Illinois Power Co. v. Illinois Commerce Comm'n

CourtAppellate Court of Illinois
DecidedMay 9, 2003
Docket5-02-0065 Rel
StatusPublished

This text of Illinois Power Co. v. Illinois Commerce Comm'n (Illinois Power Co. v. Illinois Commerce Comm'n) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Illinois Power Co. v. Illinois Commerce Comm'n, (Ill. Ct. App. 2003).

Opinion

Rule 23 order filed NO.  5-02-0065

April 1, 2003;

Motion to publish granted IN THE

May 9, 2003.

APPELLATE COURT OF ILLINOIS

FIFTH DISTRICT

___________________________________________________________________________

ILLINOIS POWER COMPANY, )  Petition for the Review of

)  an Order of the Illinois

Petitioner, )  Commerce Commission.   

)

v. )  No. 00-0714

THE ILLINOIS COMMERCE COMMISSION )

and THE PEOPLE OF THE STATE OF )

ILLINOIS, )

Respondents. )

___________________________________________________________________________

JUSTICE MAAG delivered the opinion of the court:

Illinois Power Company (Illinois Power), the petitioner, seeks the review of an order that the Illinois Commerce Commission (Commission), the respondent, issued on November 27, 2001, finding that Illinois Power was imprudent in retiring its Freeburg, Illinois, propane plant.  As a result of this finding, the Commission determined that the costs that Illinois Power incurred to obtain pipeline transportation capacity of the propane plant cannot be recovered from its customers.  Illinois Power appeals.  We reverse.

Pursuant to the Public Utilities Act (Act) (220 ILCS 5/1-101 et seq. (West 2000)), Illinois Power is statutorily required to reconcile revenues collected under its purchased-gas adjustment tariff with the actual cost of gas supplies prudently purchased for the 12 months ended December 31, 2000 (reconciliation period).  The tariff clause provides for increases or decreases of the rates or charges of a public utility such as Illinois Power based on changes in Illinois Power's cost of purchased gas.  220 ILCS 5/9-220 (West 2000).  Although the tariff clauses allow for automatic changes in rates without prior Commission approval, the General Assembly requires that the Commission initiate annual hearings to determine whether the clauses reflect the "costs of fuel, gas, power, or coal transportation purchased to determine whether such purchases were prudent."  220 ILCS 5/9-220(a) (West 2000).  In each proceeding, the burden of proof is on the utility to establish the prudence of its fuel, power, gas, or coal transportation purchases and costs.  The standard under which the Commission assesses the prudence of a utility's gas purchases, pursuant to section 9-220 of the Act, is as follows: "Prudence is that standard of care which a reasonable person would be expected to exercise under the same circumstances encountered by utility management at the time decisions had to be made."   Illinois Power Co. v. Illinois Commerce Comm'n , 245 Ill. App. 3d 367, 371, 612 N.E.2d 925, 929 (1993).  When a court considers whether a judgment was prudently made, only those facts available at the time judgment was exercised can be considered.  Hindsight review is impermissible.   Illinois Power Co. , 245 Ill. App. 3d at 371, 612 N.E.2d at 929.

In the instant case, the Commission determined, in relevant part, that the evidence showed that, for the reconciliation period, Illinois Power acted reasonably and prudently in its purchase of natural gas, except with regard to its decision to retire the Freeburg propane plant.

In Illinois Power's case before the Commission, Frank Starbody, Illinois Power's director for gas supply, testified that he is responsible for the procurement of Illinois Power's natural-gas supply and pipeline capacity, the transportation of customer-owned natural gas, and Illinois Power's storage and transmission assets.  Starbody testified that in 2000, Illinois Power purchased 55.2 million MMBtu of natural gas from various producers and marketers.  Illinois Power also leased transportation and storage capacity via five interstate pipelines.  Starbody stated that Illinois Power began the reconciliation period with eight underground gas-storage fields.  One field was retired during the reconciliation period.  Starbody said that Illinois Power designs its supply portfolio so that firm natural-gas supply is sufficient to meet requirements on a peak day.  For 2000, Illinois Power reserved sufficient pipeline capacity and firm winter natural-gas supply to serve, along with the gas deliverable from Illinois Power's storage fields, the gas load expected in weather conditions equivalent to the coldest in the previous 20 years.  Starbody also testified that Illinois Power began the reconciliation period with one propane plant facility with a peak-day deliverability equivalent to 20,000 MMBtu of natural gas.  This facility was retired in 2000.  As a result, during the reconciliation period, Illinois Power used existing propane inventory to operate the propane plant prior to its retirement and did not need to acquire additional supplies of propane during the reconciliation period.

Starbody claimed that in order to continue operating the Freeburg propane plant,  substantial capital expenditures would have been required.  The plant had obsolete compressor controls and switchgear, the fire-protection and gas-detection equipment did not conform to current standards, and the insulation in the refrigerated sphere that holds the propane inventory required replacement.  Starbody opined that regulatory requirements applicable to propane facilities could become more strict, thereby raising the concern that the substantial expenditures that would have been necessary to renovate the propane plant could prove insufficient within a few years.  Starbody stated that the facility was grandfathered under earlier provisions of various codes and standards but that major upgrades to the facility, including those that were needed in 2000, could cause the facility to become subject to current versions of applicable codes and standards.  This would require the propane plant to be brought into compliance with current codes and standards that would require additional capital expenditures.

Starbody was also concerned because the area around the Freeburg propane plant was experiencing significant growth in residential development.  Starbody stated that the risks and consequences associated with gas leakage or fires that are inherent to propane facilities were a matter of increasing concern.  Starbody claimed that the safety issues associated with  the residential areas that were developing around the plant site were a significant factor in the decision to retire the plant.

Starbody also testified that operating a propane facility requires specialized training and experience that is unique to Illinois Power's system.  The Freeburg facility was more complex than the types of propane plants described in the Commission staff's testimony because it included refrigeration, compression, and control equipment not present in other types of propane facilities.  The need for specialized training and expertise, the infrequency with which the plant actually needed to be operated, and the resulting lack of hands-on experience for Illinois Power personnel were additional factors leading to the closing of the Freeburg facility.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thompson v. Illinois Commerce Commission
115 N.E.2d 622 (Illinois Supreme Court, 1953)
Citizens Utilities Co. v. Illinois Commerce Commission
529 N.E.2d 510 (Illinois Supreme Court, 1988)
City of Chicago v. Illinois Commerce Commission
150 N.E.2d 776 (Illinois Supreme Court, 1958)
Monarch Gas Co. v. Illinois Commerce Commission
633 N.E.2d 1260 (Appellate Court of Illinois, 1994)
Mississippi River Fuel Corp. v. Illinois Commerce Commission
116 N.E.2d 394 (Illinois Supreme Court, 1953)
Citizens Utility Board v. Illinois Commerce Commission
651 N.E.2d 1089 (Illinois Supreme Court, 1995)
Illinois Power Co. v. Illinois Commerce Commission
612 N.E.2d 925 (Appellate Court of Illinois, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Illinois Power Co. v. Illinois Commerce Comm'n, Counsel Stack Legal Research, https://law.counselstack.com/opinion/illinois-power-co-v-illinois-commerce-commn-illappct-2003.