusions of the Commission on questions of fact shall be held
prima facie to be true and as found by the Commission,” except when a finding or conclusion is
not supported by substantial evidence or, otherwise stated, is against the manifest weight of the
evidence. 220 ILCS 5/10-201(d) (West 2022); see People ex rel. Raoul v. Illinois Commerce
Comm’n, 2025 IL App (4th) 230491, ¶ 54. “[A] finding is against the manifest weight of the
evidence if all reasonable persons would agree that the finding is erroneous and that the opposite
conclusion is evident.” (Internal quotation marks omitted.) Raoul, 2025 IL App (4th) 230491, ¶ 54.
¶ 85 Separately, we decide questions of law, such as the interpretation of statute or a regulation
of the Commission, de novo. Save Our Illinois Land, 2022 IL App (4th) 210008, ¶ 42. “While we
are not bound by the Commission’s conclusion on questions of law, we will give substantial weight
and deference to an interpretation of an ambiguous statute by the agency charged with the
administration and enforcement of the statute.” (Internal quotation marks omitted.) People ex rel.
27 Madigan v. Illinois Commerce Comm’n, 2011 IL App (1st) 101776, ¶ 6. The reason for this
deference is that “courts appreciate that agencies can make informed judgments upon the issues,
based upon their experience and expertise[,] and *** agencies must have wide latitude to adopt
regulations reasonably necessary to effectuate their statutory functions.” (Internal quotation marks
omitted.) Id.
¶ 86 Additionally, mixed questions of law and fact are reviewed for clear error. Id. ¶ 8. A mixed
question of law and fact is one that asks the legal effect of a given set of facts or, otherwise stated,
“is one in which the historical facts are admitted or established, the rule of law is undisputed, and
the issue is whether the facts satisfy the statutory standard, or whether the rule of law as applied to
the established facts is or is not violated.” Id. An agency decision is clearly erroneous when “the
reviewing court, on the entire record, is left with the definite and firm conviction that a mistake
has been committed.” (Internal quotation marks omitted.) Id. ¶ 9.
¶ 87 B. Capital Structure
¶ 88 First, Nicor argues that the Commission erred in numerous ways in rejecting its proposed
capital structure, which Nicor asserted before the Commission reflected its actual capital structure.
Nicor argues that, to start, the Commission applied the incorrect legal standard in deciding whether
to adopt Nicor’s proposed capital structure, in that the Commission noted in its Order the qualities
of an “optimal” capital structure and that Nicor’s proposed capital structure contained more
common equity than “necessary.” According to Nicor, by requiring that it have an “optimal” capital
structure and no more common equity than “necessary,” the Commission deviated from the proper
legal standard, which compelled Nicor’s proposed capital structure only to have been reasonable.
¶ 89 Section 16-108.5(c) of the Act mandates that the rates set by the Commission “[r]eflect the
utility’s actual year-end capital structure for the applicable calendar year, *** subject to a
28 determination of prudence and reasonableness consistent with Commission practice and law.” 220
ILCS 5/16-108.5(c) (West 2022). “[T]he Commission shall not include any *** incremental risk
*** [or] increased cost of capital *** which is the direct or indirect result of the public utility’s
affiliation with unregulated or nonutility companies.” Id. § 9-230. Additionally, “the Commission
should disallow recovery of any cost of capital in excess of that reasonably necessary for the
provision of services.” Citizens Utility Board, 276 Ill. App. 3d at 746. “If a utility has included
excessive equity in its capital structure, it has inflated the rate of return and its capital cost.” Id.
¶ 90 Here, the Commission’s statement in its Order that Nicor’s proposed capital structure
contained more common equity than “necessary” corresponds with the rule noted in case law that
a utility cannot recover costs beyond those that were “reasonably necessary.” See id. Additionally,
although the Commission referred to an “optimal” capital structure in its Order, as Nicor itself
concedes, the Commission nevertheless correctly articulated that “a utility’s actual capital structure
is adopted unless it is found to be unreasonable, imprudent, or unfairly burdensome.” See 220
ILCS 5/16-108.5(c) (West 2022). Further, in deciding whether to adopt Nicor’s proposed capital
structure, the Commission expressly considered whether the utility’s proposed common equity
ratio was high due to its association with unregulated entities, which accords with section 9-230
of the Act. See id. § 9-230. Thus, we find that the Commission applied the correct legal standard
in assessing Nicor’s proposed capital structure.
