Board of Supervisors v. Paine

210 N.W. 929, 203 Iowa 263
CourtSupreme Court of Iowa
DecidedNovember 23, 1926
StatusPublished
Cited by5 cases

This text of 210 N.W. 929 (Board of Supervisors v. Paine) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of Supervisors v. Paine, 210 N.W. 929, 203 Iowa 263 (iowa 1926).

Opinion

Vermilion, J.

Prior to 1917, a drainage district had been established in Webster County, consisting, in part, of an open ditch near the boundary between that and Hamilton County, In that year, the boards of supervisors of the two counties, acting as a joint board, established a j0jnt drainage district. The improvement, as so contemplated and constructed, consisted of the deepening of a portion of the open ditch in Webster County, that had been constructed by the original district in that county, and its use as an outlet, and the construction of tiled ditches in Hamilton County, connecting with such outlet. Separate contracts were let for deepening the -open, ditch and for the laying of the tile. The work of deepening the old ditch in Webster County was completed in 1918, and on October 26, 1918, the engineer in charge of the work reported to the joint board the completion of the open-work section of the drain, in accordance with the plans and specifications. This report was approved by action of the joint board on October 28, 1918. With the proceedings so far, this litigation has no direct concern.'

In November and December of 1918, the appellant Paine, under an oral contract with a committee of the joint board, put in certain corrugated iron pipes, to carry the surface water through the spoil banks of the open ditch, and also at the ends of certain tiled drains that had discharged into the ditch, as originally constructed, and which had been disturbed by the deepening of the ditch. The pipe was furnished by the district, *265 and the work performed by Paine was only the hauling .and installing of the pipe; and this work was completed, before December, 11, 1918.

On the last named date, the estimates , of the engineer of the work done by Paine were before, -the board, and, on that date, a written contract was executed by the chairman of the .joint board and Paine, covering the work done by him. This contract bears date October 20, 1918, but the testimony is undisputed that it was in fact executed on December 11, 1918, and after the work was completed. On the same date, warrants were issued by .the auditor of Webster County to Paine for the work done by him, as shown by the estimates of the engineer, and at the prices specified in such written contract. Paine is still the holder of one of these warrants, and the others have been assigned, and are now held by others of the defendants and appellants. .

This action was brought by the boards of supervisors, of Webster and Hamilton Counties against the present holders of the warrants so issued to Paine and against the treasurers and auditors of the respective counties, asking that the warrants be decreed void, and that they be canceled, and that the county treasurers be enjoined from paying them.

The question is .raised, although not strenuously pressed, of the right of the plaintiffs to maintain the action. Our conclusion on the merits makes it unnecessary that we determine that question.

There is no dispute oyer the making of the oral agreement under which the work was done, and no claim that the .contract was not fully and strictly performed by Paine, or that the warrants are invalid merely because the written contract was executed after the completion of the work.

I. There is no allegation in the petition of actual fraud on the part of either Paine or the joint board, nor is such a claim made here. The only allegation or contention in that respect is that the price was excessive, and that, for that reason, the contract was a fraud on the landowners subject to. assessment. No owner of land subject to assessment is objecting, or, so far as the record discloses, has . ever made formal objection, to the assessment on that ground.

There was testimony tending to show that the price, stipulated in the contract was grossly excessive, .and represented an *266 unreasonably large profit. There was also testimony that it .was no higher than had been paid for like work in' Webster and near-by counties about the same time, where the contracts had been let on competitive bids, and was the same as Paine received under another contract for such work in Webster County which was so let, and where there had been a number of bidders. There was evidence of some difficulties peculiar to the work in question. Some explanation of the situation may be found in the fact that the time, just at the close of the war, was one of considerable extravagance in the making of public improvements, great scarcity of labor, extremely high prices, and enormous profits.

However, we do not understand it to be seriously contended that, if' the joint board acted within the authority conferred upon it by statute in making the contract, payment of the contract price could be avoided after full performance by Paine, merely because it was a bad contract for the district and the price was excessive.

II. The contention of appellees is, in the final analysis, that the joint board was not authorized by Section 1989-¿21, Code Supplement of 1913, the statute then in force, to contract for the work done by Paine, and that the only authority for such work was to be 'found in Section 1989-all, and that there was a failure to comply with the provisions of the latter section, in that the work was not recommended by the engineer of the joint drainage district; that it was not authorized by resolution of the joint board; that it increased, and was intended to increase, the assessment against the lands in the district, and no notice was given the property owners; that there was no advertisement for bids for such work, and no opportunity for competitive bidding thereon; and that there were no plans and specifications for the work.

Section 1989-all is as follows:

"If, after the establishment of said district, and before the completion of the drainage improvements therein, it shall becomé apparent that a levee or drain should be enlarged, deepened or otherwise changed or that a change or alteration in the location should be made for the better service thereof, said board may by resolution authorize such change or changes in the said improvement as the engineer shall recommend; provided that, *267 whenever any change or changes are made either under this section or under -any other section of this chapter, all .persons ■whose land shall be taken or whose .assessments shall be. increased thereby shall first have been given like notices as provided in Section 1989-a3 of this chapter, and shall have like opportunity to file claims for damages, as provided for in Section 1989-a4“ of this'chapter, or file objection to such assessment as provided in Section 1989-al2 of this chapter, as the case may be, and like opportunity to appeal from the action of the board as provided in Section 1989-a6 of this chapter, or Section 1989-al4 of this chapter,, as the case may be.”

Section 1989-a21 provides:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hicks v. Franklin County Auditor
514 N.W.2d 431 (Supreme Court of Iowa, 1994)
Haugen v. Humboldt-Kossuth Joint Drainage District No. 2
1 N.W.2d 242 (Supreme Court of Iowa, 1941)
Hogue v. Monona-Harrison Drainage District
296 N.W. 204 (Supreme Court of Iowa, 1941)
Baldozier v. Mayberry
285 N.W. 140 (Supreme Court of Iowa, 1939)
Mooney v. Drainage District No. 1
252 N.W. 910 (Nebraska Supreme Court, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
210 N.W. 929, 203 Iowa 263, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-supervisors-v-paine-iowa-1926.