Breiholz v. Board of Supervisors

186 Iowa 1147
CourtSupreme Court of Iowa
DecidedJuly 10, 1919
StatusPublished
Cited by13 cases

This text of 186 Iowa 1147 (Breiholz v. Board of Supervisors) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Breiholz v. Board of Supervisors, 186 Iowa 1147 (iowa 1919).

Opinion

Weaver, J.

.Much is said in the pleadings that is not necessary to an understanding of the issues in this case. Briefly stated, it is conceded, or shown without controversy, that, in the year 1907, a drainage district known as “No. 29” was established in Pocahontas County, and the district was improved by the construction of a drainage system composed of a certain main, with other laterals or branches. While some of these drains were of the closed or tile pattern, a large proportion thereof was open. In the year 1910, the engineer in charge of the district reported to the board of supervisors that a certain portion of the open main ditch, and one or more of the branches, had become filled with silt or sediment, to an extent making it necessary or proper to clean the obstructed channels. He estimated the- necessary excavation at 5,500 yards. Nothing seems to have been done with reference to this report during that year, or until March, 1911, when the engineer brought up the subject anew, but this time recommending a more extensive cleaning and repairing of the open ditches in the district, and estimating the entire excavation at about 4,500 cubic yards. Acting on this report and approving it, the board voted to employ >S. F. Hiatt to do the work, being approximately 7,317 yards, at 30 cents, in the upper part of the district, 36,104 yards, at 28 cents, in the lower part, and [1149]*1149936 yards in what is known as “Branch A.” A contract to this effect was then made between the county auditor and Hiatt. The letting of the contract was not advertised, and was not offered for bids. Proceeding under the contract, Hiatt performed the work, and the cost or expense so incurred was, by order of the board, assessed against all the lands within the district, in proportion to their assessment for the original construction of the system. The plaintiffs own tracts of land affected by this assessment, and bring this action to have the same adjudged invalid, and the lien thereof vacated and removed.

i. drains : establishment and maintenance: repairs : noticeHiatt was made a defendant, and by proper pleading he asked that his right to the agreed compensation be confirmed. The theory upon which jilaintiffs demand relief is that the work actually contracted for and performed was not, in ant proper sense of ” . the term, a work of repair upon the existing system, but rather in the nature of an original or independent improvement, which the supervisors could not lawfully establish or order except upon notice to the property owners, and that they could not lawfully contract for its construction, except upon due advertisement, and upon competitive bids. And this, in brief, is what we understand to be the central proposition upon which the result of this litigation turns.

The trial court, after hearing the evidence, entered a decree adjudging the equities to be with defendants; that the board of supervisors had complied with the law in letting the contract to Hiatt; and that Hiatt had performed his l>art of the agreement, and was entitled to a compliance with such contract on the part of the board of supervisors and the county auditor.

To ascertain the nature of the work contemplated, we turn to the written contract-entered into with Hiatt, and find it there recited that he agreed “to deepen, clean, re[1150]*1150open, and repair said Drainage District No. 29 from Station Zero to Station 37 in the manner and to the proportionate depth and width as specified in the report of W. B. Warrington, filed March 11, 1911; and from Station 37 to Station 87; from Station 87 to Station 170; from Station 170 to Station 250; the above approximating about 35,168 yards, herein called'the lower end of said district; also, in addition to the above work in the lower end of the district, the second party agrees to clean, reopen, and repair Branch A from Station Zero to Station 23 * * * approximating 936 cubic yards * * * and to clean, reopen, deepen, and repair said drainage improvement from Station 402 to Station 500, approximating about 7,317 cubic yards, and herein called the upper end of said district.” Other provisions of the writing relate to matters of detail, not bearing materially upon the issues in the case.

The engineer’s report and recommendation, upon which the board acted in letting the contract, do not appear to be embodied in the record; and, the engineer making it being since deceased, we do not have the advantage of -his testimony; but it may be presumed that the contract as made with Hiatt is in substantial accord with such recommendation. The work was done under the supervision of the county’s engineer; and the testimony tends to show that, in so doing, the contractor not only took out the sediment with which the ditches had, to a greater or less extent, become filled or obstructed, but, under the direction of the engineer, or in pursuance of the plans furnished by him, the contractor also, in certain places, increased the depth of the excavation below its original grade, and in other places sought to insure greater permanency of the banks of the ditch by increasing their slope; and to that extent increased the original width of the channel. There is also evidence of some original excavation at the outlet.

It further appears that the contractor extended an ex-[1151]*1151cavatiou beyond the district limits a short distance, in order to facilitate the successful operation of the drainage, system; but for this work, he testifies that he neither asked nor received compensation, and his statement does not appear to be disputed.

The Avitnesses generally agree that the ditches had become filled and obstructed to a degree rendering it. necessary, or at least appropriate, that they should be cleaned out and repaired, if they were to be of real benefit to the lands of the district; and it is also reasonably certain that, when this work was completed, the ditches were, in part at least, somewhat deeper and wider than they Avere as originally constructed. No witness undertakes to say that the work done Avas uncalled for, or did not constitute a substantial betterment of the drainage system; but there is some evidence to the effect that the compensation to the contractor, as fixed in the agreement, was in excess of its fair value. The charge in the plaintiff’s petition, and repeated in argument, that the work contracted for and. done included a lengthening or extension of the ditch or ditches beyond their original dimensions, is not justified by the record; but, as Ave have said, it is to be conceded that the channels Avere not only reopened, cleaned, and emptied of silt and obstructions, but were, to some extent, materially deepened.

Such being, in part, the nature of the work contracted for. and done, the material, legal inquiry is whether, under the provisions of the statute, the board was authorized to undertake it without notice to the property, owners, or to let the contract except upon competitive bidding.

If we will bear in mind that this work here done was in a drainage district, the organization of which had been perfected for several years, and that the drainage improvements contemplated in such organization had been fully completed long before the extension of this contract to re[1152]*1152open, clean, and deepen the ditches,- there need be no doubt •or confusion as to the effect of the statute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Haugen v. Humboldt-Kossuth Joint Drainage District No. 2
1 N.W.2d 242 (Supreme Court of Iowa, 1941)
Hogue v. Monona-Harrison Drainage District
296 N.W. 204 (Supreme Court of Iowa, 1941)
Payne v. Missouri Valley Drainage District
272 N.W. 618 (Supreme Court of Iowa, 1937)
Board of Supervisors v. Board of Supervisors
241 N.W. 14 (Supreme Court of Iowa, 1932)
Board of Supervisors v. Paine
210 N.W. 929 (Supreme Court of Iowa, 1926)
Meyerholz v. Board of Supervisors
204 N.W. 452 (Supreme Court of Iowa, 1925)
Nelson v. Graham
198 Iowa 267 (Supreme Court of Iowa, 1924)
Board of Trustees v. Boards of Supervisors
198 Iowa 117 (Supreme Court of Iowa, 1924)
Nervig v. Joint Boards of Supervisors of Polk & Story Countries
193 Iowa 909 (Supreme Court of Iowa, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
186 Iowa 1147, Counsel Stack Legal Research, https://law.counselstack.com/opinion/breiholz-v-board-of-supervisors-iowa-1919.