¶ 91 Next, Nicor argues that the Commission incorrectly ruled that its proposed capital structure
was unreasonable and that the Commission’s reasons for rejecting its proposed capital structure
had “no basis in the record.” Specifically, Nicor argues that the Commission’s findings that its
proposed equity ratio was high because of its association with unregulated entities and that Nicor
29 could maintain its current credit rating with a common equity ratio of 50% were both unsupported
by evidence.
¶ 92 Related to the Commission’s finding regarding Nicor’s affiliation with unregulated entities,
MacLeod testified in support of Nicor’s position that the fact that the company had a higher credit
rating than its parent company, Southern, was not evidence that Nicor’s affiliation with unregulated
entities increased Nicor’s cost of capital or caused Nicor to have a higher common equity ratio.
He also testified that the Commission had previously taken measures to prevent Nicor’s affiliation
with Southern from impacting Nicor’s credit quality, that Nicor had a common equity ratio of more
than 54.520% “long before it was affiliated with Southern,” and that Nicor had not sent dividends
to Southern since 2017, which indicated that Nicor was not maintaining a higher common equity
ratio than needed to service Southern.
¶ 93 However, counter to Nicor’s position, Kight-Garlisch explained that “[c]orporations have
an economic incentive to maintain relatively low equity ratios *** at the [parent] company level
while maintaining relatively high equity ratios at the utility operating company level” and that this
arrangement was common between parent companies and their subsidiaries and enabled the parent
companies to borrow at lower rates and then earn high equity returns through the subsidiaries.
Kight-Garlisch further explained that, “[t]o service its parent’s obligations, the utility subsidiary
will often maintain a higher equity ratio than it otherwise would have needed, thereby increasing
the utility’s cost of capital.” Kight-Garlisch testified that, specific to this case, Southern had
“infus[ed] *** over $1 billion in equity” into Nicor since 2016, which then allowed Nicor to
maintain an “excessive” common equity ratio of 54.5% and Southern to maintain its own common
equity ratio of only 37%. We find that, in light of Kight-Garlisch’s testimony and despite Nicor’s
assertions to the contrary, there was evidence of record to support the Commission’s finding that
30 Nicor’s proposed common equity ratio was high because of its affiliation with unregulated entities
such as Southern.
¶ 94 As to the second finding by the Commission that Nicor challenges, Kight-Garlisch testified
that Nicor could maintain its current credit rating with a common equity ratio as low as 50%, based
on a return on equity of 9.89%. In its order, the Commission ultimately adopted a common equity
ratio of 50% but authorized a return on equity of only 9.51%. Nicor now asserts that there was
“[n]o evidence” that the company could maintain its current credit rating with a common equity
ratio of 50%, based on a return on equity of 9.51%, rather than 9.89%. Although we acknowledge
that Kight-Garlisch did not directly give an opinion on whether Nicor could maintain its current
credit rating with both a common equity ratio of 50% and a return on equity of 9.51%, her
testimony still constituted at least some evidence of this fact. Moreover, Kight-Garlisch testified
that certain measures that Moody used to assess Nicor’s creditworthiness “should not” have
changed based on the company’s revenue requirement. Thus, we determine that there was also
evidence of record to support the Commission’s finding regarding Nicor’s ability to maintain its
current credit rating.
¶ 95 Nicor further argues that it was improper for the Commission to note that the company’s
proposed common equity ratio was higher than those of other utilities. Nicor asserts that the capital
structures of other utilities were “irrelevant” in this case because “every utility faces different
financial circumstances.”
¶ 96 Section 200.610(b) of the Illinois Administrative Code provides that “the rules of evidence
*** applied in civil cases in the circuit courts of the State of Illinois shall be followed” in contested
cases before the Commission. 83 Ill. Adm. Code 200.610(b) (2000). The Illinois Rules of Evidence
govern proceedings in the courts of Illinois, and Illinois Rule of Evidence 402 states that “[a]ll
31 relevant evidence is admissible.” Ill. R. Evid. 402 (eff. Jan. 1, 2011). “Relevant evidence” is
“evidence having any tendency to make the existence of any fact that is of consequence to the
determination of the action more probable or less probable than it would be without the evidence.”
