Walker v. Joint Drainage District No. 2 of Osceola & Dickinson Counties

197 Iowa 351
CourtSupreme Court of Iowa
DecidedFebruary 12, 1924
StatusPublished
Cited by11 cases

This text of 197 Iowa 351 (Walker v. Joint Drainage District No. 2 of Osceola & Dickinson Counties) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walker v. Joint Drainage District No. 2 of Osceola & Dickinson Counties, 197 Iowa 351 (iowa 1924).

Opinion

Faville, J.

I. Joint Drainage District No. 2 of Osceola and Dickinson Counties was duly established in November, 1913. The improvement provided for was constructed and an assessment to cover the costs of construction was confirmed in July, 1914. The improvement consists of a main tile, having a total length of 19,600 feet, with numerous branches, or laterals, connecting with it. In this case we are only concerned with two of these branches. The accompanying plat will help to an understanding of the questions involved.

As .shown thereon, there was originally constructed Branch No. 126, starting at Station 126 on the main line, and extending to Station 47. From said branch there extended southward [353]*353Branch 126-47, from Station 47 to Station 20. From Station 118 on the main line there extended Branch 118, which terminated at Station 5.

We take np first the matters involved in connection with Branch 126.

Branch 126 and Branch 126-47 were constructed according to the original plans and specifications, extending from Station 126 on the main line in a general southwesterly and southerly direction to Station 20. The tile system as so constructed was found inadequate to furnish drainage to the east half of Section 35, and the boards of supervisors employed an engineer to examine the premises and to make report, which was done; and subsequently the boards of supervisors ordered the construction of what is shown on the plat as Branch 126-40, starting at Station 40 on Branch 126 and extending in a general southerly and southwesterly direction, its terminal point being about 350 feet north and east of Station 20 on Branch 126-47. There is evidence in the record in great detail regarding the construction of the original lateral south of Station 47 and the necessity of the construction of the new lateral, 126-40, to adequately drain the east half of Section 35. It is contended that it was originally planned that a pond lying east of Branch 126-47 should be tiled westward into said branch, and that it was discovered that the tile as laid in Branch 126-47 were too shallow to permit drainage of the said pond in that manner. The newly constructed branch, 126-40, as shown on the plat, passes directly through the pond in question, and furnishes adequate drainage therefor to the north, and has its outlet in Branch 126 at Station 40.

Briefly stated, it is the contention of appellants that the construction of Branch 126-40 is not a repair of any portion of the original improvement, but is the construction of an entirely new and separate improvement, and that appellants cannot be assessed therefor without notice as provided by the statute.

All of the lands lying within the drainage district in the east half of Section 35 were classified and assessed for the construction of the original improvement. Code Supplement 1913, Section 1989-a21, provides that, after a drainage improvement has been constructed, it shall be under the supervision of the [354]*354board of supervisors, and “it shall be the duty of the board to keep the same iu repair and for that purpose they may cause the same to be enlarged, reopened, deepened, widened, straightened or lengthened for a better outlet, and they may change or enlarge the same or cause all or any part thereof to be converted into a closed drain when considered for the best interests of the public rights affected thereby.”

The work authorized by this section may be done without notice to landowners whose lands have been classified and assessed for the construction of the original improvement. Breiholz v. Board of Supervisors, 186 Iowa 1147.

If the construction of Branch 126-40 comes within the purview of said Section 1989-a21, then appellants were not entitled to any notice. If it is a new improvement, and not within the provisions of Section 1989-a21, then, since they received no notice of such proposed improvement, the assessment of appellants’ lands therefor is void.

Branch 126-47 extends southward from Station 47 about 2,000 feet. The newly constructed branch, 126-40, which is somewhat parallel the greater part of its length to Branch 126-47, extends southward from Station 40 about 2,100 feet. The pond through which the newly constructed branch, 126-40, extends, is approximately 900 feet east of Branch 126-47. The pond contains about six acres. The evidence tends to show that it was contemplated that the original branch, 126-47, would furnish adequate drainage for all of the lands lying north and east of Station 20 in Section 35.

It appears from the evidence that the original improvement was constructed in accordance with the plans and specifications adopted by the boards of supervisors at the time of the establishment of the district, and that the assessment was made against the tracts of lands for the cost of the construction of the improvement as so established. That Branch 126-47 failed to adequately drain the lands adjacent to it in the east half of Section 35 was due, not to defective' work in constructing the improvement, but to a defect in the plan itself. The lateral would not adequately drain the lands because it was planned in a defective manner, in providing for too small tile and for too flat a grade. The “repair” that became necessary because of [355]*355the condition was not a “repair” of the physical improvement as made upon the land, but it was a “repair” of the plan of the engineer who designed the original improvement which was adopted by the board of supervisors. In other words, the original plan for the drainage of this tract of land was inadequate and insufficient to do the work.

In order to furnish adequate drainage for the lands in this area, it became necessary either to modify the original plan by digging up the tile and laying a larger tile and at a greater depth, or to adopt some entirely new plan of drainage. There is evidence tending to show that it was determined by the board of supervisors, upon an investigation and report to them by an engineer, that it was cheaper and more efficient to leave the existing improvement and construct the new branch, 126-40, of a larger tile and with a greater fall, and laid through the pond previously referred to, and uniting with Branch 126 at Station 40. The question that confronts us at this point is whether the construction of Branch 126-40, under these conditions and for this purpose, may be properly said to be a “repair,” under Section 1989-a21, or the enlargement, reopening, deepening, widening, straightening, or lengthening of the original drain for a better outlet.

We have had said section before us for consideration in numerous cases. We do not think that it can be said that the construction of Branch 126-40, under these circumstances, is in any proper sense a “repair” of the work of the original construction of the drainage system. There is no attempt at replacement or any repair, modification, or change of any kind in the original tile as constructed. As before stated, the thing that is repaired is the plan, and not the constructed system. To repair means “to restore to a sound or good condition after decay, injury, dilapidation, or partial destruction.” American Bonding Co. v. City of Ottumwa, 137 Fed. 572. See, also, Dougherty v. Taylor & Norton Co., 5 Ga. App. 773 (63 S. E. 928); Walker v. City of Detroit, 143 Mich. 427 (106 N. W. 1123); Brown County v. Keya Paha County, 88 Neb. 117 (129 N. W. 250).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hicks v. Franklin County Auditor
514 N.W.2d 431 (Supreme Court of Iowa, 1994)
Morrow v. Harrison County
64 N.W.2d 52 (Supreme Court of Iowa, 1954)
Jagodzinske v. County of Martin
58 N.W.2d 61 (Supreme Court of Minnesota, 1953)
Haugen v. Humboldt-Kossuth Joint Drainage District No. 2
1 N.W.2d 242 (Supreme Court of Iowa, 1941)
Untitled Texas Attorney General Opinion
Texas Attorney General Reports, 1941
Hogue v. Monona-Harrison Drainage District
296 N.W. 204 (Supreme Court of Iowa, 1941)
Kelleher v. Joint Drainage District No. 18
249 N.W. 401 (Supreme Court of Iowa, 1933)
Maasdam v. Kirkpatrick
243 N.W. 145 (Supreme Court of Iowa, 1932)
Board of Supervisors v. Paine
210 N.W. 929 (Supreme Court of Iowa, 1926)
Meyerholz v. Board of Supervisors
204 N.W. 452 (Supreme Court of Iowa, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
197 Iowa 351, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walker-v-joint-drainage-district-no-2-of-osceola-dickinson-counties-iowa-1924.