Hercules Manufacturing Co. v. Burch

16 N.W.2d 350, 235 Iowa 568, 1944 Iowa Sup. LEXIS 504
CourtSupreme Court of Iowa
DecidedNovember 14, 1944
DocketNo. 46485.
StatusPublished
Cited by7 cases

This text of 16 N.W.2d 350 (Hercules Manufacturing Co. v. Burch) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hercules Manufacturing Co. v. Burch, 16 N.W.2d 350, 235 Iowa 568, 1944 Iowa Sup. LEXIS 504 (iowa 1944).

Opinions

*569 Garfield, J.

On May 3, 1940, U. C. Burch contracted in writing to do grading for the state highway commission on a secondary road in Wayne county. At that time Maryland Casualty Company became surety on the contractor’s bond in the sum of $7,500. The contractor completed the work on September 7, 1940, and it was later accepted by the highway commission. On October 15, 1940, the Hercules Manufacturing Company filed its petition in equity against the highway commission, Burch, Maryland Casualty Company, Iowa State Bank and Trust Company of Fairfield — Burch’s assignee — and several parties who had furnished labor or material on the project, alleging that it furnished material to Burch of the value of $351.14 for which it was entitled to a claim against the retained percentage of the contract price.

The highway commission asked leave to pay the balance o£ the contract price, $1,806.59, into court to be disbursed according to the rights of the parties. Maryland Casualty Company filed answer and cross-petition alleging the execution of the contract and bond, the approval and acceptance of the work by the highway commission, that cross-petitioner had paid several claims for labor and material furnished on the project, which claims had been assigned to it, and that under the provisions o'f chapter 452, Code of Iowa, it is subrogated to the rights of these claimants to the funds in the hands of the highway commission. Iowa State Bank and Trust Company of Fairfield alleged in its answer that it was entitled to the balance of the contract price under a written assignment from Burch, the contractor, made on August 3, 1940, filed with the highway commission three days, later.

Upon the trial all facts were stipulated. It was agreed that: The contract, bond, and assignment to the Fairfield bank were executed as alleged; the work described in the contract was completed on September 7, 1940; the surety had paid claims for labor and material totaling $2,370.77 and taken assignments thereof; in August the highway commission estimated that work of the value of $8,219.20 had been completed; ten per cent of this amount, or $821.92, was retained by the commission, the balance of $7,397.28 was disbursed in two checks payable to Burch and the assignee bank; on November 2, 1940, the commission estimated the balance of the completed work was of the *570 value of $984.67, none of which had been disbursed; the assignment to the Fairfield bank was to secure a loan from it to Burch upon which there was due more than the sum retained by the highway commission.

Section 1109.06 of the specifications, part of the contract which in turn was incorporated in the bond, provides:

‘1 If the work extends over a period of more than one month the Contractor will receive monthly estimates based on the amount of work completed in an acceptable manner, and on material delivered. * # * Ten per cent of each estimate shall be deducted and held as a suspended payment until final acceptance of the entire contract. * * * 90 per cent of the contract sum for each item shall become due upon final acceptance of that item by the Commission. The amount deducted from the contract sum shall be retained by the Commission as a suspended payment until final acceptance by the Commission of all of the items included in the contract.”

The total contract price was $9,203.87. The highway commission was required by the contract to retain ten per cent of this amount, $920.39, until final acceptance of the work. It is conceded this ten per cent retention fund should be applied to the payment of claims and should go to the surety as assignee and subrogee of the claimants paid by it. The balance unpaid by the commission above the ten per cent, $886.20, is the amount in controversy. The lower court held that claimants for labor and material and the surety as their assignee and' subrogee had no right to any part of the contract price except the ten per cent retention fund and awarded the amount in controversy to the bank. The surety has appealed. We think the trial court was right.

The rights of the claimants for labor and material and oi appellant surety as their assignee and subrogee against the un paid fund are determined by the statutes in chapter 452, Code 1939. Southern Surety Co. v. Jenner Bros., 212 Iowa 1027 1036, 237 N. W. 500; Missouri Gravel Co. v. Federal Surety Co. 212 Iowa 1322, 1327, 237 N. W. 635; Independent Sch. Dist. v. Hall, 159 Iowa 607, 611, 140 N. W. 855. All sections of the chapter should -be considered in the light of their relation tfl *571 the whole. Ahrweiler v. Board of Supervisors, 226 Iowa 229, 231, 283 N. W. 889, 890; Eysink v. Board of Supervisors, 229 Iowa 1240, 1243, 296 N. W. 376, 378; 50 Am. Jur. 361, 362, section 358. When this is done it seems plain that the claimants and appellant, as their assignee and subrogee, could resort only to the ten per cent of the contract price which the highway commission was required to retain. The applicable statutes in chapter 452 are (all italics supplied) :

“Section 10304. Subcontractors on public improvements. The following provisions shall be held to be a part of every bond given for the performance of a contract for the construction of a public improvement * * *:
“1. ‘The principal and sureties on this bond hereby agree to pay * * # all just claims * * * for labor performed or materials furnished, in the performance of the contract on account of which this bond is given, when the same are not satisfied out of the portion of the contract price which the ^public corporation is required to retain until completion of the public improvement, but the principal and sureties shall not be liable m * * unless the claims of said claimants against said portion of the contract price shall have been established as provided by law.’ [Here the bond contains the exact language of section 10304.]
“Section 10310. Payments under public contracts. Payments made under contracts for the construction of public improvements, unless provided otherwise by law,, shall be made on the basis of monthly estimates of labor performed and material delivered; said payments to be made for not more than ninety percent of said estimates and to be so made that at least ten percent of the contract price will remain unpaid 'at the dale of the -•ompletion of the contract * * *.
“Section 10311. Inviolability and disposition of fund. * * * die retained percentage of the contract price, which in no case shall be less than ten percent, shall constitute a fund for the payment of claims for materials furnished and labor performed >n said improvement, and shall be held and disposed of by the mblic corporation as hereinafter provided.
“Section 10312. Retention of unpaid funds. Said fund hall be retained by the public corporation for a period of thirty lays after the completion and final acceptance of the improve *572 ment. If at the end of said thirty-day period claims are on file as herein provided the public corporation shall continue to retain from said unpaid funds

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lumberman's Wholesale Co. v. Ohio Farmers Insurance Co.
402 N.W.2d 413 (Supreme Court of Iowa, 1987)
First Federal State Bank v. Town of Malvern
270 N.W.2d 818 (Supreme Court of Iowa, 1978)
State Ex Rel. McElhinney v. All-Iowa Agricultural Ass'n
48 N.W.2d 281 (Supreme Court of Iowa, 1951)
Sinclair Refining Co. v. Burch
16 N.W.2d 359 (Supreme Court of Iowa, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
16 N.W.2d 350, 235 Iowa 568, 1944 Iowa Sup. LEXIS 504, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hercules-manufacturing-co-v-burch-iowa-1944.