Hocking v. City of Dodgeville

2010 WI 59, 785 N.W.2d 398, 326 Wis. 2d 155, 72 U.C.C. Rep. Serv. 2d (West) 400, 2010 Wisc. LEXIS 52, 2010 WL 2633862
CourtWisconsin Supreme Court
DecidedJuly 2, 2010
Docket2008AP2812
StatusPublished
Cited by23 cases

This text of 2010 WI 59 (Hocking v. City of Dodgeville) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hocking v. City of Dodgeville, 2010 WI 59, 785 N.W.2d 398, 326 Wis. 2d 155, 72 U.C.C. Rep. Serv. 2d (West) 400, 2010 Wisc. LEXIS 52, 2010 WL 2633862 (Wis. 2010).

Opinion

*161 MICHAEL J. GABLEMAN, J.

¶ 1. This case comes before us on review of a published decision of the court of appeals 1 affirming the circuit court's order of summary judgment in favor of the City of Dodgeville in a lawsuit against it by Glen and Louann Hocking ("Hockings") for damage to their property. The Hockings claimed that the City was negligent in the design, plotting, approval, and development of a subdivision adjacent to their property and that negligence caused significant water damage to their property. The City asserted that the suit was barred under Wis. Stat. § 893.89 (2007-08), 2 which imposes a ten-year statute of repose on actions for injury resulting from improvements to real property. Both the circuit court and court of appeals agreed with the City that the statute of repose applied.

¶ 2. The specific issue before us is whether either of two exceptions contained in § 893.89 apply and therefore allow the Hockings' suit to proceed. 3 First, the Hockings allege that the City expressly warranted or guaranteed the improvement to real property under § 893.89(4)(b). The Hockings also assert that the City was negligent in the maintenance, operation, or inspection of the improvement to real property under § 893.89(4)(c). If either of these two exceptions applies, the ten-year statute of repose would not bar the Hockings' suit.

*162 ¶ 3. We conclude that neither § 893.89(4)(b) nor § 893.89(4)(c) applies, and the Hockings' suit is therefore barred by the ten-year statute of repose in Wis. Stat. § 893.89. Section 893.89(4)(b) does not apply because the Hockings have not shown that the City of Dodgeville itself made any express warranty or guarantee regarding the improvements. Section 893.89(4)(c) does not apply because the City has not been negligent in maintaining, operating, or inspecting the improvements. Accordingly, we affirm the court of appeals and hold that the circuit court properly granted summary judgment for the City, thereby dismissing the Hockings' suit.

I. BACKGROUND

¶ 4. The following facts are undisputed for the purposes of this appeal.

¶ 5. In 1978, Glen and Louann Hocking purchased a home situated on a small parcel of land at 216 Swayne Street in Dodgeville, Wisconsin. At the time of purchase, the nearest residence to the Hocking property was a farm house 200 or 300 feet away.

¶ 6. In 1989, Wallace Rogers purchased property adjacent to the Hockings' land, which at the time was largely undeveloped and covered with trees. Rogers planned to develop the property into a subdivision with multiple lots. In order to complete this project, he hired professional engineer Lawrence E. Schmit to design the subdivision. The City of Dodgeville also contracted with Schmit to design and install streets and sewers; this involved laying out the roadways, curbs, and street gutters for the proposed development. 4 Rogers named the completed development the "Lorraine Subdivision."

*163 ¶ 7. The terrain of the proposed subdivision was uneven, and Schmit had to bring in large amounts of landfill to level the land and build up the places where the homes would sit. This landscaping created a steep slope that ran downhill to the Hockings' property.

¶ 8. Prior to the development of the subdivision, Glen Hocking spoke with Corny James, a member of the City of Dodgeville Common Council. Hocking informed James that he was concerned about the steep gradation that he anticipated would result from building the subdivision. Despite the Hockings' concerns, the City approved the plans for the development on July 16, 1991. Throughout the construction of the Lorraine Subdivision, Mr. Hocking continued to informally speak with the city engineer and various common council members who assured him that if a problem arose, it would be addressed by the City.

¶ 9. On September 12, 1992, the Lorraine subdivision was completed, and the owners of the individual lots were allowed to occupy their property. Schmit's final contact with the subdivision was on June 3, 1993, when the final coat of blacktop was laid over the asphalt on Roelli Lane, one of the subdivision's main streets.