Ill. R. Evid. 401 (eff. Jan. 1, 2011).
¶ 97 In this case, the Commission does not dispute Nicor’s assertion that every utility faces
circumstances unique to itself. However, regardless of whether all utilities indeed differ from one
another in some ways, there was nothing that precluded the Commission from believing, based on
its experience, that they were all similar enough in other ways to warrant comparing their
respective capital structures. There was also nothing that precluded the Commission from finding,
based on such a belief, that the fact that other utilities had capital structures that contained less
common equity than that proposed by Nicor made it more probable that Nicor’s proposed common
equity ratio was unreasonable. Consequently, we reject Nicor’s argument that evidence of other
utilities’ capital structures was irrelevant in this case and conclude that substantial evidence
supported the Commission’s ultimate determination that Nicor’s proposed capital structure was
unreasonable.
¶ 98 However, as part of its final argument on the issue of its capital structure, Nicor points out
that, in earlier cases, the Commission “had repeatedly approved [the company’s] actual capital
structure with ratios similar to or even greater than the one [the company] proposed [in this case],”
despite there having been “a greater difference between [the company’s] actual capital structure
and the average capital structure for other gas utilities nationwide ***.” (Emphasis in original.)
Nicor further points out that the Commission had “also previously refused to accept an industry
average as an appropriate benchmark for prudence, because each utility is different and faces
different constraints.” Nicor argues that, in rejecting the company’s proposed common equity ratio
32 on the basis that it was higher than typically approved, the Commission “arbitrarily departed” from
its precedent and, thus, was required to acknowledge and justify the divergence.
¶ 99 Illinois courts have consistently articulated that the doctrine of res judicata does not apply
to Commission decisions. See, e.g., GridLiance Heartland LLC v. Illinois Commerce Comm’n,
2023 IL App (5th) 230073, ¶ 53. Rather, the Commission has the power to deal with each situation
before it, regardless of how it might have dealt with a similar or the same situation in the past.
Citizens Utility Board v. Illinois Commerce Comm’n, 291 Ill. App. 3d 300, 307 (1997).
Additionally, the Commission may change its policies regarding substantive issues, so long as the
changes are not implemented in an arbitrary and capricious manner. United Cities Gas Co. v.
Illinois Commerce Comm’n, 225 Ill. App. 3d 771, 782 (1992). However, when “the Commission
departs from its ‘usual rules of decision to reach a different, unexplained result in a single case,’
thus depriving a party of equal treatment before the Commission, [its decision will] be entitled to
less deference on review.” Abbott Laboratories, Inc. v. Illinois Commerce Comm’n, 289 Ill. App.
3d 705, 715 (1997) (quoting Central Illinois Public Service Co., 268 Ill. App. 3d at 479).
¶ 100 Here, even if it is true that the Commission has previously approved common equity ratios
greater than that proposed by Nicor in this case, Nicor fails to identify a particular rule of decision
from which the Commission supposedly deviated in rejecting the company’s proposed common
equity ratio. See 5 ILCS 100/1-70 (West 2022) (defining the term “rule” in the context of
administrative agencies). Moreover, even if it is also true that the Commission has previously
refused to rely upon an industry average to measure a utility’s prudence, in noting in its Order that
Nicor’s proposed common equity ratio was greater than those typically approved, the Commission
expressly stated that this consideration was “not dispositive.” Thus, we find that the Commission
did not deviate from any of its rules of decisions to such a degree so as to warrant us giving less
33 deference to its decision in this case. See Citizens Utility Board, 291 Ill. App. 3d at 304 (“[T]he
Commission’s decisions are entitled to less deference when the Commission drastically departs
from past practice.” (Emphasis added.)).
