Sharp Bros. Contracting Co. v. Westvaco Corp.

817 P.2d 547, 15 Brief Times Rptr. 283, 1991 Colo. App. LEXIS 61, 1991 WL 33828
CourtColorado Court of Appeals
DecidedMarch 14, 1991
Docket89CA1969
StatusPublished
Cited by16 cases

This text of 817 P.2d 547 (Sharp Bros. Contracting Co. v. Westvaco Corp.) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sharp Bros. Contracting Co. v. Westvaco Corp., 817 P.2d 547, 15 Brief Times Rptr. 283, 1991 Colo. App. LEXIS 61, 1991 WL 33828 (Colo. Ct. App. 1991).

Opinion

Opinion by

Judge MARQUEZ.

Plaintiffs, Sharp Bros. Contracting Co. and Sanders Company, Inc., a joint venture, appeal from a judgment of the trial court dismissing all but one claim against defendant Westvaco Corporation, and all claims against defendants American Steel and Iron Works, Inc., and American Painting and Sandblasting, Inc. We affirm in part, reverse in part, and remand for further proceedings.

In late 1980, plaintiffs’ joint venture entered an agreement, as the general contractor, with the Denver Board of Water Commissioners, to construct a potable water reuse demonstration plant. In February 1981, plaintiffs entered into a subcontract with Westvaco Corporation to furnish and install a carbon regeneration system in a portion of the demonstration plant.

*549 Westvaco subsequently subcontracted with American Steel for the construction and installation of two carbon storage tanks. Thereafter, American Steel entered into an agreement with Carboline Company, Inc., to supply a product to be used as a liner to the interior of the carbon storage tanks.

Some time thereafter, the Board of Water Commissioners rejected the application of Carboline’s product and required that the liner be removed and reapplied. The removal and reapplication of the linings was subcontracted to American Painting.

On March 21, 1983, an explosion and fire occurred at one of the carbon storage tanks where the tank lining was being removed with a highly flammable substance. The record reflects that this fire caused damage to the tank and surrounding areas of the demonstration plant.

On March 15, 1984, plaintiffs sued West-vaco in the United States District Court for the Western District of Missouri for damages they suffered as a result of the March 1983 fire. The case was transferred to the United States District Court of Colorado. Plaintiffs added claims against American Steel, American Painting, and Carboline in September 1986. However, all claims were subsequently dismissed, without prejudice, on June 10, 1987, because of the lack of subject matter jurisdiction.

On July 20, 1987, plaintiffs refiled their complaint in the United States District Court for the District of Colorado against Westvaco, American Steel, and American Painting, but did not join Carboline as a defendant. The court dismissed that action without prejudice, on August 31, 1987, for lack of jurisdiction.

On September 4, 1987, plaintiffs then filed the action, which is the subject of this appeal, in Denver District Court, alleging breach of certain contracts, misrepresentation, and negligence against Westvaco, and negligence against American Steel, American Painting, and Carboline. The court dismissed the claim against Carboline as barred by the three-year statute of limitations relating to manufacturers and sellers of products, Colo.Sess.Laws 1977, ch. 199, § 13-80-127.5, at 819. The court also dismissed the claims against American Steel and American Painting as being barred by the two-year statute of limitations then in effect, Colo.Sess.Laws 1979, ch. 144, § 13-80-127, at 631 (now codified with amendments at § 13-80-104, C.R.S. (1987 Repl. Vol. 6A)). In connection with that ruling, the court held that such claims did not relate back to the date that other parties asserted claims against these defendants. Furthermore, the court dismissed all claims against Westvaco, except an oral contract claim, as barred by § 13-80-127, and not revived by the remedial revival statute, § 13-80-111, C.R.S. (1987 Repl.Vol. 6A).

Upon motion of the plaintiffs, the court subsequently directed that its order be made a final judgment and stayed the remaining claim pending appeal. The ruling dismissing Carboline is not being appealed.

