Homestake Enterprises, Inc. v. Oliver

817 P.2d 979, 15 Brief Times Rptr. 1321, 1991 Colo. LEXIS 622, 1991 WL 185337
CourtSupreme Court of Colorado
DecidedSeptember 23, 1991
Docket90SC355
StatusPublished
Cited by16 cases

This text of 817 P.2d 979 (Homestake Enterprises, Inc. v. Oliver) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Homestake Enterprises, Inc. v. Oliver, 817 P.2d 979, 15 Brief Times Rptr. 1321, 1991 Colo. LEXIS 622, 1991 WL 185337 (Colo. 1991).

Opinions

Chief Justice ROVIRA

delivered the Opinion of the Court.

This is a certiorari proceeding initiated by petitioner Homestake Enterprises, Inc. (Homestake), to review the court of appeals decision in Oliver v. Homestake Enterpris[980]*980es, 800 P.2d 1331 (Colo.App.1990). In Oliver, the court held that the two-year statute of limitations applicable to actions against contractors and builders, § 13-80-127, 6 C.R.S. (1984 Supp.),1 did not apply to the negligence action brought by respondent Margaret P. Oliver. We reverse.

I

In September 1984, Homestake entered into a construction subcontract with a general contractor not involved in this litigation to install a sprinkler system, landscape, and lay sod on property owned by Penrose Hospital of Colorado Springs.2 On November 15, 1984, prior to the completion of the subcontract work, Oliver suffered injuries when she slipped and fell on an icy sidewalk located on the property.

In February 1988, Oliver filed a negligence action against Homestake. Her complaint initially alleged that Homestake was liable to her because the injuries resulted from the negligent testing by Home-stake employees of the sprinkler system in freezing temperatures, which caused ice to form on the sidewalk.3 Oliver’s amended complaint withdrew her allegation of negligent testing and instead alleged that Homestake “negligently operated or caused the sprinkling system to be operated during freezing temperatures, which caused ice to form on the ... sidewalk where it knew, or should have known, that pedestrians such as the Plaintiff would be walking.”

The trial court granted Homestake’s motion for summary judgment on the ground that Oliver failed to file her action within the two-year limitations period for actions against contractors such as Homestake, see § 13-80-127, 6 C.R.S. (1984 Supp.).4 Relying on Irwin v. Elam Construction, 793 P.2d 609 (Colo.App.), cert. denied, No. 90SC171 (Colo. July 9, 1990), the court of appeals reversed the trial court’s ruling, reasoning that section 13-80-127 “applied only to negligence in planning, design, construction, supervision, or inspection that results in a defect in an improvement to real property that, in turn, causes injury to a claimant,” and Oliver had alleged only that Homestake employees were negligent and not that any of Homestake’s improvements to real property were “defective.” Oliver v. Homestake Enters., 800 P.2d 1331, 1331-32 (Colo.App.1990). Accordingly, it concluded that the six-year statute of limitations applied rather than the two years mandated by section 13-80-127.5 We granted certiorari to determine the scope of section 13-80-127.

II

The issue here is whether section 13-80-127, 6 C.R.S. (1984 Supp.), applies when a plaintiff alleges that a contractor negligently operated a sprinkler system but does not allege that the contractor caused a “defect” in an improvement to real property. Section 13-80-127 provides in part:

(l)(a) All actions against any architect, contractor, builder or builder vendor, engineer, or inspector performing or furnishing the design, planning, supervision, inspection, construction, or observation [981]*981of construction of any improvement to real property shall be brought within two years after the claim for relief arises, and not thereafter....
(b) A claim for relief arises under this section at the time the damaged party discovers or in the exercise of reasonable diligence should have discovered the defect in the improvement which ultimately causes the injury, when such defect is of a substantial or significant nature.
(c) Such actions shall include any and all actions in tort, contract, indemnity, or contribution or other actions for the recovery of damages for:
(I) Any deficiency in the design, planning, supervision, inspection, construction, or observation of construction of any improvement to real property; or
(III) Injury to or wrongful death of a person caused by any such deficiency.

Two divisions of the court of appeals have considered the issue presented in this case. In Irwin v. Elam Construction, 793 P.2d 609 (Colo.App.), cert. denied, No. 90SC171 (Colo. July 9, 1990), the plaintiffs brought a negligence action against a construction company alleging that physical damage to their home was the result of vibrations caused by the company’s use of heavy equipment on an adjacent road. Their complaint was filed more than three years after they moved out of their damaged house. The trial court granted the construction company’s motion for summary judgment on the ground that the action was barred by section 13-80-127’s two-year limitation of actions against contractors. Division II of the court of appeals reversed, holding that section 13-80-127 “was intended to apply only to negligence in planning, design, construction, supervision, or inspection that results in a defect in an improvement to real property that, in turn, causes injury to a claimant.” Id. at 611.

In Sharp Brothers Contracting Co. v. Westvaco Corp., 817 P.2d 547 (Colo.App. 1991),6 the plaintiffs contracted with the Denver Board of Water Commissioners to construct a water re-use demonstration plant. They entered into a subcontract with Westvaco to furnish and install a carbon regeneration system in a portion of the plant. Westvaco subcontracted with American Steel for the construction of two storage tanks. In turn, American Steel entered into an agreement with Carboline Company to supply a liner for the interior of the tanks. Subsequently, the water board rejected the storage-tank liners, and Westvaco contracted with another company to remove the liners. While the liners were being removed an explosion occurred, damaging the tanks and the demonstration plant. The plaintiffs brought a negligence action against Westvaco, alleging that Westvaco, acting through its subcontractors and agents, negligently handled the highly flammable material being used to remove the liners, thus causing damage to the demonstration plant. The trial court dismissed the action on the ground that it was filed beyond the two-year time limitation set forth in section 13-80-127.

Division IV of the court of appeals affirmed. The court stated that the statute’s applicability “is not limited only to claims resulting from a ‘defect in the improvement’; it also applies to ‘any and all actions’ that result from a ‘deficiency’ in the design or construction process, including such a deficiency in ‘supervision’ of those processes.” The court then held that “the resulting injury here was directly related to a deficiency in the construction of an improvement to the real property.” Id. at 551.

A

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Montgomery v. Engelhard
352 P.3d 218 (Court of Appeals of Washington, 2015)
Shaw Construction, LLC v. United Builder Services, Inc.
2012 COA 24 (Colorado Court of Appeals, 2012)
Smith v. Executive Custom Homes, Inc.
230 P.3d 1186 (Supreme Court of Colorado, 2010)
Smith v. Executive Custom Homes, Inc.
209 P.3d 1175 (Colorado Court of Appeals, 2009)
Hersh Companies v. Highline Village Associates
30 P.3d 221 (Supreme Court of Colorado, 2001)
Gleason v. Becker-Johnson Associates, Inc.
916 P.2d 662 (Colorado Court of Appeals, 1996)
People v. Thomas
867 P.2d 880 (Supreme Court of Colorado, 1994)
Maryland Casualty Co. v. Formwork Services, Inc.
812 F. Supp. 1127 (D. Colorado, 1993)
Homestake Enterprises, Inc. v. Oliver
817 P.2d 979 (Supreme Court of Colorado, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
817 P.2d 979, 15 Brief Times Rptr. 1321, 1991 Colo. LEXIS 622, 1991 WL 185337, Counsel Stack Legal Research, https://law.counselstack.com/opinion/homestake-enterprises-inc-v-oliver-colo-1991.