H.J. Kramer Plumbing & Heating, Inc. v. Scharmer

386 N.W.2d 742, 1986 Minn. App. LEXIS 4264
CourtCourt of Appeals of Minnesota
DecidedApril 29, 1986
DocketC1-85-1564
StatusPublished
Cited by9 cases

This text of 386 N.W.2d 742 (H.J. Kramer Plumbing & Heating, Inc. v. Scharmer) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H.J. Kramer Plumbing & Heating, Inc. v. Scharmer, 386 N.W.2d 742, 1986 Minn. App. LEXIS 4264 (Mich. Ct. App. 1986).

Opinion

OPINION

RANDALL, Judge.

Ralph A. Scharmer & Sons, Inc. and Ralph A. Scharmer appeal from a judgment entered against them by the trial court on July 1, 1985. The trial court judgment reformed the contract between appellants and respondent, H.J. Kramer Plumbing and Heating (Kramer), a subcontractor, to ex- *744 elude construction of the lift station building for the Enterprise Rest Area being constructed by appellant under the terms of a government contract. The court found the written contract between Kramer and Scharmer Construction contained no term requiring respondent to pay a bond fee. The court assessed prejudgment interest under Minn.Stat. § 549.09, subd. 1(c) (1984), on the amount due from April 26, 1979, the day Kramer demanded payment.

Appellants did not move for amended findings or a new trial. After appellants filed this appeal, respondent moved to dismiss, stating as grounds that appellants' statement of facts “does not include evidence tending to support the judgment or a single transcript reference, as required by Minn.R.Civ.App.P. 128.02, subd. 1(c).” This court denied respondent’s motion, finding the motion to dismiss improper because appellants’ brief was timely filed.

FACTS

Ralph A. Scharmer is a masonry contractor and owner of Ralph A. Scharmer & Sons, Inc. (Scharmer Construction). Henry Scharmer, Ralph Scharmer's brother, negotiated with Robert Heftman, then an employee of Kramer, the terms of the contract at issue here. Henry Scharmer owns Winona Excavating Company. David Scharmer is an officer of Scharmer Construction and is the son of Ralph Scharmer.

On February 23, 1977, Scharmer Construction entered into a contract with the State of Minnesota to construct an “Enterprise Rest Area” near Lewiston in Winona County. The job consisted of constructing a building and sewage disposal system, and developing the site. Scharmer Construction subcontracted out the excavating, plumbing, electric, heating, and ventilation work.

Kramer submitted a telephoned bid for the sewage disposal system, known as Item 31 of the contract. Scharmer initially rejected Kramer’s bid because it was not the lowest bid. Scharmer acknowledges receiving the telephone bid, but was unable to produce his written record of the bid at trial. Each of the three bids Scharmer received for the sewage disposal system, including Kramer’s, expressly excluded construction of the lift station building. None included an express term for a performance bond.

Early in 1977, a chance meeting between Hubert Kramer, president of Kramer Plumbing, and Ralph Scharmer occurred at a local restaurant. Scharmer told Kramer that negotiations with the company to which the sewage disposal contract had been awarded had been unsuccessful and that Kramer could still get the contract. Ralph Scharmer told Kramer to resubmit a bid, which would include all work inside the lift station. The trial court found that no contract was formed at this meeting.

The court found that Ralph Scharmer asked Henry Scharmer to coordinate subcontracting of the sewage disposal system because Ralph ran into difficulties and had underestimated the cost of construction of the sewage disposal system.

The trial court also found that Robert Heftman, a Kramer employee, met on at least one occasion with Henry Scharmer to negotiate the terms of the contract. During that meeting, Heftman told Scharmer that the Kramer bid excluded construction of the lift station. The trial court found that an agreement was formed during this meeting. That agreement excluded construction of the lift station building. Heft-man drafted a contract expressing the agreement and presented it to Ralph Scharmer for final approval.

