Hicks v. Franklin County Auditor

514 N.W.2d 431, 1994 Iowa Sup. LEXIS 55, 1994 WL 94055
CourtSupreme Court of Iowa
DecidedMarch 23, 1994
Docket93-258
StatusPublished
Cited by24 cases

This text of 514 N.W.2d 431 (Hicks v. Franklin County Auditor) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hicks v. Franklin County Auditor, 514 N.W.2d 431, 1994 Iowa Sup. LEXIS 55, 1994 WL 94055 (iowa 1994).

Opinion

ANDREASEN, Justice.

This is a drainage ease. Plaintiff landowners in the drainage district filed suit against the county auditor, the county board of supervisors, and the drainage district board of trustees to compel a reclassification of property subject to assessments for the costs óf a 1990 construction project. They alleged that notice of the proposed project was deficient, that the project was improperly classified as a repair, and that they were entitled to compensation for all of the property taken for the drainage easement. Following a bench trial, the court ruled that the notice requirements were met, the project was properly considered a repair, and that plaintiffs failed to establish their equitable claims. The court directed the defendants to institute *434 condemnation proceedings for the property taken which exceeded the original right-of-way boundary. Plaintiffs appealed. We affirm.

I. Background and Factual Proceedings.

Drainage District No. 1 (district) was established in February 1906 by the board of supervisors (board) of Franklin County, Iowa. It consisted of an open ditch with a bottom of four feet across and a side slope of one and one-half to one. The width at the top of the ditch depended on the depth of the ditch at any particular location. At a depth of nine and one-half feet the width at the top of the ditch would be approximately thirty-two and one-half feet. The minutes from subsequent meetings of the board indicated that the planned width at the top of the ditch would have to be increased in some places to avoid slopes that would be too steep to construct.

In 1916 the board appointed an engineer to survey the district. He reported that the district was “inadequate, insufficient, and out of repair.” The board then authorized further construction on the district and it was renumbered No. 48. A bulkhead was built between sections three and four of the original plans. The area south of the bulkhead remained an open ditch with a bottom width of six feet and side slopes of approximately one and one-half to one. Tile was installed north of the bulkhead and thirty-seven laterals were constructed. After installation of the tile along the main ditch, the plans called for back-filling to a grade line as shown on the profile. The construction created a surface waterway above the tile line. The actual side slopes of the improvements were not specified in the 1916 plans except for a notation that they were to be no “steeper than 3 vertical to 10 horizontal.” Construction on the drainage district improvements was completed in 1917.

During the period between 1917 and the late 1930s the surface waterway north of the bulkhead became partially filled in. The parties dispute when and how the waterway was filled in, by whom, and to what extent. Several of the plaintiff landowners north of the bulkhead testified that the drainage easement had been farmed with row crops since the early 1940s.

No additional work was done in the district until 1952 when the open ditch south of the bulkhead was cleaned out. The open ditch was again cleaned out in 1983. At that time the entire district was reclassified and the assessments were apportioned among the landowners along the main line and the laterals.

In the 1980s, an extensive federally funded construction project, the Morlee watershed project, was planned for several drainage districts, including district No. 48. Improvements to the main tile and eight laterals were recommended. The board notified affected landowners in the fall of 1987 of the proposed improvements to the district. After a hearing on a remonstrance filed by a group of landowners against the project, the board voted to dismiss all further proceedings on the Morlee project.

In April 1989 six landowners in the district petitioned the board to reactivate the plans for the Morlee watershed improvements. A hearing was held in July, and in August the board voted to take no further action on the petition. Late in August two landowners, who lived north of the plaintiffs, asked the board to look into what repairs were necessary to the tile lines in the district. The board then authorized an engineer, Brent Johnson, to investigate the petition for repairs. In early January 1990 Johnson presented his report on proposed repairs and improvements to the main tile and to lateral No. 17. The report set forth four options; option one was labeled a repair, while the others were labeled improvements.

Next, the county auditor prepared notice of a public hearing on the proposed drainage projects. Notice was published in the local newspaper and mailed to forty-one of the district landowners. The first hearing on the project was held on February 20. At that hearing Johnson indicated the landowners south of the bulkhead would not be assessed any costs of the construction. The discussion was continued to March 5 and notice was given on the rescheduled hearing. In March the hearing was again continued to April to *435 permit additional research and discussion on the issue of cost assessments. When the hearing reconvened on April 9 the board voted to proceed with the repair option. Those present at the April meeting were informed that the landowners to the south of the bulkhead would be assessed for the costs of the repair project. The board approved a bid for construction in early November and work on the project commenced soon thereafter.

On November 26, 1990, landowners Richard and Delores Blackford filed an action in Franklin County raising a number of challenges to the 1990 project. See Iowa Code §§ 468.88-84 (Supp.1989). On January 22, 1991, twenty-three landowners, including the Blackfords, filed a petition for a writ of mandamus also challenging the drainage district proceedings. Id. § 661.1. These plaintiffs also filed petitions appealing from the board’s denial of damages arising from the construction and from denial of their objections to cost assessments made in conjunction with the project. Two additional plaintiffs later intervened in the mandamus action. In February 1992 the district court ordered the two cases consolidated. The plaintiffs then filed a recast consolidated petition on June 1,1992. A trial to the court was held in September 1992 and judgment was entered for the defendants on all claims except compensation for the expansion of the drainage easement. This appeal followed.

On appeal the plaintiffs contend the court erred in (1) determining that notice to forty-one of seventy landowners in the drainage district was sufficient; (2) finding that the 1990 project was a repair rather than an improvement; (3) rejecting their claims for compensation for the easement right-of-way under theories of adverse possession, estop-pel, or laches; and (4) failing to order a reclassification for equitable reasons. We will detail additional facts as they pertain to the arguments presented.

II. Standards for Review.

This consolidated action involves both a direct appeal from the board’s proceedings and a collateral attack on the actions of the board and the auditor by writ of mandamus. See Iowa §§ 468.83-84, 661.1. Such actions are tried as equitable proceedings. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lemke v. Franklin County Board of Supervisors
Court of Appeals of Iowa, 2025
Abbas v. Franklin County Board of Supervisors
Court of Appeals of Iowa, 2024
Sadusky v. Lake Creek
Court of Appeals of Iowa, 2020
Brede v. Koop
706 N.W.2d 824 (Supreme Court of Iowa, 2005)
Koenigs v. Mitchell County Board of Supervisors
659 N.W.2d 589 (Supreme Court of Iowa, 2003)
Brunsman v. DeKalb Swine Breeders, Inc.
952 F. Supp. 628 (N.D. Iowa, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
514 N.W.2d 431, 1994 Iowa Sup. LEXIS 55, 1994 WL 94055, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hicks-v-franklin-county-auditor-iowa-1994.