¶ 101 C. Distribution Investment Costs
¶ 102 Second, Nicor argues that the Commission erred by disallowing $55.1 million of the
company’s proposed distribution investment costs. To start, Nicor asserts that, in its order, the
Commission “held” that [the company] should not incur [infrastructure replacement] costs until
replacement was immediately ‘required’ or ‘urgently’ needed.” Nicor also asserts that the
Commission’s ruling on the issue of its distribution investment costs amounted to a “categorical
finding of imprudence” that was based on the fact Nicor had proactively addressed known safety
risks in its distribution infrastructure prior to any harm being imminent.
¶ 103 A review of the Order in this case shows that the Commission never once stated that Nicor
was required to wait until harm was imminent or the replacement of distribution infrastructure was
“immediately required” or “urgently needed” in order to recover the costs of then performing the
replacement. Rather, the Commission expressly stated that it was tasked with considering multiple
factors in deciding whether to approve Nicor’s proposed distribution investment costs. According
to the Commission, these factors included the “types of pipes to be replaced, to what degree safety
and reliability [were] affected, and importantly, at what cost.” (Emphasis added.)
¶ 104 Additionally, Nicor is correct that the Commission noted that the company had failed to
establish that the replacements that it sought to complete were “required” and as “urgent[***]” as
those of LPP materials. However, the Commission noted this within its broader analysis of whether
Nicor had presented sufficient evidence as to each of the relevant considerations. Indeed, the
Commission did not disallow a portion of Nicor’s proposed distribution investment costs on the
34 sole basis that the company had failed to prove that the replacements were “immediately required”
or “urgently needed.” To the contrary, it denied the proposed costs on the additional basis that the
Attorney General had presented more compelling evidence as to the multiple questions that the
Commission had to consider. Thus, we reject Nicor’s argument that the Commission categorically
found that the company’s infrastructure replacement costs were imprudent solely because the
company had proactively addressed known safety risks in its gas distribution system.
¶ 105 Nicor also argues that its distribution investment costs were prudently incurred. We find
the decision in Ameren Illinois Co. v. Illinois Commerce Comm’n, 2025 IL App (5th) 240014, to
be instructive in addressing Nicor’s argument.
¶ 106 In Ameren, Ameren Illinois Company (AIC), a natural gas utility, filed proposed tariff
sheets in which it sought to recover $186 million in distribution investment costs, based on a future
test year. Id. ¶¶ 1, 3, 6. AIC specified that it needed to invest in its infrastructure to replace the
mechanically coupled steel mains and services that it contained. Id. ¶ 6. The company presented
evidence that its mechanically coupled steel mains and services were “a ‘top threat to the integrity
of the distribution system,’ ” were “ ‘prone to leakage,’ ” and were “ ‘two of the [c]ompany’s top
leak risks.’ ” Id. The company also presented evidence that it had between 600 and 800 miles of
mains with mechanically coupled steel out of its 8,900 miles of steel mains. Id.
¶ 107 The Attorney General recommended that the Commission disallow $45.5 million of AIC’s
proposed distribution investment costs. Id. ¶ 7. In support of this recommendation, the Attorney
General argued that AIC’s infrastructure did not include LPP materials and that the mechanically
coupled steel in its infrastructure was not as likely as LPP materials to leak. Id. The Attorney
General further argued that AIC had already completed “a large part of” the remediations to its gas
distribution system; that, more specifically, AIC had already remediated 533 miles of mechanically
35 coupled steel pipes out of its estimated 1,233 miles of such pipes; and that AIC was “well ahead”
of the remediation deadlines set by the applicable regulations. Id. Additionally, the Attorney
General argued that AIC had failed to identify, “with specificity,” which of its projects underlay
the proposed increase in costs related to mains and services, as well as to quantify the alleged risk
that AIC sought to mitigate by performing the proposed replacements. Id. The Attorney General
argued that, thus, AIC’s remediation process should be slowed. Id.
¶ 108 In its decision, the Commission in Ameren credited the testimony of the Attorney General’s
experts, which it found to be persuasive and reasonable. Id. ¶ 13. Ultimately, the Commission
adopted the Attorney General’s recommendation to disallow $45.5 million, or 33%, of AIC’s
proposed distribution investment costs. Id.
