Southern Surety Co. v. Jenner Bros.

237 N.W. 500, 212 Iowa 1027
CourtSupreme Court of Iowa
DecidedJune 20, 1931
DocketNo. 40827.
StatusPublished
Cited by8 cases

This text of 237 N.W. 500 (Southern Surety Co. v. Jenner Bros.) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Surety Co. v. Jenner Bros., 237 N.W. 500, 212 Iowa 1027 (iowa 1931).

Opinion

Kindig, J.

Jenner Bros., defendants and appellees, on October 15, 1928, entered into , a contract with the state highway commission for excavation and grading on a certain primary state highway in Warren County, designated, as Project P-568. Section 10300 of the 1927 Code provides:

“Contracts for the construction of a public improvement shall, when the contract price equals or exceeds one thousand dollars, be accompanied by a bond, with surety, conditioned for the faithful performance of the contract, and for the fulfillment of such other requirements as may- be provided by law. Such bond may also be required when the contract price does not equal said amount.”

The contract with Jenner Bros, was of the kind requiring a bond. Hence, on October 20, 1928, a statutory construction bond was executed by Jenner Bros., appellees, as principal, and the Southern Surety. Company, plaintiff and appellant, as surety. This bond was duly accepted and filed. Under section 10304 of the 1927 Code the bond, among others, shall contain these stipulations: .

“The following provisions shallbe held to be a part of every bond given for the performance of a contrdct for the construction of a public improvement, whether said provisions be inserted in such bond or not, to wit:
“1. ‘ The principal- and sureties on this bond hereby agree to pay to all persons, firms, or corporations having contracts directly with the principal or with subcontractors, all just claims due them for labor performed or materials furnished, in the performance of the contract on account of which this bond is given, when the same are not satisfied out of the portion of the contract price which the public corporation is required to retain until-completion of the public improvement, but the prin *1030 cipa! and sureties shall not be liable to said persons, firms, or corporations unless the claims of said claimants against said portion of the contract price shall have been established as provided by law. * * * * ”

, Thereafter, the appellee Jenner Bros, completed the construction under the aforesaid contract, and, on September 26, 1929, the work was accepted by the state highway commission. A controversy arises, however, so far as material here, over the liability of the appellant, as surety .on the contractor’s bond, for claims held by appellees-défendants, and arising out of latior performed and material furnished the appellee Jenner Bros, in the execution of the contract. Another dispute grows out of: First, a claim for interest on the claims established; and,.second, a deduction made from the demand of the.appellee, Sinclair Refining Company.

Claims were filed by the following appellees, in the amounts named below, with the officers, commission, or district court, at the -times- designated respectively: -

For labor: «1 a-2 ■ ■ ■ Io Claimant ' 4]g Date filed ■with State Auditor Date filed with Court Date filed with Highway Commission Date filed with County Auditor
Lulu May Kephart,' Disputed ¿O Ui CO Cí CJ 05 O rH co to co o rH
Ed'. Kephart, $78.20 tO Oi CO Q CJ 05 co to co ! — 1 O
Emil J.' Serk, Disputed H OD CO C5 <?q H
T. Anglin, $200.00 ¿O M CO 05 Cj! CO M to M to f" to co
Wm.. Hathaway, $544.18 ¿ M CO C5 N CO M to M to to CO
W::B. Lister, .$1,417.02 tO Oí CO C5 CJ M to M to to CO
Coy Bullard,. Disputed Ó O to ¿0 to
Evert F. Duncan, - Disputed ; 1 — * tO • ^ CO o H-1 to to to CO
Mrs. .Wm.. ■ Hathaway, $305.00 M tO ^ CO o to CO rH M to to CO
For Material: Dave Young, $332.38. • o CO rH <N G5> <M O rH to CO o T — |
Farmers-Eley. & . . Feed Co., . Disputed CO O to cn MO M-<01 to CO
*1031 McCoy Hdw. & Harness Co., Disputed 10-15-29 1-23-30
Gi. F. Carpenter, $115.00 10-16-29 10-16-29 1-21-30
Marshall’s Repair Shop, Disputed 11-1-29 11-2-29 1-8-30
Sinclair Refining Company Disputed 10-1-29 3-12-30

For Rentals for use of machinery:

Paul T. Pfeifer, Disputed . 12-16-29 12-16-29 1-7-30 12-16-29

There is now held by the state highway commission from the contract price due the appellee, Jenner Bros., $9,201.12. Of that amount, the sub-final estimate is $3,427.15, and the final estimate. $5,773.97.

Many objections were made by appellant to the claims filed.’ Among these objections is the one that the claims were not filed with the state.auditor, or in a proper action pending in the district court, within thirty days, as required by law.

.After a hearing on the merits, the district court disallowed the following claims: McCoy Hardware & Harness Company, Coy Bullard, and Paul T. Pfeifer. Allowance's, however, were made on the other claims above named in the amounts set forth after the name of each claimant, respectively, as follows':

Labor:
Lulu May Kephart, $486.75
Mrs. William Hathaway, $305.00
Ed. Kephart, $78.20 '
Administrator of Emil J. Serk Estate, $861.20
T. Anglin, $200:00
Wm. Hathaway, $544.18'
W. B. Lister, $1,417.02
Everett F. Duncan, $400.00
Material:
David Young, $332.38
Farmers Elevator Company, $213.24
Gr. F. Carpenter, $115.00
Marshall’s Repair Shop, $7.50
Sinclair Refining Company, $5,758.76

*1032 Thus the total claims allowed for labor and material were $10,719.23. In addition to the foregoing, the district court allowed attorneys fees, as contemplated by section 10318 of the 1927 Code, to the following attorneys in the amounts set opposite the names of each:

Watson & Watson, $350.00
M. T. Wells, $75.00
Maxwell & Ryan, $450.00
W. M. Wilson, $25.00

The court costs (without the attorney fees).in the district court, when judgment was entered, amounted to $300.36. Consequently the total costs with attorney fees at that time were $1,200.36. Thereby, the aggregate claims allowed for labor and material, together with the costs aforesaid, amount in all to $11,919.58.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northwest Limestone Co. v. State Department of Transportation
499 N.W.2d 8 (Supreme Court of Iowa, 1993)
Lumberman's Wholesale Co. v. Ohio Farmers Insurance Co.
402 N.W.2d 413 (Supreme Court of Iowa, 1987)
Economy Forms Corp. v. City of Cedar Rapids
340 N.W.2d 259 (Supreme Court of Iowa, 1983)
Rohlin Const. Co., Inc. v. Lakes, Inc.
252 N.W.2d 403 (Supreme Court of Iowa, 1977)
State ex rel. Hanrahan v. Miller
96 N.W.2d 474 (Supreme Court of Iowa, 1959)
Hercules Manufacturing Co. v. Burch
16 N.W.2d 350 (Supreme Court of Iowa, 1944)
Cities Service Oil Co. v. Longerbone
6 N.W.2d 325 (Supreme Court of Iowa, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
237 N.W. 500, 212 Iowa 1027, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-surety-co-v-jenner-bros-iowa-1931.