Cianciola LLP v. Milwaukee Metropolitan Sewerage District

2011 WI App 35, 796 N.W.2d 806, 331 Wis. 2d 740, 2011 Wisc. App. LEXIS 97
CourtCourt of Appeals of Wisconsin
DecidedFebruary 1, 2011
DocketNo. 2010AP87
StatusPublished
Cited by5 cases

This text of 2011 WI App 35 (Cianciola LLP v. Milwaukee Metropolitan Sewerage District) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cianciola LLP v. Milwaukee Metropolitan Sewerage District, 2011 WI App 35, 796 N.W.2d 806, 331 Wis. 2d 740, 2011 Wisc. App. LEXIS 97 (Wis. Ct. App. 2011).

Opinion

KESSLER, J.

¶ 1. The Milwaukee Metropolitan Sewerage District ("MMSD") appeals from a judgment awarding damages to Cianciola, LLP ("Cianciola") caused by the operation and maintenance of a deep tunnel that runs under Cianciola's property. MMSD also appeals from an order of the trial court denying its motion for reconsideration. We affirm.1

[743]*743BACKGROUND

¶ 2. Cianciola, created on June 5, 1996, by Frank and Shirley Cianciola, is a limited liability partnership. Cianciola has owned the land and property located at 107 E. Lincoln Ave., Milwaukee, Wisconsin ("Lincoln property"), since 1996, when it acquired the land, along with all of the rights and benefits that run with the land, from Pre-Pac Produce Distributors, Inc. ("Pre-Pac"). Pre-Pac was owned by one or more members of the Cianciola family and is Cianciola's tenant. Frank was identified as the managing partner of Cianciola, a position he held until his death in 2000. His son, Thomas Cianciola, is the current managing partner of Cianciola and the president of Pre-Pac.

¶ 3. Although Cianciola was formed in 1996, Frank2 had owned the Lincoln property for approximately three decades prior to Cianciola's formation. Frank was approached by MMSD in 1988 to negotiate an easement to install a tunnel underneath the Lincoln property.3 The parties executed an easement agreement on June 2, 1988. As a part of the agreement, MMSD covenanted to:

[744]*744[CJonstruct and maintain said intercepting sewer in good order and condition and that, in and during the construction of said intercepting sewer and thereafter in and about its operation, maintenance, repair or reconstruction, will indemnify and save harmless the party of first part, its successors and assigns, from all loss or injury to its property and persons due to such construction, operation, maintenance, repair or reconstruction.

Cianciola is a successor to the grantor of the easement.

¶ 4. Following the creation and execution of the easement, in 1989, MMSD began construction of the tunnel system. MMSD's construction led to soil compression under the Lincoln property and to a differential settlement of the property. Specifically, the trial court found:

MMSD's mining activities caused greater than expected inflows of ground water into the construction site which in turn caused soil compression. While this initial groundwater was pumped from the work site, the drop shaft and work chamber were flooded to stabilize the groundwater levels, and recharge wells were installed, the soil compression caused by the initial flooding led to differential settlement of [the Lincoln property] and caused damage to [the Lincoln property.]

¶ 5. Frank contacted MMSD in June 1991 to complain that the tunnel construction had adversely affected his building. MMSD engineer Steven Hunt met with Frank on June 20,1991 and on June 25,1991, and directed MMSD crews to establish a network of surveying pins and crack monitors around the Lincoln property. Based upon the data collected from the surveying tools, MMSD's consulting engineers recommended that MMSD pay Frank for any damage to the building that [745]*745had been caused by the construction. Consulting engineers advised Frank to retain an engineer, at MMSD's expense, to repair the damages. Frank retained MSI General Corporation and the repair work was completed in late 1993. MMSD paid Frank a total of $63,641.93 for the engineering costs, with $18,224.00 constituting a final payment by MMSD to Frank, made pursuant to a release signed by Frank. At the time of the payments, Frank was assured by Hunt that the settlements would not worsen.

¶ 6. Although Frank was told that his building would no longer settle, in 1992 a consultant suggested to MMSD that because of continuing damage that the property across the street from the Lincoln property was incurring, MMSD should completely line the tunnel in the area of the Lincoln property. MMSD declined to follow this suggestion. As a result, the Lincoln property still continues to settle.

¶ 7. Cianciola commenced this action on June 4, 2007 for damages resulting from MMSD's breach of contract, pursuant to the easement, for failure to maintain the tunnel in good order and condition and for MMSD's failure to indemnify Cianciola.4 During a bench trial, Cianciola called Richard Stehly, an engineer with American Engineering Testing, to testify as to the cause of the damages to the Lincoln property as well as to the necessary repairs. Stehly testified that considerable leakage continues to occur in the Deep Tunnel, and that at the time of the tunnel's construction, small flows in the area of the property resulted in unexpectedly large changes in water elevation. Stehly also testified [746]*746that if MMSD had raised the water levels up to preconstruction levels in 1993, there would have been some settlement, but not enough to cause a need for major repair. The trial court found Stehly's testimony credible.

¶ 8. The trial court also found that the daily water inflow into the Deep Tunnel System is approximately 2.8 million gallons. Approximately 4,320 gallons of water enter the tunnel per day from Cianciola's property.

¶ 9. Cianciola also called Steve Jaques, an expert in deep foundation construction, and Lavern Nall, a structural engineer consultant, to testify as to the damages and necessary repairs to the Lincoln property. Both witnesses indicated that major structural repairs to the property are necessary. Based on the testimony of expert witnesses, the trial court found that repairs to the foundation of the Lincoln property would cost approximately $443,670 and repairs made necessary as a result of continuing settlement would cost $592,644. The total amount of damages awarded by the trial court was $1,083,282.74.

¶ 10. Following the bench trial, the trial court issued written findings of fact and conclusions of law. MMSD filed a motion for reconsideration with the trial court, which was denied. MMSD now appeals.

DISCUSSION

¶ 11. MMSD bases its appeal on three grounds: (1) Cianciola's claims are barred by the statute of repose; (2) Cianciola's claims are barred by the statute of limitations; and (3) the trial court erroneously exercised its discretion in its award of damages. We address each argument in turn.

[747]*747I. Standard of Review.

¶ 12. Following a bench trial, "[flindings of fact shall not be set aside unless clearly erroneous, and due regard shall be given to the opportunity of the trial court to judge the credibility of the witnesses." Wis. Stat. § 805.17(2). We will therefore not upset a trial court's findings of fact unless they are clearly erroneous, nor will we reweigh evidence or assess witness credibility. Dickman v. Vollmer, 2007 WI App 141, ¶ 14, 303 Wis. 2d 241, 736 N.W.2d 202. "Findings of fact made by the trial court with regard to damages will not be upset by us unless clearly erroneous." Three & One Co. v. Geilfuss, 178 Wis. 2d 400, 410, 504 N.W.2d 393 (Ct. App. 1993).

II. The Statute of Repose.

¶ 13.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Edward J. Ritger v. Estate of Douglas P. Dahm
Court of Appeals of Wisconsin, 2020
Daniel J. Frank v. Randy Yajcharthao
Court of Appeals of Wisconsin, 2020
John M. Schuepbach v. Leistikow Properties, LLC
Court of Appeals of Wisconsin, 2020
Jay Link v. John Link
Court of Appeals of Wisconsin, 2019
Laughland v. Beckett
2015 WI App 70 (Court of Appeals of Wisconsin, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
2011 WI App 35, 796 N.W.2d 806, 331 Wis. 2d 740, 2011 Wisc. App. LEXIS 97, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cianciola-llp-v-milwaukee-metropolitan-sewerage-district-wisctapp-2011.