Maryland Casualty Co. v. Formwork Services, Inc.

812 F. Supp. 1127, 1993 U.S. Dist. LEXIS 1738, 1993 WL 36157
CourtDistrict Court, D. Colorado
DecidedFebruary 10, 1993
DocketCiv. A. 91-K-762
StatusPublished
Cited by4 cases

This text of 812 F. Supp. 1127 (Maryland Casualty Co. v. Formwork Services, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maryland Casualty Co. v. Formwork Services, Inc., 812 F. Supp. 1127, 1993 U.S. Dist. LEXIS 1738, 1993 WL 36157 (D. Colo. 1993).

Opinion

MEMORANDUM OPINION AND ORDER

KANE, Senior District Judge.

In this diversity action, Plaintiff Maryland Casualty Company seeks indemnification from Defendant Formwork Services, Inc. under a construction contract. Maryland Casualty’s claim arises from damages it paid to Regina Dominguez after the death of her husband on a construction site. Formwork moves for summary judgment, asserting that Maryland Casualty may not sue on the contract because its subrogor, Ronald L. Moore Construction Company, was not a third-party beneficiary of the contract. In addition, it argues that Maryland Casualty’s indemnification claim is barred by the statute of limitations. Both arguments have merit.

I. Facts.

On November 16, 1984, James Dominguez stepped on to unsupported plywood sheathing in the newly constructed shell of the Fort Collins Holiday Inn, the sheathing collapsed, and he fell to his death. Dominguez was an employee of Formwork, a subcontractor on the project. The general contractor and owner of the project was John Q. Hammons Industries (“Ham-mons”). The Ronald L. Moore Construction Company (“Moore”) was project manager. Maryland Casualty was Moore’s liability insurer.

On August 22, 1985, Dominguez’ widow, on behalf of herself and her children, commenced a wrongful death action in state court seeking damages from Moore (“the Dominguez action”). On April 19, 1990, the jury returned a verdict in favor of Mrs. Dominguez, awarding damages of $690,-706. She consented to a reduction of the award to $450,000 in consideration for Moore’s agreement not to appeal the decision. Maryland Casualty then paid Mrs. Dominguez this reduced amount under Moore’s liability policy.

On May 7, 1991, Maryland Casualty brought this action to recover the $450,000 it paid to Mrs. Dominguez on behalf of Moore. The company alleges that it is entitled to reimbursement of this amount from Formwork under an indemnity provision in Formwork’s contract with Ham-mons (“the Subcontract”). That provision, Article 11,11.1 of the AIA Standard Form of Agreement Between Contractor and Subcontractor, states:

To the fullest extent permitted by law, the Subcontractor shall indemnify and hold harmless the Owner, the Architect and the Contractor and all of their agents and employees from and against all claims, damages, losses and expenses, including but not limited to attorney’s fees, arising out of or resulting from the performance of the Subcontractor’s Work under this Subcontract,....

(Mem.Br.Supp.Def.’s Mot.Summ.J., Attach. B at 6 [hereinafter, Subcontract].) Maryland Casualty claims that Moore, as project manager, is a third-party beneficiary of the Subcontract and that it is entitled to reimbursement as Moore’s subrogee.

Formwork now moves for summary judgment, asserting that since Moore is not the owner, architect or contractor as defined in the Subcontract, the indemnification clause is not applicable. Furthermore, Formwork contends that Maryland Casualty’s indemnification claim is barred by Colo.Rev.Stat. § 13-80-104 (1987), Colorado’s statute of limitations for actions *1129 against architects, contractors and builders.

II. Merits.

A. Moore’s Status as a Third Party Beneficiary of the Subcontract.

Formwork's first argument is that Moore, and Maryland Casualty as Moore’s subrogee, are not entitled to indemnification under the Subcontract. Article 11.11.1 of the Subcontract limits indemnification to the “Owner, the Architect and the Contractor and all of their agents and employees.” (Subcontract at 6.) Formwork notes that Maryland Casualty admitted in its complaint that Moore was neither the owner nor the general contractor and has never claimed that Moore was the architect or an employee. Thus, Formwork reasons, Maryland Casualty’s claim must be premised on Moore’s status as an agent of Ham-mons, the owner and general contractor. Formwork contends, however, that Maryland Casualty is collaterally estopped from asserting that Moore was Hammons' agent. That issue was conclusively resolved against Moore in the Dominguez action, where the jury ruled that Moore was not an agent of Hammons for the purposes of statutory immunity under Colorado's workmen’s compensation law. (See Mem.Br.Supp.Def.’s Mot.Summ.J., Attach. 0).

In response, Maryland Casualty does not focus on Formwork’s argument that Moore cannot be considered Hammons’ agent. 1 Instead, it seeks reimbursement under the indemnification clause by casting Moore as the “Contractor.” Maryland Casualty maintains that whether Moore can be considered the “Contractor” under the Subcontract is a disputed issue of material fact. It relies on an entirely separate agreement, the agreement between Moore and Ham-mons establishing Moore’s duties as project manager. In that agreement, Moore is referred to as the “Contractor.” (See Pl.’s Mem.Opp’n Def.’s Mot.Summ.J., Ex. A.) Maryland Casualty’s attempt to create a genuine issue of material fact by reference to this separate agreement is unavailing.

While the intent of parties to a contract may be determined by reference to separate ancillary instruments, see Powder Horn Constructors, Inc. v. City of Florence, 754 P.2d 356, 365 (Colo.1988), this is not the rule when the contract itself is fully integrated and the contract term to be construed is unambiguous. See Restatement (Second) of Contracts § 215 (1981) (“where there is a binding agreement, either completely or partially integrated, evidence of prior or contemporaneous agreements or negotiations is not admissible to contradict the term of the writing.”) Reference to a separate writing is even less appropriate where the writing has not been executed contemporaneously or where the parties to the two agreements differ. See generally 17A C.J.S. Contracts § 298 (1963); 4 Samuel Williston, A Treatise on the Law of Contracts § 628 (3d ed. 1961) (writings not between the same parties or not known to both of them are “irrelevant to aid in interpretation of one another”). Whether a contract is fully integrated is a determination the court must make before deciding a question of contract interpretation. Restatement, supra, § 209(2).

Here, the first paragraph of Subcontract defines who each party is. Hammons is shown as both the Contractor and the Owner, Hood-Rich Architects is the Architect, and Formwork Services is the Subcontractor. Moore is not identified or referenced in the text of the Subcontract or its addenda. Furthermore, the Subcontract contains an integration clause, which provides that “the Contract Documents, which constitute the entire Agreement between the Owner and the Contractor, are listed in Article 1, and the documents which are applicable to this Subcontract, except for Addenda and Modifications issued after ex *1130 ecution of the Subcontract, are enumerated [below].” 2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
812 F. Supp. 1127, 1993 U.S. Dist. LEXIS 1738, 1993 WL 36157, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maryland-casualty-co-v-formwork-services-inc-cod-1993.