The written contract, formed by formal acceptance of the Kramer bid, reads as follows:

Section 60-All Plumbing Work $23,300.00
Section 64-Water Supply System $16,000.00
Section 65-Site Irrigation System $ 7,000.00
Item No. 31 Sewage Disposal System $45,256.00
Electrical included in above as per specification and backhoe as agreed $91,556.00
WE PROPOSE hereby to furnish material and labor— complete in accordance with above specifications, for the sum of: Ninety One Thousand Five Hundred Fifty Six Dollars ($91,556.00)

*745 This contract was formed by Ralph Scharmer’s signature at a place on the bid form, indicating that he accepted the Kramer bid and authorized Kramer to begin the work. Appellant and respondent did not review the contract together. The underlined portion of the contract, pertaining to the electrical work, was added to the typed bid by Ralph Scharmer. The trial court found that the “Sewage Disposal System,” term of the contract, Item 31, mistakenly failed to specifically exclude construction of the lift station. “Item 31” refers to a portion of the Department of Transportation contract with Scharmer Construction. In their oral negotiations, the parties agreed that not all Item 31 work was to be done by Kramer. Respondent contends, and the trial court found, that the parties did not intend for Kramer to construct the lift station building. Scharmer Construction disputes this finding.

During construction of the Enterprise Rest Area, the State expressed to David Scharmer its concern that the project might be in jeopardy because the lift station had not been constructed. Scharmer Construction did not request or demand that Kramer construct the station and Scharmer Construction built the lift station building.

The cost of constructing the lift station building was $7,000. Scharmer Construction withheld the entire final contract payment of $12,784.37 due Kramer, $7,000 for construction of the lift station and $915.56 for a performance bond. Scharmer concedes that he owes Kramer $4,868.81 of the final payment. Scharmer Construction testified at trial that industry custom dictates a one percent surcharge for a performance bond on all contracts.

Kramer first learned of Scharmer Construction’s claim that Kramer was responsible for constructing the lift station two years after the project was completed, during the final accounting in April, 1979, which revealed that $4,868.81 was due from Scharmer Construction to Kramer.

Kramer began suit January 6, 1981, to collect the balance due. The trial court awarded Kramer a judgment of $12,784.37, which included the total due, $4,868.81, the $7,000 Scharmer Construction withheld for the construction of the lift station, $915.56 withheld by Scharmer Construction for the bond, plus prejudgment interest from April 26, 1979, the day Kramer demanded payment.

ISSUES

1. Did the trial court properly reform the parties’ contract to exclude construction of the lift station building?

2. Did the trial court properly find respondent was not obligated to pay appellant a performance bond premium?

3. Did the trial court properly compute prejudgment interest under Minn.Stat. § 549.09 (1984)?

ANALYSIS

I.

Standard of Review

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Staffing Specifix, Inc. v. TempWorks Management Services, Inc.
896 N.W.2d 115 (Court of Appeals of Minnesota, 2017)
Norwest Bank Wisconsin, N.A. v. Malachi Corp.
245 F. App'x 488 (Sixth Circuit, 2007)
Farrell v. Johnson
442 N.W.2d 805 (Court of Appeals of Minnesota, 1989)
Apple Valley Red-E-Mix, Inc. v. Mills-Winfield Engineering Sales, Inc.
436 N.W.2d 121 (Court of Appeals of Minnesota, 1989)
Herbst v. Northern States Power Co.
432 N.W.2d 463 (Court of Appeals of Minnesota, 1988)
Alexander v. Holmberg
410 N.W.2d 900 (Court of Appeals of Minnesota, 1987)
Solid Gold Realty, Inc. v. Mondry
399 N.W.2d 681 (Court of Appeals of Minnesota, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
386 N.W.2d 742, 1986 Minn. App. LEXIS 4264, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hj-kramer-plumbing-heating-inc-v-scharmer-minnctapp-1986.