¶ 109 On appeal, AIC argued that the Commission had erroneously disallowed portions of its
proposed distribution investment costs. Id. ¶ 64. In addressing this argument, the court noted that
the record revealed that AIC had not compared the level of risk for mechanically coupled steel to
that of LPP materials, that AIC had failed to specifically define the subset of mechanically coupled
steel in its infrastructure that was at issue, and that there was no evidence that AIC had graded the
risks in its infrastructure or identified which specific parts of its infrastructure were most prone to
leaking or had the highest-risk leaks. Id. ¶ 68. The court also noted that AIC had answered the
Attorney General’s questions regarding the company’s distribution investment costs by stating
merely that bases for the costs were “safety and reliability.” (Internal quotation marks omitted.) Id.
Describing this answer as “seriously lacking in detail,” the court upheld the Commission’s
disallowance of portions of AIC’s proposed distribution investment costs. Id. ¶¶ 68, 71.
¶ 110 We find the facts in Ameren to be analogous to those in this case. To start, like AIC, who
had already remediated 533 out of the 1,233 miles of its mechanically coupled steel pipes by the
36 time of its proposal, Walker testified that Nicor had already reduced the LPP mains and services
in its gas distribution system by 83% and 88.5%, respectively, by the time of its own proposal.
Also like AIC, who the Commission found had not compared the risk level for mechanically
coupled steel to that of LPP materials, the Commission in this case similarly found that Nicor had
not shown that the qualifying vintage material that it sought to replace posed similar risks as LLP
materials. Additionally, AIC and Nicor both attempted to justify their distribution investment costs
by stating that they were incurred to ensure the safety and reliability of their gas distribution
systems, but the Commission similarly found in both cases that the companies’ justifications lacked
sufficient detail. Because of these similarities, we follow the court in Ameren by analogously
finding that the Commission’s determination in this case to disallow $55.1 million of Nicor’s
proposed distribution costs was proper, despite the evidence presented by the company.
¶ 111 D. MAOP Investment Costs
¶ 112 Third, Nicor argues that the Commission erred by disallowing $43.3 million of its MAOP
reconfirmation investment costs. Nicor also asserts that the Commission’s determination was
“fatally flawed in several respects” where the Commission stated that, because “Nicor *** [was]
well ahead of its MAOP reconfirmation and [had] not sufficiently demonstrated the reasonableness
of the 2024 MAOP budget, including identifying specific projects and scope of work, the
Commission believe[d] a pause was necessary until the Company [had] properly planned and
justified its MAOP costs.”
¶ 113 Returning to the Ameren decision, the Commission there disallowed 75% of AIC’s
proposed MAOP investment costs and required AIC to submit a Compliance Plan to “assist the
Commission in assessing whether AIC was fairly considering its options when pursuing MAOP
reconfirmation work.” Id. ¶ 22. In arriving at its decision, the Commission found that the record
37 was insufficient to approve AIC’s proposed MAOP investment costs, in light of “AIC’s lack of
detail on a per-project basis and other reasonable potential (and less costly) alternatives,” as well
as the fact that “AIC did not ‘enable the Commission, Staff, or stakeholders to recreate, verify, or
assess [AIC’s] analysis.’ ” Id. ¶ 21.
¶ 114 The Commission in Ameren also found that it had been shown that AIC would accomplish
50% compliance with the MAOP Rule in 2023 and full compliance by 2028, “nearly seven years
before the 2035 compliance deadline.” Id. ¶ 22. The Commission further found that the evidence
supported its concerns “ ‘with the cost and pace of the Company’s MAOP reconfirmation
efforts.’ ” Id.
¶ 115 On appeal, the court in Ameren considered whether the Commission’s disallowance of 75%
of AIC’s proposed MAOP investment costs was proper. Id. ¶¶ 73-87. The court began by noting
that, in documentation that it had submitted to the Commission, AIC had outlined each of its
MAOP projects and explained the company’s reasons for using replacement to remediate the
pipeline segments at issue. Id. ¶ 85. The court stated that, thus, “[t]he Commission decision
ignore[d] the evidence where AIC explained why it chose each MAOP reconfirmation method,”
and further noted that AIC had explained “that the appropriate method of reconfirmation depended
on numerous factors.” Id.
