Apple Valley Red-E-Mix, Inc. v. Mills-Winfield Engineering Sales, Inc.

436 N.W.2d 121, 8 U.C.C. Rep. Serv. 2d (West) 21, 1989 Minn. App. LEXIS 214, 1989 WL 14988
CourtCourt of Appeals of Minnesota
DecidedFebruary 28, 1989
DocketC1-88-1210
StatusPublished
Cited by17 cases

This text of 436 N.W.2d 121 (Apple Valley Red-E-Mix, Inc. v. Mills-Winfield Engineering Sales, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Apple Valley Red-E-Mix, Inc. v. Mills-Winfield Engineering Sales, Inc., 436 N.W.2d 121, 8 U.C.C. Rep. Serv. 2d (West) 21, 1989 Minn. App. LEXIS 214, 1989 WL 14988 (Mich. Ct. App. 1989).

Opinion

OPINION

CRIPPEN, Judge.

Appellant contends the parol evidence rulé conflicts with the trial court’s finding of an express warranty on the capacity of a cement unloading machine. We agree and reverse. As a consequence, we do not reach the question of sufficiency of the evidence on the express warranty nor the conflicting claims of the parties regarding damages.

FACTS

Respondent Apple Valley Red-E-Mix, Inc., a cement plant operator, entered into an agreement to lease an unloading machine from appellant Cyclonaire, Corp. which manufactures systems used to transport products, such as cement, from one site to another. The agreement was for the use of the “Docksider II-V,” a single piece of equipment capable of transferring cement from barges to a storage site.

The lease agreement between the parties required respondent to make monthly payments of 12 percent of the full value of the Docksider II-V and to insure it throughout the lease to its full value of $157,000. The lease also provided respondent with an option to purchase the Docksider II-V during the first three months of the lease period. The lease included an exclusive warranty of merchantability and an exclusive replace and repair remedy for breach of warranty. Additionally, the lease contained an integration clause stating that the parties’ entire agreement was contained in the written lease. Respondent submitted a check for $19,000, one-third of the three month lease term, to appellant’s Twin City representative, Mills-Winfield Engineering Sales, Inc., also an appellant.

Respondent sued appellant for breach of warranty, claiming that the Docksider II-V failed to meet an unloading rate of 125 tons per hour and that because of the delay respondent incurred $125,000 in consequential damages for additional barge demur-rage charges and other expenses. The trial court held the delay was caused in part by breach of an express warranty on capacity of the machine.

The trial court calculated the damages due to delay by taking respondent’s total expenses and multiplying it by the ratio between actual average unloading capacity (55 tons per hour) and minimum expected unloading capacity (100 tons per hour) to determine the amount apportionable to respondent’s normal unloading expenses. This figure ($139,151.29) was then subtracted from the total expense ($253,002.36) to give the amount of consequential damages to be apportioned ($113,851.07). The trial court found, based on comparative fault, that appellants were 60 percent responsible (in the amount of $68,310.64) for the consequential damages and respondent 40 percent responsible. Both parties dispute the trial court’s calculation of damages.

Appellant disputes the legality of parol evidence on the express warranty, as well as sufficiency of the evidence to prove a warranty in light of the contract disclaimer. Because we are convinced the express warranty depends on evidence prohibited by the parol evidence rule, we reverse on this point alone.

ISSUE

Did the trial court err in using parol evidence to find an express performance warranty?

*123 ANALYSIS

Pursuant to general contract law, the terms of a final and integrated written expression may not be contradicted by par-ol evidence of previous “understandings and negotiations * * * for the purpose of varying or contradicting the writing.” 3 A. Corbin, Corbin on Contracts § 573 (1960); see Lehman v. Stout, 261 Minn. 384, 389-91, 112 N.W.2d 640, 643-45 (1961); ICC Leasing Corp. v. Midwestern Machinery Co., 257 N.W.2d 551, 554 (Minn.1977). This rule is also found in Minnesota’s Uniform Commercial Code. Minn.Stat. 336.2-202 (1988); see also Minn.Stat.Ann. § 336.2-202 Minnesota Code Comment, at 177 (West 1966). On the other hand, if a term is ambiguous, parol evidence may be allowed to reach the intent of the parties. ICC Leasing Corp., 257 N.W.2d at 554. In this case the trial court determined the term “Docksider II-V” was ambiguous.