¶ 10. The Lorraine Subdivision significantly impacted the physical condition of the Hockings' property. Before its development, the Hockings experienced no flooding problems in their yard or basement. But around 1992 or 1993, they began to notice water in their yard, and over time storm water run-off began to collect both inside and outside the Hockings' residence, causing damage to their home and erosion of their land. They had to install a sump pump in order to capture the *164 water, but even that only partially mitigated the problem. In 1995, the Blockings' basement completely flooded. Moreover, water damage throughout the 1990's caused mold to develop inside their home.

¶ 11. From the early-1990's until 2003, Mr. Hocking frequently spoke with elected officials and employees of the City (collectively "city officials") who continued to assure him the problem would be resolved. Several city officials, including members of the common council, even visited the Hockings' home to inspect the damage. The council members assured the Hockings that the problem would be addressed. At one point, the City considered installing a drainage system or a moat, either of which Mr. Hocking readily approved, but no action was taken to follow through on installing either. At some point in 2003 the city engineer 5 and the city assessor advised Mr. Hocking that the City could not resolve the flooding issue.

¶ 12. The Hockings brought this action against the City, Rogers, and Schmit on August 22, 2006, in the Circuit Court for Iowa County, Edward E. Leineweber, Judge. The Hockings asserted claims of negligence, and negligent and intentional creation and maintenance of a nuisance.

¶ 13. The three defendants moved for summary judgment on the ground that Wis. Stat. § 893.89 bars this action because it was filed more than ten years after the substantial completion of the subdivision. The Hockings argued that they received express guarantees from the City that it would resolve the situation, and therefore, pursuant to § 893.89(4)(b), the statutory bar *165 did not apply. They also contended that the suit could move forward pursuant to § 893.89(4) (c) because the City owned and controlled the subdivision streets and was negligent in maintaining a nuisance.

¶ 14. The circuit court rejected the Hockings' arguments and concluded that the statutory bar did apply. With respect to Wis. Stat.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

William B. Larimore v. Midland Plastics Inc.
Court of Appeals of Wisconsin, 2025
Jalal Kareem Khoury v. American Honda Motor Co. Inc.
Court of Appeals of Wisconsin, 2025
Soletski v. Krueger Int'l, Inc.
2019 WI App 7 (Court of Appeals of Wisconsin, 2019)
Peter v. Sprinkmann Sons Corp.
2015 WI App 17 (Court of Appeals of Wisconsin, 2015)
Schuetta v. Aurora National Life Assurance Co.
30 F. Supp. 3d 800 (E.D. Wisconsin, 2014)
Crisanto v. Heritage Relocation Services, Inc.
2014 WI App 75 (Court of Appeals of Wisconsin, 2014)
Bostco LLC v. Milwaukee Metropolitan Sewerage District
2013 WI 78 (Wisconsin Supreme Court, 2013)
Patricia Mudlaff v. Joseph McLeod
2013 WI 76 (Wisconsin Supreme Court, 2013)
State v. Gilbert
2012 WI 72 (Wisconsin Supreme Court, 2012)
Fond du Lac County v. Helen E. F.
2012 WI 50 (Wisconsin Supreme Court, 2012)
Crown Castle USA, Inc. v. Orion Construction Group, LLC
2012 WI 29 (Wisconsin Supreme Court, 2012)
Covenant Healthcare System, Inc. v. City of Wauwatosa
2011 WI 80 (Wisconsin Supreme Court, 2011)
E-Z Roll Off, LLC v. County of Oneida
2011 WI 71 (Wisconsin Supreme Court, 2011)
Kilian v. Mercedes-Benz USA, LLC
2011 WI 65 (Wisconsin Supreme Court, 2011)
Harborview Office Center, LLC v. Nash
2011 WI App 109 (Court of Appeals of Wisconsin, 2011)
Bostco LLC v. Milwaukee Metropolitan Sewerage District
2011 WI App 76 (Court of Appeals of Wisconsin, 2011)
Cianciola LLP v. Milwaukee Metropolitan Sewerage District
2011 WI App 35 (Court of Appeals of Wisconsin, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
2010 WI 59, 785 N.W.2d 398, 326 Wis. 2d 155, 72 U.C.C. Rep. Serv. 2d (West) 400, 2010 Wisc. LEXIS 52, 2010 WL 2633862, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hocking-v-city-of-dodgeville-wis-2010.