Illinois Power Company v. Illinois Commerce Commission

CourtAppellate Court of Illinois
DecidedApril 11, 2008
Docket3-06-0879, 3-07-0569 Cons. Rel
StatusPublished

This text of Illinois Power Company v. Illinois Commerce Commission (Illinois Power Company v. Illinois Commerce Commission) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Illinois Power Company v. Illinois Commerce Commission, (Ill. Ct. App. 2008).

Opinion

No. 3-06-0879 consolidated with No. 3-07-0569

_________________________________________________________________ Filed April 11, 2008 IN THE

APPELLATE COURT OF ILLINOIS

THIRD DISTRICT

A.D., 2008

ILLINOIS POWER COMPANY, ) d/b/a/ AMERENIP, ) ) Petition for Review of an Petitioner-Appellant, ) Order of the Illinois ) Commerce Commission in v. ) Docket No. 03-0699 and ) Docket No. 04-0677. ILLINOIS COMMERCE COMMISSION ) and DYNEGY, INC., ) ) Respondents-Appellees. ) _________________________________________________________________

JUSTICE LYTTON delivered the opinion of the court: _________________________________________________________________

The petitioner, Illinois Power Company, d/b/a AmerenIP

(Illinois Power), seek review of two orders issued by the Illinois

Commerce Commission (Commission), finding that Illinois Power did

not act prudently in remediating deliverability issues at its

natural gas storage facility in Hillsboro, Illinois. As a result,

the Commission concluded that the costs Illinois Power incurred to

obtain natural gas to reinject the field in 2003 and 2004 could not

be recovered from its customers. On appeal, Illinois Power argues

that (1) the Commission’s findings are not supported by substantial

evidence in the record, and (2) the Commission improperly applied

the prudence standard. We affirm.

I. Commerce Commission Proceedings

This consolidated appeal concerns Illinois Power’s Hillsboro

natural gas storage facility. The Hillsboro facility is an underground reservoir that contains two different storage layers.

The top layer of the reservoir contains working gas. Working gas

is the volume of gas in the reservoir that is injected for storage

during the summer months and then withdrawn to be supplied to

customers in the winter months. The bottom layer houses base gas

which is the volume of gas required to provide adequate pressure to

cycle the working gas. Generally, a utility does not remove the

base gas from a reservoir field.

Following an expansion project in 1993, Illinois Power began

experiencing reduced inventory and deliverability problems at the

Hillsboro plant and inadvertently began removing base gas from the

field. After years of investigation, the company determined that

the problems were caused by improper metering. In 2003, they began

reinjecting the field to restore the depleted natural gas

inventory. The reinjection process was not completed until the

spring of 2004. Pursuant to the Public Utilities Act (Act) (220

ILCS 5/10-201 et seq. (West 2002)), Illinois Power passed

$6,879,109 in 2003 and $2,979,849 in 2004 onto its customers in the

form of purchase gas adjustment (PGA) tariffs to recover the costs

of the reinjection process.

In November of 2003, the Commission commenced reconciliation

hearings in accordance with section 9-220 of the Act and directed

Illinois Power to present evidence showing its reconciliation of

PGA tariff revenues with the actual cost of gas supplies prudently

incurred for the 12 month period ending December 31, 2003 (Docket

No. 03-0699). One year later, the Commission initiated a second

reconciliation proceeding directing Illinois Power to present

2 evidence for the 12 month period ending December 31, 2004 (Docket

No. 04-0677). The evidence presented at both proceedings was

substantially the same.

Illinois Power engineers and expert witnesses testified that

the expansion of the Hillsboro field increased the working gas

inventory from 3.1 billion cubic feet (Bcf) to 7.6 Bcf and

increased the peak day capacity (the amount of gas to be withdrawn

per day) from 50,000 million cubic feet (Mcf) to 125,000 Mcf. The

company operated Hillsboro at those levels for the 1993-1994

season. In subsequent winters, however, Illinois Power was unable

to withdraw the full amount of gas that had been previously

injected into the field.

Given the actions taken to expand the storage reservoir, the

possibility existed that the reservoir was physically breached

during the expansion process, thereby allowing the newly injected

gas to escape or migrate into other areas of the reservoir from

which the gas could not be accessed. Other potential causes

involved gas migration, gas leaks to the surface, or damage to the

intake and withdrawing wells, which would have prevented efficient

production of gas inventory. Illinois Power conducted numerous

tests in an attempt to determine the cause of the problem. The

company was concerned about taking corrective action without first

properly identifying the cause of the problem.

The company’s experts testified that because of the expansion,

it was logical and appropriate to focus initially on a reservoir or

structural defect. Thus, Illinois Power decided to pursue an

extensive structural investigation beginning in 1997. Illinois

3 Power had a vertical seismic profile of the reservoir field

prepared by outside consultants. This study concluded that a more

detailed three dimensional seismic analyses was necessary. The

preliminary results of the 3-D seismic study indicated that

approximately 3.5 Bcf of gas had migrated to another structure

northeast of the field. In November 2000, based on the results of

this study, Illinois Power drilled a new well but found no

substructure below. In light of these inconsistent findings,

Illinois Power asked the consultants to reevaluate the 3-D seismic

analysis. After collecting additional information and reprocessing

the 3-D seismic data, the firm concluded that the additional

structure that had been thought to exist to the northeast of the

Hillsboro field did not exist. This conclusion was reached in the

fall of 2001.

While investigating the possibility of structural causes or

reservoir problems, Illinois Power also retained Peterson

Engineering to conduct an audit of the metering instruments at

Hillsboro. Peterson was retained in August of 1999 and issued its

finding in December of 1999. In its report, Peterson identified

two problems with the Hillsboro meters. First, two new turbine

injection meters were over-registering gas volumes under certain

operating conditions. Specifically, when the nearby plant

compressors operated at certain levels, they caused the meters to

over-spin, thereby recording a greater amount of gas as having been

injected than was actually passing through the meter. The turbine

meter over-registration was calculated to be 26% when the

compressors were operating at 50% but only 1.7% when the

4 compressors were operating at 100% loadings. Second, the orifice

meter on one of the four withdrawal wells had an opening that was

smaller than the size value stamped on the orifice plate. The

diameter stamped on the plate was 10% larger than its actual

diameter. This meant that less gas was being withdrawn from the

field that had been believed. In basic terms, there was less gas

going in and less gas coming out than the meters were indicating.

According to Illinois Power, the amount of error on the

withdrawal meter could be easily calculated based on the different

sized orifice measurements. However, the company maintained that

the injection meter over-registration could not be as easily

determined.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Continental Mobile Telephone Company, Inc. v. Illinois Commerce Commission
645 N.E.2d 516 (Appellate Court of Illinois, 1994)
Illinois Power Co. v. Illinois Commerce Commission
790 N.E.2d 377 (Appellate Court of Illinois, 2003)
Illinois Power Co. v. Illinois Commerce Commission
612 N.E.2d 925 (Appellate Court of Illinois, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Illinois Power Company v. Illinois Commerce Commission, Counsel Stack Legal Research, https://law.counselstack.com/opinion/illinois-power-company-v-illinois-commerce-commiss-illappct-2008.