¶ 116 The court in Ameren also noted that AIC had provided a timeline for its planned MAOP
reconfirmation showing that reconfirmation would occur over the next eight years as follows:
“2023-20.3 miles, 2024-11.2 miles, 2025-11.4 miles, 2026-6.5 miles, 2027-14.2 miles, 2028-8.9
miles, and 2030-0.9 miles.” Id. ¶ 86. The court also found “[e]qually concerning” the fact that the
Commission had “simply eliminated” all of AIC’s MAOP projects, despite the fact that some of
the projects included “MAOP reconfirmation work that was not based on main replacement as well
38 as projects that did not involve MAOP reconfirmation.” Id. ¶ 87. The court found that the
Commission’s decision to disallow 75% of AIC’s proposed MAOP investment costs was not
supported by substantial evidence. Id. However, the court did express, as a final note, that it found
“it disingenuous for the Commission to penalize AIC for allegedly failing to *** meet a standard
not previously required—i.e., a MAOP and Records Compliance Plan—prior to the issuance of
the Commission decision, especially when it provided the statutorily required information.” Id.
¶ 117 As was similarly so in Ameren, the Commission in this case expressed a concern that Nicor
had been frontloading its MAOP work and ordered Nicor to file a compliance plan. Nicor also
presented evidence that it used “a comprehensive process to analyze pipeline segments requiring
reconfirmation to determine appropriate actions to achieve reconfirmation” and considered factors
such as the company’s ability to reduce pressure, the company’s ability to take the pipeline segment
out of service, impact to customers, and financial impact.
¶ 118 However, unlike AIC in Ameren, which submitted documentation to the Commission that
outlined each of its MAOP projects and explained the company’s reasons for using replacement to
mediate the pipeline segments at issue, the Commission in this case found that Nicor had not
identified its specific MAOP projects or the scope of the work involved in each project, which
Nicor does not now dispute. Also unlike AIC, which provided a timeline for its planned MAOP
reconfirmation, in this case, Walker testified that Nicor had outright stated that it did not have a
time-based plan for replacement and refused to state the year in which it would achieve 100%
compliance with the MAOP Rule. Without this depth of information having been provided, we are
unable to determine, as the court analogously did in Ameren, whether the Commission in this case
improperly disallowed a sweeping 75% of Nicor’s proposed MAOP investment costs despite some
of the costs arising outside of any pipeline replacement or MAOP reconfirmation work. Thus, we
39 uphold the Commission’s determination in this case to disallow $43.3 million of Nicor’s proposed
MAOP investment costs.
¶ 119 Last on this issue, Nicor argues that the Commission’s decision regarding the company’s
proposed MAOP investment costs in this case constituted a departure from its decisions in “at least
two prior rate cases.” Nicor points out that, in these prior rate cases, the Commission approved
Nicor’s proposed MAOP investment costs that were “presented with the same degree of
specificity” as in this case, despite the Attorney General having made “the same” arguments. Nicor
asserts that, in deviating from its decisions in these prior cases, the Commission was required to
acknowledge its “prior practice” and justify its deviation therefrom.
¶ 120 Otherwise stated, Nicor’s present argument seems to be that the Commission should have
approved the company’s proposed MAOP investment costs in this case because it had approved
such costs under similar circumstances in past cases. However, as we earlier articulated, orders by
the Commission do not have the effect of res judicata, and the Commission has the authority to
address each matter before it freely, even if a matter involves issues identical to those previous.
Commonwealth Edison Co. v. Illinois Commerce Comm’n, 2016 IL 118129, ¶ 24. Thus, we find
Nicor’s argument to be meritless.
¶ 121 E. Transmission Pipeline Investment Costs
¶ 122 Fourth, Nicor argues that the Commission erred by disallowing $28.43 million in proposed
transmission pipeline investment costs. Specifically, Nicor argues that the Commission’s finding
that the company did not demonstrate that such costs were reasonable and prudent with respect to
the four contested projects was “manifestly incorrect” because, in so finding, the Commission
“ignored” the evidence that Nicor had presented in support of its proposal.