Whether a contract term is ambiguous is a legal question for the trial court. See Blattner v. Forster, 322 N.W.2d 319, 321 (Minn.1982). On appeal, it must be determined whether the trial court properly found ambiguity. Kenko, Inc. v. Lowry Hill Construction Co., 392 N.W.2d 18, 20 (Minn.Ct.App.1986), pet for rev. denied (Minn. Oct. 22, 1986). Respondent claims the trial court’s opinion can be supported by H.J. Kramer Plumbing & Heating, Inc. v. Scharmer, 386 N.W.2d 742 (Minn.Ct.App.1986).

In Kramer, the court determined the term “Item No. 31 Sewage Disposal System” was incomplete or ambiguous. Id. at 745. The court held that parol evidence from oral negotiations was admissible to explain what was involved in “Item No. 31” work. Id. In order to do so, the trial court properly weighed documentary and testimonial evidence to determine which projects were included in “Item No. 31.” Id.

On the agreement here the trial court determined:

The agreement does not describe the Docksider II-V. The agreement provides no technical specifications. This machine is a highly sophisticated piece of equipment, which is not in common consumer use. It is not like a Chevy ½ ton pick-up, where naming alone transmits reasonable information. In fact, the Docksider II-V was brand new at the time of this agreement. Naming such a machine without further identification imparts no useful information to the Court or to anyone to aid in discussing this transaction. Clearly parol evidence is necessary to explain what a Docksider II-V is, what it does, and how it operates.

We conclude it was error to permit parol evidence on the theory stated by the trial court. Reference to the Docksider II-V is not ambiguous. Both parties knew which piece of machinery the term Docksider II-V referred to. Moreover, the record shows respondents chose not to lease the Docksider II-P, a larger and more expensive model with greater capacity. It reasonably can be said that the Docksider II-V is indeed like the Chevy ⅛ ton pick-up. The particular equipment named in the lease was not ambiguous, contrary to the term involved in Kramer.

Respondent also contends that parol evidence regarding precontract negotiations is admissible because there is no integrated contract. The trial court in its memorandum observed that the contract was incomplete. The question of whether a contract is completely integrated and not subject to variance by parol evidence is also an issue of law for the trial court. United Artist Communications, Inc. v. Corporate Property Investors, 410 N.W.2d 39,42 (Minn.Ct.App.1987).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sandra Weise v. Alan M. Powell
Court of Appeals of Minnesota, 2024
Staffing Specifix, Inc. v. TempWorks Management Services, Inc.
896 N.W.2d 115 (Court of Appeals of Minnesota, 2017)
Leslie Davis v. Macy's Retail Holdings, Inc.
Court of Appeals of Minnesota, 2017
HORTON, INC. v. NSK Corp., Inc.
544 F. Supp. 2d 817 (D. Minnesota, 2008)
Taylor v. Lifetouch National School Studios, Inc.
490 F. Supp. 2d 944 (N.D. Indiana, 2007)
Borgersen v. Cardiovascular Systems, Inc.
729 N.W.2d 619 (Court of Appeals of Minnesota, 2007)
Mies Equipment, Inc. v. NCI Building Systems, L.P.
167 F. Supp. 2d 1077 (D. Minnesota, 2001)
Bib Audio-Video Products v. Herold Marketing Associates, Inc.
517 N.W.2d 68 (Court of Appeals of Minnesota, 1994)
Maurice Sunderland Architecture, Inc. v. Simon
5 F.3d 334 (Eighth Circuit, 1993)
TRIPLE B & G, INC. v. City of Fairmont
494 N.W.2d 49 (Court of Appeals of Minnesota, 1992)
Resolution Trust Corp. v. Johnson (In Re Johnson)
139 B.R. 208 (D. Minnesota, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
436 N.W.2d 121, 8 U.C.C. Rep. Serv. 2d (West) 21, 1989 Minn. App. LEXIS 214, 1989 WL 14988, Counsel Stack Legal Research, https://law.counselstack.com/opinion/apple-valley-red-e-mix-inc-v-mills-winfield-engineering-sales-inc-minnctapp-1989.