Sharp Bros. Contracting Co. v. Westvaco Corp.

878 P.2d 38, 18 Brief Times Rptr. 119, 1994 Colo. App. LEXIS 9, 1994 WL 8667
CourtColorado Court of Appeals
DecidedJanuary 13, 1994
Docket92CA1772
StatusPublished
Cited by10 cases

This text of 878 P.2d 38 (Sharp Bros. Contracting Co. v. Westvaco Corp.) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sharp Bros. Contracting Co. v. Westvaco Corp., 878 P.2d 38, 18 Brief Times Rptr. 119, 1994 Colo. App. LEXIS 9, 1994 WL 8667 (Colo. Ct. App. 1994).

Opinion

Opinion by

Judge HUME.

Defendant, Westvaco Corporation, appeals from a judgment entered upon a jury verdict awarding damages for breach of a construction contract with plaintiff, Sharp Bros. Contracting Company and Sanders Company, Inc., a joint venture. Defendant also appeals the trial court’s orders dismissing its third-party claims against defendants American Steel and Iron Works, Inc. (American Steel), Carboline Company (Carboline), and American Painting and Sandblasting, Inc. (Ameri *42 can Painting). Plaintiff cross-appeals the trial court’s order denying its motion for hearing on a request for attorney fees. We affirm the judgment and orders entered by the trial court.

In late 1980, plaintiff contracted with the City and County of Denver to serve as general contractor in the construction of a potable water reuse demonstration plant for the City. Plaintiff subcontracted with defendant to furnish and install a carbon regeneration system for the plant. The subcontract agreement expressly provided that Missouri law was to govern its interpretation.

Defendant entered a sub-subcontract with American Steel for construction and installation of two carbon storage tanks required by the regeneration system. American Steel, in turn, contracted with Carboline to provide liners for the tanks and with American Painting for installing the tanks on the site.

The tank liners were rejected after delivery to the site, because they did not meet contract specifications. While American Painting was using a highly flammable chemical to remove defective tank linings, a fire and explosion occurred, damaging the tank and surrounding areas of the plant and delaying completion of the project.

Plaintiff first sued defendant in the U.S. District Court in Missouri for negligence, indemnity, and contract damages suffered as a result of the fire. Defendant timely asserted third-party claims against American Steel, American Painting, and Carboline (the sub-subcontractors) for contribution and indemnity. The action was transferred to the U.S. District Court in Colorado. Thereafter plaintiff added direct claims against the sub-subcontractors, which resulted in the dismissal of the action without prejudice for lack of subject matter jurisdiction because plaintiff and Carboline were citizens of the same state. Plaintiff attempted to save the action by moving to dismiss its claims against Carboline, but the court concluded that Car-boline was an indispensable party and denied the motion.

Plaintiff then refiled its complaint in federal court without asserting a claim against Carboline so that the action would meet diversity requirements. However, the U.S. District Court again dismissed the action without prejudice because it deemed Carbo-line to be an indispensable party to the action.

Plaintiff then commenced this action asserting claims against defendant and the sub-subcontractors in the trial court. The action was filed more than four years after the fire and six days before the expiration of the period permitted under the Colorado remedial revival statute, § 13-80-111, C.R.S. (1987 Repl.Vol. 6A). Plaintiffs complaint was served on all defendants approximately five weeks after that period expired. Shortly after being served with this complaint, defendant filed cross-claims against each of the three sub-subcontractors.

The court dismissed all but one of plaintiffs claims against defendant and both plaintiffs and defendant’s claims against the sub-subcontractors because the statute of limitations had expired.

On appeal, a division of this court upheld the dismissal of plaintiffs claims against the sub-subcontractors but concluded that plaintiff had timely filed its claims against defendant within the period provided by the remedial revival statute. Sharp Bros. Contracting Co. v. Westvaco Corp., 817 P.2d 547 (Colo.App.1991).

In a related appeal decided the same date, that division also affirmed the trial court’s summary judgment dismissing as time barred defendant’s third-party claims against the sub-subcontractors. Westvaco Corp. v. American Steel & Iron Works, Inc., (Colo.App. No. 89CA1440, March 14, 1991) (not selected for official publication).

On remand, defendant sought to re-institute as third-party claims the cross-claims it had previously asserted against the sub-subcontractors. However, the trial court dismissed the third-party claims as barred by the doctrines of res judicata, law of the case, and the statute of limitations. The matter was ultimately tried solely upon plaintiffs claim for defendant’s breach of performance under the parties’ contract and its indemnity provision and defendant’s counterclaim for *43 moneys allegedly owed to it under the contract.

The jury found in favor of plaintiff on both the claim and counterclaim. The trial court added prejudgment interest to the jury’s damage award and entered judgment accordingly.

I.

Defendant first contends that the federal court’s determination that Carboline was an indispensable party is res jtidicata and that, therefore, the state court did not have jurisdiction to proceed in this action. We disagree.

The doctrine of res judicata encompasses both claim preclusion, which is true res judicata, and issue preclusion, more commonly called collateral estoppel.

Res judicata bars a second action on a claim previously litigated if there is a final judgment and identity of subject matter, claims for relief, and parties to the action. Collateral estoppel bars relitigation of an issue if it is identical to an issue actually and necessarily adjudicated at a prior proceeding; if the party against whom estoppel is asserted was a party or is in privity with a party in the prior proceeding; if there was a final judgment; and if the party against whom estoppel is asserted had a full and fair opportunity to litigate the issue in the prior proceeding. Denver v. Block 173 Associates, 814 P.2d 824 (Colo.1991).

A judgment based on procedural rather than substantive grounds is not a final judgment on the merits and does not give rise to application of the doctrine of res judicata or collateral estoppel. See Platte River Drive Joint Venture v. Vasquez, 860 P.2d 599 (Colo.App.1993). Further, dismissal without prejudice for lack of jurisdiction is not an adjudication on the merits. Dash v. Rubey, 144 Colo. 481, 357 P.2d 81 (1960).

Here, the federal court twice dismissed the actions without prejudice for lack of jurisdiction based upon a finding that Car-boline was an indispensable party whose join-der destroyed diversity of citizenship. The federal court’s determination of subject matter jurisdiction was not an adjudication on the merits.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chrisco v. Gibson
D. Colorado, 2019
In Re Estate of Murphy
195 P.3d 1147 (Colorado Court of Appeals, 2008)
Grynberg v. Phillips
148 P.3d 446 (Colorado Court of Appeals, 2006)
FSDW, LLC v. First National Bank
94 P.3d 1256 (Colorado Court of Appeals, 2004)
FSDW, LLC v. First Nat. Bank
94 P.3d 1260 (Colorado Court of Appeals, 2004)
In Re the Marriage of Mallon
956 P.2d 642 (Colorado Court of Appeals, 1998)
Shell Western E&P, Inc. v. Dolores County Board of Commissioners
948 P.2d 1002 (Supreme Court of Colorado, 1997)
Aztec Minerals Corp. v. Romer
940 P.2d 1025 (Colorado Court of Appeals, 1996)
Brooks v. Bank of Boulder
891 F. Supp. 1469 (D. Colorado, 1995)
Amoco Rocmount Co. v. Anschutz Corp.
873 F. Supp. 1492 (D. Wyoming, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
878 P.2d 38, 18 Brief Times Rptr. 119, 1994 Colo. App. LEXIS 9, 1994 WL 8667, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sharp-bros-contracting-co-v-westvaco-corp-coloctapp-1994.