40 ¶ 123 In its Order, the Commission detailed at great length the evidence that Nicor had presented
to support its proposed transmission pipeline investment costs. The Commission noted, for
example, that Nicor had presented evidence that, in conducting his industry-standard cost analysis,
Walker had improperly relied on model projects that had “nothing in common with the
[c]ompany’s projects *** other than the pipeline diameters[***] and presented different economies
of scale and construction challenges.” The Commission further noted Nicor’s additional evidence
that the transmission pipeline investment costs for two of the contested projects were based on
competitive bidding and that the costs for all four contested projects were based on Chicagoland
pricing. Additionally, the Commission acknowledged that Nicor had presented evidence that
Walker’s 10% increase to his calculated benchmark was “neither reasonable or accurate” because
the increase did not fully account for the cost differences between urban and rural projects, with
urban projects tending to be longer and more expensive because of numerous factors. The
Commission detailed Nicor’s evidence to the extent that it negated any suggestion that the
Commission did not consider it. Thus, we reject Nicor’s argument that the Commission “ignored”
its evidence.
¶ 124 However, Nicor further argues that the Commission’s disallowance of $28.43 million of its
proposed transmission pipeline investment costs was erroneous for the additional reason that the
decision was not supported by substantial evidence. In support of the disallowance, Walker
testified that, according to the industry-standard cost analysis that he had conducted, the contested
projects had a per Dia-inch-Mile cost that was “significantly higher” than his calculated benchmark
and that Nicor’s proposed transmission pipeline investment costs were unreasonable. Walker also
explained his methodology in conducting the industry-standard cost analysis and later increased
his calculated benchmark by 10% to account for numerous factors that Nicor identified specific to
41 projects in urban areas. Although Nicor argued that the 10% increase to Walker’s calculated
benchmark insufficiently accounted for the company’s work in urban areas, the Commission found
that Nicor had not sufficiently shown the ways in which the increase was insufficient.
¶ 125 In determining that Nicor’s evidence was inadequate, the Commission further noted that,
despite the fact that the company alleged that certain work could cost more for smaller projects, it
did not offer evidence of what such work would specifically cost in the context of its own projects.
Additionally, the Commission acknowledged Nicor’s evidence that the some of the costs for the
contested projects were “budgeted or bid,” but commented on the fact that Nicor had provided no
evidence to show that it necessarily selected the lowest bids. Based on such a showing by both
Nicor and the Attorney General, we find that the Commission’s disallowance of $28.43 million of
Nicor’s proposed transmission pipeline investments costs was supported by substantial evidence.
¶ 126 F. Long-Term Gas Infrastructure Plan
¶ 127 Fifth, Nicor argues that the infrastructure plan should be vacated because the Commission
exceeded the scope of its authority under the Act by ordering it. Nicor also argues that the
Commission’s “new rule” imposing an infrastructure plan was invalid because the Commission
did not conduct the required “notice-and-comment” process under the Illinois Administrative
Procedure Act (5 ILCS 100/1-1 et seq. (West 2022)).
¶ 128 “The Commission, because it is a creature of the legislature, derives its power and authority
solely from the statute creating it ***.” City of Chicago v. Illinois Commerce Comm’n, 79 Ill. 2d
213, 217-18 (1980). Thus, any acts that the Commission performs outside of its statutory authority
are void as being beyond its jurisdiction. Id.; see Business & Professional People for the Public
Interest v. Illinois Commerce Comm’n, 136 Ill. 2d 192, 243 (1989).
42 ¶ 129 The Commission ordered the infrastructure plan in this case pursuant to sections 4-101, 9-
201(c), 9-211, and 8-501 of the Act. The Commission also cited Abbott Laboratories, 289 Ill. App.
3d 705, in support of its order. In assessing whether these sources authorized the Commission to
order the infrastructure plan, we turn once more to the decision in Ameren, which we again find to
be instructive.
¶ 130 In Ameren, the Commission noted, on the issue of an infrastructure plan, that, “while AIC
likely engaged in internal system planning, AIC d[id] not submit a public long-term system plan,
which create[d] an inherent information asymmetry between [AIC] and the Commission.”
