Frantl Industries, Inc. v. Maier Construction, Inc.

229 N.W.2d 610, 68 Wis. 2d 590, 1975 Wisc. LEXIS 1619
CourtWisconsin Supreme Court
DecidedJune 3, 1975
Docket399
StatusPublished
Cited by8 cases

This text of 229 N.W.2d 610 (Frantl Industries, Inc. v. Maier Construction, Inc.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Frantl Industries, Inc. v. Maier Construction, Inc., 229 N.W.2d 610, 68 Wis. 2d 590, 1975 Wisc. LEXIS 1619 (Wis. 1975).

Opinion

Heffernan, J.

On December 28, 1971, Frantl Industries, Inc., entered into a contract with Maier Construction, Inc., to perform work and furnish materials for the interior of a steam-heated drying kiln at a plant of the American Concrete Pipe Company. After the work was completed, the paint used bubbled off and it was necessary for Maier to recontract to have the work done by another. Nevertheless, on May 10, 1972, Frantl Industries commenced an action against Maier Construction, Inc., for payment in the sum of $5,516 for the work done pursuant to the contract dated December 28, 1971. It also sued Maier on an oral contract by which Maier agreed to pay Frantl $400 for removal of the of the urethane lining of the kiln, which deteriorated after the paint softened and bubbled away.

The case was tried to the court, and the trial judge found that Frantl was entitled to $1,380, the cost of a steel ceiling which Frantl had properly installed in the kiln. He concluded, however, that Frantl could not recover on the written contract of December 28, 1971, because it had failed to comply with a provision of that contract that the materials must withstand live steam to the temperature of 250 degrees, a provision not written into the contract, but which the judge concluded was omitted by mutual mistake. Thus, the trial judge reformed the contract to include the specification in regard to the ability of the materials to withstand heat. As the contract was reformed, he found that the plaintiff had breached the contract and therefore was not entitled to recover.

From an examination of the record, we conclude that there is no evidence that the parties intended to include *592 in the written contract a specification or warranty that the paint withstand steam heat to a temperature of 250 degrees. There was no evidence that the failure to include that provision was due to a mutual mistake of the parties. Under accepted rules of law, the facts shown were not sufficient to warrant reformation.

We accordingly conclude that the contract was performed, and the plaintiff is entitled to recover the contract price.

In examining the record, we find that Frantl had previously, and only a short time before, attempted to do the work on the steam-heated drying kiln for the American Concrete Pipe Company, but the paint then used ignited and American Concrete was obliged to have the work done over. This prior contract is of importance only to the extent that it furnishes evidence that Frantl knew that the materials used in the interior of the kiln would be subjected to live steam.

The defendant contends that the undisputed facts found by the trial judge are sufficient to authorize the reformation of the contract and, as reformed, the plaintiff failed to fulfil its obligation. The facts which the defendant considers controlling are these: (1) The parties entered into a written contract on December 28, 1971; (2) at the time the contract was made, both parties knew that the materials used must withstand steam to 250 degrees Fahrenheit; (8) that specification, in regard to temperature, was not written into the contract; and (4) the materials used did not withstand 250 degrees Fahrenheit steam and dissolved upon the first use of the kiln.

The defendant argues that, by the proof of these facts, its defense and counterclaim under the reformed contract was satisfied. We think not. Three elements must be proved by clear, satisfactory, and convincing evidence to make possible the substitution of a reformed contract for the written contract entered into by the parties. *593 Those elements are: (1) The parties reached an agreement; (2) the parties intended that such an agreement he included in the written expression of agreement; and (3) the oral agreement was not included in the written expression because of the mutual mistake of the parties.

Under this accepted test, the mere fact that in the instant case both parties knew' that the materials must withstand steam to a temperature of 250 degrees is not synonymous with the statement that the parties agreed to that provision or that they agreed that such provision should be included in the written contract. Nor are those facts probative that mutual mistake was the reason for not including that agreement in the written contract.

The trial judge’s findings of fact parallel the statement of undisputed facts, which the defendant contends are controlling. However, as the plaintiff points out, the question is not whether those facts are supported by the evidence but whether those facts are sufficient to mandate a reformation of the contract. Conceding that the facts found by the trial judge are supported by the evidence, they are, nonetheless, insufficient. Moreover, from an examination of the record we conclude that the facts proved were insufficient to support findings that would mandate reformation.

The rule in respect to reformation of written contracts was succinctly stated in Ahnapee & Western Ry. Co. v. Challoner (1967), 34 Wis. 2d 134, 137, 148 N. W. 2d 646:

“An insurance policy like any other contract may be reformed because of mutual mistake when the policy does riot contain the provisions intended by the parties to be included. But, the contract must be reformed to conform to some oral agreement or understanding which the written document was intended to express. . . . The quantum of proof necessary to show that through inadvertence, accident, or mutual mistake the contract of insurance does not fully or correctly set forth the inten *594 tion of the parties is the so-called middle burden of proof —clear, satisfactory and convincing evidence.”

Touchett v. E Z Paintr Corp. (1953), 263 Wis. 626, 630, 58 N. W. 2d 448, 59 N. W. 2d 433, also stated the circumstances under which a court was permitted to reform a written contract:

‘The rule may be stated briefly that reformation cannot be allowed except upon the most positive and satisfactory evidence showing either fraud or mistake in committing an agreement to writing; that is, that there is either mutual mistake or mistake on the part of one party and fraud on the part of the other. The proof must be clear, plain, convincing, and beyond reasonable controversy that by fraud or mistake the true contract was not presented in writing. . . . There is a further rule of law that the court will not insert a provision in a contract which was omitted with the consent of the parties asking for reformation, although such consent was given in reliance on an oral promise of the other party that the omission would not make any difference. A further elementary rule of law is that a court, even in an equitable action seeking reformation, cannot make for the parties a contract upon which there has been no meeting of the minds, or make for the parties a contract covering elements which have been entirely overlooked by the parties themselves. Such omissions may result in misunderstandings or disagreements between the parties, and they may be the source of eventual lawsuits, regretful as such consequences may seem. However, such differences are to be resolved in an action at law and not in an action in equity seeking reformation.’ ”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kay Beer Distributing, Inc. v. Energy Brands, Inc.
408 F. App'x 996 (Seventh Circuit, 2011)
Hocking v. City of Dodgeville
2010 WI 59 (Wisconsin Supreme Court, 2010)
State Bank of La Crosse v. Elsen
383 N.W.2d 916 (Court of Appeals of Wisconsin, 1986)
St. Norbert College Foundation, Inc. v. McCormick
260 N.W.2d 776 (Wisconsin Supreme Court, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
229 N.W.2d 610, 68 Wis. 2d 590, 1975 Wisc. LEXIS 1619, Counsel Stack Legal Research, https://law.counselstack.com/opinion/frantl-industries-inc-v-maier-construction-inc-wis-1975.