Bostco LLC v. Milwaukee Metropolitan Sewerage District

2011 WI App 76, 800 N.W.2d 518, 334 Wis. 2d 620, 2011 Wisc. App. LEXIS 411
CourtCourt of Appeals of Wisconsin
DecidedMay 24, 2011
DocketNos. 2007AP221, 2007AP1440
StatusPublished
Cited by3 cases

This text of 2011 WI App 76 (Bostco LLC v. Milwaukee Metropolitan Sewerage District) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bostco LLC v. Milwaukee Metropolitan Sewerage District, 2011 WI App 76, 800 N.W.2d 518, 334 Wis. 2d 620, 2011 Wisc. App. LEXIS 411 (Wis. Ct. App. 2011).

Opinion

BRENNAN, J.

¶ 1. Bostco LLC and Parisian, Inc. (collectively "Bostco" unless otherwise noted) brought this lawsuit against the Milwaukee Metropolitan Sewerage District ("the District") for damages sustained to the Bostco-owned Boston Store building in downtown Milwaukee. Bostco alleged that the District's negligent maintenance and operation of the Deep Tunnel—a nineteen mile, thirty-two foot diameter, sewage and stormwater tunnel, running 300 feet below downtown Milwaukee—permitted groundwater in the downtown area to excessively seep into the Deep Tunnel, dewatering the ground underneath the Boston Store. Bostco contended that, as a result of the dewatering, the water table in the area of the Boston Store dropped and the timber piles upon which the store was founded began to rot and shift due to exposure to air and soil settlement, resulting in millions of dollars in damages.

¶ 2. Bostco's amended complaint against the District alleged four claims: (1) negligence; (2) continuing nuisance; (3) inverse condemnation; and (4) excavation protection under Wis. Stat. § 101.111 (2009-10).1 The District filed a motion to dismiss the amended complaint, alleging that Bostco had failed to meet the [631]*631notice-of-claim requirements set forth in Wis. Stat. § 893.80(1). The trial court denied the motion and determined that Bostco substantially complied with § 893.80(l)'s requirements. The District later filed for summary judgment, and the trial court granted the motion, in part, dismissing Bostco's claims for inverse condemnation and statutory excavation protection. Bostco's negligence and nuisance claims proceeded to a jury trial.

¶ 3. Bostco only prevailed on the negligence claim at trial. On that claim, the jury found that Bostco suffered $9 million in past and future harm, but that Bostco was thirty percent contributorily negligent. With respect to the nuisance claim, the jury concluded that although the District interfered with Bostco's use and enjoyment of its building, Bostco did not suffer "significant harm," thereby defeating the claim.

¶ 4. Both parties filed post-verdict motions, and, after a hearing, the trial court: (1) upheld the jury's finding that Bostco was thirty percent contributorily negligent; (2) reversed the jury's finding that Bostco knew or should have known of its injury prior to June 4, 1997; (3) upheld the jury's verdict that Bostco incurred no significant harm from the District's interference with Bostco's full use and enjoyment of its property; (4) concluded that the District did not enjoy governmental immunity pursuant to Wis. Stat. § 893.80(4); and (5) applied the $50,000 municipal damage cap in § 893.80(3). The effect of the trial court's post-verdict rulings was to limit Bostco's recovery to $100,000, i.e., $50,000 for each Bostco and Parisian.

¶ 5. Following the trial court's post-verdict order applying the $50,000 cap on damages, Bostco filed a motion for injunctive relief, claiming that it was irreparably harmed by the District's negligence and that the [632]*632imposition of the caps prevented it from obtaining an adequate remedy under the law. As relief, Bostco asked the trial court to order the District to line that portion of the Deep Tunnel near the Boston Store with concrete. The trial court granted Bostco's motion, ordering the District to fully line the Deep Tunnel with concrete one-half mile north and one-half mile south of the Boston Store.2

¶ 6. Bostco now appeals, arguing that the trial court erred by: (1) refusing to change the jury's finding that Bostco did not suffer "significant harm," despite also awarding Bostco millions of dollars in past damages; (2) applying the $50,000 municipal damage cap set forth in Wis. Stat. § 893.80(3); (3) failing to change the jury's finding that Bostco was contributorily negligent; (4) dismissing Bostco's inverse condemnation claim on summary judgment; and (5) dismissing Bostco's Wis. Stat. § 101.111 claim on summary judgment.

¶ 7. The District cross-appeals, arguing that the trial court erred by: (1) failing to conclude that the District is immune from liability pursuant to Wis. Stat. § 893.80(4); (2) reversing the jury's finding that Bostco's claims were barred by the statute of limitations; (3) concluding that Bostco substantially complied with the notice and itemization of relief requirements set forth in § 893.80(1); and (4) ordering injunctive relief after trial and after the deadline for filing post-verdict motions had passed.

¶ 8. We affirm all but two of the trial court's orders, albeit some on different grounds. We overturn [633]*633the trial court's order refusing to reverse the jury's nuisance finding that Bostco did not suffer significant harm and its order granting Bostco injunctive relief.

Discussion

¶ 9. We will address each of the parties' arguments in the context of Bostco's causes of action, that is, negligence, followed by nuisance, then inverse condemnation, and Wis. Stat. § 101.111. Finally, we will address the trial court's injunction order.

I. Negligence

¶ 10. We turn first to Bostco's negligence claim; the only claim on which Bostco succeeded before the trial court. The jury found that the District was "negligent in the manner in which it operated or maintained the tunnel near the Boston Store" and that the negligence was "a cause of the claimed damage to the Boston Store foundation." Furthermore, the jury concluded that $3 million would "fairly and reasonably compensate" Bostco for past damages and $6 million would "fairly and reasonably compensate" Bostco for any future damages. However, the jury also found Bostco thirty percent contributorily negligent, and during the post-verdict hearing, the trial court applied the municipal damage cap set forth in Wis. Stat. § 893.80(3), reducing Bostco's total relief to $100,000, to wit, $50,000 for each Bostco and Parisian.

¶ 11. With respect to negligence, we turn first to the District's argument on cross-appeal that it is entitled to immunity pursuant to Wis. Stat. § 893.80(4). Second, we address the application of the municipal tort cap on damages set forth in § 893.80(3). Third, we look to the trial court's decision to change the jury's answer [634]*634regarding the applicable statute of limitations. Finally, we address the District's claim that Bostco failed to properly serve the District with a notice of claim or an itemization of damages pursuant to § 893.80(1).

¶ 12.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bostco LLC v. Milwaukee Metropolitan Sewerage District
2013 WI 78 (Wisconsin Supreme Court, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
2011 WI App 76, 800 N.W.2d 518, 334 Wis. 2d 620, 2011 Wisc. App. LEXIS 411, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bostco-llc-v-milwaukee-metropolitan-sewerage-district-wisctapp-2011.