(Internal quotation marks omitted.) Ameren, 2025 IL App (5th) 240014, ¶ 31. The Commission
explained that “AIC’s lack of transparent planning processes made it challenging for the
Commission, customers, and other stakeholders to determine whether AIC was prioritizing prudent
investments that were likely to be used and useful.” (Internal quotation marks omitted.) Id. The
Commission also expressed that “AIC’s capital spending (and associated planning, budgeting, and
project section processes) merit[ed] careful consideration in [that] and future rate cases.” (Internal
quotation marks omitted.) Id. The Commission then ordered AIC to file an infrastructure plan
every two years, beginning on July 1, 2025, and cited sections 4-101, 9-201(c), 9-211, and 8-501
of the Act and Abbott Laboratories, 289 Ill. App. 3d at 712, to support its order. Ameren, 2025 IL
App (5th) 240014, ¶ 31.
¶ 131 On appeal, the court analyzed whether the Commission had the authority to order AIC to
file an infrastructure plan. Id. ¶¶ 64-71. The court first noted that the Commission’s order regarding
the infrastructure plan was “not applicable to the current case” before the Commission, but rather,
“provide[d] a requirement solely for future cases.” (Emphases added.) Id. ¶ 92. The court then
noted that Public Act 102-662 (eff. Sept. 15, 2021) imposed long-term planning requirements for
43 electric utilities but not for gas utilities, and explained that, if the legislature had intended for the
Commission to have the power to order infrastructure plans for utilities, then it would have had no
need to mandate long-term planning requirements for electric utilities in Public Act 102-662.
Ameren, 2025 IL App (5th) 240014, ¶¶ 93, 95-96. The court also found “equally relevant” that the
Commission’s rules already outlined the information that utilities were required to provide to
support their capital recovery requests and stated that, if the Commission truly had the power to
order infrastructure plans, then it could have just amended its rules to require the additional desired
long-term planning information. Id. ¶ 97.
¶ 132 Next, the court found that the Commission’s mandate of an infrastructure plan constituted
a “rule” subject to the Illinois Administrative Procedure Act, which, the court explained, set forth
certain “public notice and comment” requirements that agencies must follow in enacting “rules.”
A “rule” was defined as an “agency requirement that prescribe[d] law or policy affecting the private
rights or procedures of people or entities outside [the] agenc[ies].” Id. ¶¶ 98, 101, 103. The court
concluded that the Commission had failed to comply with the notice and comment provisions of
the Illinois Administrative Procedure Act and, consequently, “vacate[d] the Commission’s
requirement to prepare a long-term *** infrastructure plan as void for being outside the
Commission’s authority.” Id. ¶ 103.
¶ 133 The Commission in this case ordered an infrastructure plan that was nearly identical to that
in Ameren, pursuant to identical authority and after making highly similar findings. See Northern
Illinois Gas Co., Ill. Comm. Comm’n No. 23-0066, at 248-49 (Order-Final Nov. 16, 2023). We
find no reason to depart from the court’s analysis and decision in Ameren. Therefore, we similarly
vacate the infrastructure plan in this case on the grounds that the Commission exceeded its
authority by ordering it.
44 ¶ 134 III. CONCLUSION
¶ 135 For the reasons stated herein, we affirm the Commission’s orders adopting the imputed
capital structure proposed by Staff and disallowing $55.1 million of Nicor’s proposed distribution
investment costs, $43.3 million of the company’s MAOP investment costs, and $28.4 million of
the company’s proposed transmission pipeline investment costs. We vacate the Commission’s
order requiring Nicor to file an infrastructure plan.
¶ 136 Affirmed in part and vacated in part.
45 46 Northern Illinois Gas Co. v. Illinois Commerce Comm’n, 2025 IL App (3d) 240093
Decision Under Review: Petition for review of order of the Illinois Commerce Commission, No. 23-0066.
Attorneys John E. Rooney, of Benesch Friedland Coplan & Aronoff LLP, for and Clifford W. Berlow and Marjorie R. Kennedy, of Jenner & Appellant: Block LLP, both of Chicago, for petitioner.
Attorneys Brian J. Dodds, Robert W. Funk, and Thomas R. Stanton, for Special Assistant Attorneys General, of Illinois Commerce Appellee: Commission, of Chicago, for respondent.
Related
Cite This Page — Counsel Stack
2025 IL App (3d) 240093, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northern-illinois-gas-co-v-the-illinois-commerce-commission-illappct-2025.