I.

Plaintiffs first argue that their claims against Westvaco, American Steel, and American Painting are not governed by § 13-80-127 because they do not arise out of a defect in an improvement to real property. They assert that the fire was not caused by a defect, but, instead, was caused by the negligent conduct of defendants. They contend, therefore, that the claims were governed by the general six-year statute of limitations in effect at the times pertinent here and that they were brought within that statutory period.

Although the applicability of the six-year statute is raised for the first time on appeal, since Oliver v. Homestake Enterprises, Inc., 800 P.2d 1331 (Colo.App.1990) (certiorari granted December 10, 1990) and Irwin v. Elam Construction, Inc., 793 P.2d 609 (Colo.App.1990) were decided after this appeal was filed, we will address it here.

We conclude that § 13-80-127 applies to plaintiffs claims.

Section 13-80-127(1) provides:

“(a) All actions against any architect, contractor, builder or builder vendor, engineer, or inspector performing or furnishing the design, planning, supervision, *550 inspection, construction, or observation of construction of any improvement to real property shall be brought within two years after the claim for relief arises, and not thereafter, but in no case shall an action be brought more than ten years after the substantial completion of the improvement to the real property, except as provided in subsection (2) of this section.
(b) A claim for relief arises under this section at the time the damaged party discovers or in the exercise of reasonable diligence should have discovered the defect in the improvement which ultimately causes the injury, when such defect is of a substantial or significant nature.
(c) Such actions shall include any and all actions in tort, contract, indemnity, or contribution or other actions for the recovery of damages for:
(I) Any deficiency in the design, planning, supervision, inspection, construction, or observation of construction of any improvement to real property; or
(II) Injury to real or personal property caused by such deficiency; or
(III) Injury to or wrongful death of a person caused by any such deficiency.”

A court’s primary task in statutory construction is to ascertain and give effect to the legislative purpose underlying a statutory enactment. In ascertaining the legislative purpose, we look first to the statutory language employed by the General Assembly and give words their commonly accepted and understood meaning. When the statutory language is clear and unambiguous, there is no need to resort to interpretative rules of statutory construction. Woodsmall v. Regional Transportation District, 800 P.2d 63 (Colo.1990). Interpretation of statutes is a question of law and appellate courts need not defer to the trial court’s interpretation. People v. Terry, 791 P.2d 374 (Colo.1990).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

West Colo. Motors v. General Motors
2019 COA 77 (Colorado Court of Appeals, 2019)
Veatch v. Bartels Lutheran Home
804 N.W.2d 530 (Court of Appeals of Iowa, 2011)
A.C. Excavating v. Yacht Club II Homeowners Ass'n
114 P.3d 862 (Supreme Court of Colorado, 2005)
SMLL, L.L.C. v. Peak National Bank
111 P.3d 563 (Colorado Court of Appeals, 2005)
Highline Village Associates v. Hersh Companies
996 P.2d 250 (Colorado Court of Appeals, 2000)
Hebertson v. Bank One, Utah, N.A.
1999 UT App 342 (Court of Appeals of Utah, 1999)
Two Denver Highlands Ltd. Partnership v. Dillingham Construction N.A.
932 P.2d 827 (Colorado Court of Appeals, 1996)
Gleason v. Becker-Johnson Associates, Inc.
916 P.2d 662 (Colorado Court of Appeals, 1996)
People v. Easter
914 P.2d 493 (Colorado Court of Appeals, 1995)
Sharp Bros. Contracting Co. v. Westvaco Corp.
878 P.2d 38 (Colorado Court of Appeals, 1994)
Homestake Enterprises, Inc. v. Oliver
817 P.2d 979 (Supreme Court of Colorado, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
817 P.2d 547, 15 Brief Times Rptr. 283, 1991 Colo. App. LEXIS 61, 1991 WL 33828, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sharp-bros-contracting-co-v-westvaco-corp-coloctapp-1991.